Notice2025-18831
Actions Taken at the September 24, 2025 Meeting
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
September 29, 2025
Issuing agencies
Susquehanna River Basin Commission
Abstract
As part of its regular business meeting held on September 24, 2025 in Harrisburg, Pennsylvania, the Commission approved the applications of certain water resources projects and took additional actions, as set forth in the SUPPLEMENTARY INFORMATION below.
Full Text
<html>
<head>
<title>Federal Register, Volume 90 Issue 186 (Monday, September 29, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 186 (Monday, September 29, 2025)]
[Notices]
[Pages 46729-46730]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-18831]
=======================================================================
-----------------------------------------------------------------------
SUSQUEHANNA RIVER BASIN COMMISSION
Actions Taken at the September 24, 2025 Meeting
AGENCY: Susquehanna River Basin Commission.
ACTION: Notice.
-----------------------------------------------------------------------
SUMMARY: As part of its regular business meeting held on September 24,
2025 in Harrisburg, Pennsylvania, the Commission approved the
applications of certain water resources projects and took additional
actions, as set forth in the SUPPLEMENTARY INFORMATION below.
DATES: September 25, 2025.
ADDRESSES: Susquehanna River Basin Commission, 4423 N Front Street,
Harrisburg, PA 17110-1788.
FOR FURTHER INFORMATION CONTACT: Jason E. Oyler, General Counsel and
Secretary, telephone: (717) 238-0423, ext. 1312, fax: (717) 238-2436;
email: <a href="/cdn-cgi/l/email-protection#660c091f0a0314261514040548010910"><span class="__cf_email__" data-cfemail="dbb1b4a2b7bea99ba8a9b9b8f5bcb4ad">[email protected]</span></a>. Regular mail inquiries may be sent to the above
address. See also the Commission website at <a href="http://www.srbc.gov">www.srbc.gov</a>.
SUPPLEMENTARY INFORMATION: The Commission took the following actions
at its September 24, 2025 business meeting: (1) adopted the preliminary
Fiscal Year 2027 budget; (2) unanimously adopted the member
jurisdiction allocation requests for Fiscal Year 2027; (3) approved a
grant amendment with the PA Department of Environmental Protection; (4)
approved two settlements of regulatory violations; and (5) approved 21
regulatory program projects and tabled one project as listed below.
Project Applications Approved
1. Project Sponsor and Facility: Blackhill Energy LLC (Chemung
River), Athens Township, Bradford County, Pa. Application for renewal
with modification of surface water withdrawal of up to 1.999 mgd (peak
day) (Docket No. 20220903).
2. Project Sponsor: Calpine Mid Merit, LLC. Project Facility: York
Energy Center 1, Peach Bottom Township, York County, Pa. Application
for consumptive use of up to 4.900 mgd (peak day).
3. Project Sponsor: Calpine Mid Merit, LLC. Project Facility: York
Energy Center 2 (Susquehanna River), Peach Bottom Township, York
County, and Drumore Township, Lancaster County, Pa. Modification to
surface water withdrawal of up to 19.010 mgd (peak day) and consumptive
use of up to 5.800 mgd (peak day) (Docket No. 20060308).
4. Project Sponsor and Facility: City of Lock Haven, Wayne
Township, Clinton County, Pa. Applications for groundwater withdrawals
(30-day averages) of up to 0.720 mgd from the Matz Well and 0.720 mgd
from the Quaker Hill Well.
5. Project Sponsor and Facility: Coterra Energy Inc., Eaton
Township, Wyoming County, Pa. Application for renewal of groundwater
withdrawals of up to 0.864 mgd (30-day average) from the Hatchery
Wellfield (Wells 1, 2, and 3) (Docket No. 20200903).
6. Project Sponsor and Facility: Expand Operating LLC (Susquehanna
River), Standing Stone Township, Bradford County, Pa. Application for
surface water withdrawal of up to 4.000 mgd (peak day).
7. Project Sponsor and Facility: Expand Operating LLC (Susquehanna
River), Wilmot Township, Bradford County, Pa. Application for renewal
of surface water withdrawal of up to 3.000 mgd (peak day) (Docket No.
20200905).
8. Project Sponsor and Facility: Expand Operating LLC (Susquehanna
River), Windham Township, Wyoming County, Pa. Application for renewal
of surface water withdrawal of up to 3.000 mgd (peak day) (Docket No.
20200906).
9. Project Sponsor and Facility: Expand Operating LLC (Wyalusing
Creek), Wyalusing Township, Bradford County, Pa. Application for
renewal of surface water withdrawal of up to 3.000 mgd (peak day)
(Docket No. 20200907).
10. Project Sponsor: Graymont (PA) Inc. Project Facility: Pleasant
Gap Facility, Spring Township, Centre County, Pa. Application for
renewal of groundwater withdrawal of up to 0.050 mgd (30-day average)
from the Plant Make-Up Well (Docket No. 20100307).
11. Project Sponsor and Facility: Green Leaf Water LLC (Lycoming
Creek), Lewis Township, Lycoming County, Pa. Application for renewal of
surface water withdrawal of up to 0.900 mgd (peak day) (Docket No.
20200908).
12. Project Sponsor and Facility: Greylock Production, LLC (Pine
Creek), Gaines Township, Tioga County, Pa. Application for surface
water withdrawal of up to 3.000 mgd (peak day).
13. Project Sponsor and Facility: Hanover Foods Corporation, Penn
and Heidelberg Townships, York County, Pa. Applications for renewal of
consumptive use of up to 0.499 mgd (peak day) and groundwater
withdrawals (30-day averages) of up to 0.072 mgd from Well PW-3, 0.144
mgd from Well PW-4, and 0.231 mgd from Well PW-5 (Docket Nos. 19980503
and 19991104).
14. Project Sponsor and Facility: Hegins-Hubley Authority, Hegins
Township, Schuylkill County, Pa. Application for renewal of groundwater
withdrawal of up to 0.216 mgd (30-day average) from Well 6 (Docket No.
19981204).
15. Project Sponsor: Hillandale-Gettysburg, L.P. Project Facility:
Site 3, Tyrone Township, Adams County, Pa. Applications for groundwater
withdrawals (30-day averages) of up to 0.019 mgd from Well 1, 0.035 mgd
from Well 2, 0.035 mgd from Well 3, and 0.060 mgd from Well 4.
16. Project Sponsor and Facility: Lykens Borough Authority,
Wiconisco Township, Dauphin County, Pa. Applications for groundwater
withdrawals (30-day averages) of up to 0.393 mgd from Well 2 and 0.035
mgd from Well 3.
17. Project Sponsor and Facility: Pennsylvania General Energy
Company, L.L.C. (Muncy Creek), Shrewsbury Township, Lycoming County,
Pa. Application for surface water withdrawal of up to 1.500 mgd (peak
day).
18. Project Sponsor and Facility: Repsol Oil & Gas USA, LLC
(Susquehanna River), Sheshequin Township, Bradford County, Pa.
Application for renewal of surface water withdrawal of up to 1.500 mgd
(peak day) (Docket No. 20200913).
[[Page 46730]]
19. Project Sponsor and Facility: Sabre Energy Development LLC
(Muncy Creek), Muncy Creek Township, Lycoming County, Pa. Application
for surface water withdrawal of up to 1.700 mgd (peak day).
20. Project Sponsor and Facility: Sabre Energy Development LLC
(Muncy Creek), Penn Township, Lycoming County, Pa. Application for
surface water withdrawal of up to 1.700 mgd (peak day).
21. Project Sponsor: York Haven Power Company, LLC. Project
Facility: York Haven Hydroelectric Project, Londonderry Township,
Dauphin County; Conoy Township, Lancaster County; and York Haven
Borough and Newberry Township, York County, Pa., Modification to the
design of the nature-like fishway (Docket No. 20200308).
Project Tabled
22. Project Sponsor: Veolia Water Pennsylvania, Inc. Project
Facility: Newberry Operation, Newberry Township, York County, Pa.
Application for renewal of groundwater withdrawal of up to 0.121 mgd
(30-day average) from the Paddletown Well (Docket No. 20090917).
Authority: Public Law 91-575, 84 Stat. 1509 et seq., 18 CFR parts
806, 807, and 808.
Dated: September 25, 2025.
Jason E. Oyler,
General Counsel and Secretary to the Commission.
[FR Doc. 2025-18831 Filed 9-26-25; 8:45 am]
BILLING CODE 7040-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on September 29, 2025.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.