Notice2025-22342

International Falls Power Company; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
December 9, 2025

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 90 Issue 234 (Tuesday, December 9, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 234 (Tuesday, December 9, 2025)]
[Notices]
[Pages 57041-57042]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-22342]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 5223-040]


International Falls Power Company; Notice of Application Tendered 
for Filing With the Commission and Soliciting Additional Study Requests 
and Establishing Procedural Schedule for Relicensing and a Deadline for 
Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.

    a. Type of Application: New Major License.
    b. Project No.: 5223-040.
    c. Date filed: November 24, 2025.
    d. Applicant: International Falls Power Company.
    e. Name of Project: International Falls Hydroelectric Project 
(project).
    f. Location: The project is located on the Rainy River in 
Koochiching and St. Louis Counties, Minnesota.

[[Page 57042]]

    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Mr. Robert Pflederer Assistant 
Superintendent--Power/Recovery PCA--International Falls, MN, 400 2nd 
Street International Falls, MN 56649; telephone: 218-324-3931; or 
email: <a href="/cdn-cgi/l/email-protection#ecbe838e899e98bc8a808988899e899eac9c8d8f878d8b85828b8f839e9cc28f8381"><span class="__cf_email__" data-cfemail="94c6fbf6f1e6e0c4f2f8f1f0f1e6f1e6d4e4f5f7fff5f3fdfaf3f7fbe6e4baf7fbf9">[email&#160;protected]</span></a>.
    i. FERC Contact: Colleen Corballis at (202) 502-8598; or email at 
<a href="/cdn-cgi/l/email-protection#31525e5d5d54545f1f525e4353505d5d584271575443521f565e47"><span class="__cf_email__" data-cfemail="a6c5c9cacac3c3c888c5c9d4c4c7cacacfd5e6c0c3d4c588c1c9d0">[email&#160;protected]</span></a>.
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See, 94 FERC ] 
61,076 (2001).
    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and serve a copy of 
the request on the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: on or before 5:00 p.m. Eastern Time on 
January 23, 2026.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at <a href="http://www.ferc.gov/docs-filing/efiling.asp">http://www.ferc.gov/docs-filing/efiling.asp</a>. Commenters can submit brief comments up to 10,000 
characters, without prior registration, using the eComment system at 
<a href="http://www.ferc.gov/docs-filing/ecomment.asp">http://www.ferc.gov/docs-filing/ecomment.asp</a>. For assistance, please 
contact FERC Online Support at <a href="/cdn-cgi/l/email-protection#e9afacbbaaa6878580878cba9c9999869b9da98f8c9b8ac78e869f"><span class="__cf_email__" data-cfemail="54121106171b3a383d3a31072124243b262014323126377a333b22">[email&#160;protected]</span></a>, (866) 208-
3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic 
filing, please send a paper copy via U.S. Postal Service to: Debbie-
Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via 
any other carrier must be addressed to: Debbie Anne A. Reese, 
Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, 
Rockville, Maryland 20852. The first page of any filing should include 
docket number P-5223-040.
    m. The application is not ready for environmental analysis at this 
time.
    n. The project consists of: (1) a 48,296.3-acre impoundment (Rainy 
Lake) having a storage capacity of 1,545,482 acre-feet at elevation 
1,108.1 feet mean sea level; (2) a 170-foot-long masonry overflow 
gravity section; (3) a 215-foot-long powerhouse integral with the dam 
containing seven turbine-generator units with a total installed 
capacity of 14.45 megawatts; (4) 6.9-kilovolt generator leads 
connecting the project to the non-project International Falls Mill; and 
(5) appurtenant facilities.
    The project is operated pursuant to the orders of the International 
Joint Commission, established by the Boundary Waters Treaty of 1909 
between the United States of America (U.S.A) and Canada. The project 
dam spans between the U.S.A. and Canada, but the project boundary only 
encompasses the U.S.A. side of the dam.
    o. In addition to publishing the full text of this notice in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this notice, as well 
as other documents in the proceeding (e.g., license application) via 
the internet through the Commission's Home Page (<a href="http://www.ferc.gov">http://www.ferc.gov</a>) 
using the ``eLibrary'' link. Enter the docket number excluding the last 
three digits in the docket number field to access the document (P-
5223). For assistance, contact FERC at <a href="/cdn-cgi/l/email-protection#97d1d2c5d4d8f9fbfef9f2c4e2e7e7f8e5e3d7f1f2e5f4b9f0f8e1"><span class="__cf_email__" data-cfemail="6e282b3c2d21000207000b3d1b1e1e011c1a2e080b1c0d40090118">[email&#160;protected]</span></a>, 
(866) 208-3676 (toll free), or (202) 502-8659 (TTY).
    You may also register online at <a href="https://ferconline.ferc.gov/FERCOnline.aspx">https://ferconline.ferc.gov/FERCOnline.aspx</a> to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    p. For public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, contact the Office 
of Public Participation at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#410e111101272433226f262e37"><span class="__cf_email__" data-cfemail="78372828381e1d0a1b561f170e">[email&#160;protected]</span></a>.
    q. Procedural schedule and final amendments: The application will 
be processed according to the following preliminary schedule. Revisions 
to the schedule will be made as appropriate.

------------------------------------------------------------------------
                Milestone                           Target date
------------------------------------------------------------------------
Issue Deficiency Letter and Request        March 2026.
 Additional Information.
Issue Acceptance Letter and Notice.......  June 2026.
Issue Scoping Notice.....................  June 2026.
Scoping Comments due.....................  July 2026.
Issue Ready for Environmental Analysis     August 2026.
 Notice.
------------------------------------------------------------------------

    r. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

(Authority: 18 CFR 2.1)

    Dated: December 4, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-22342 Filed 12-8-25; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on December 9, 2025.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.