Abstract
In accordance with the Paperwork Reduction Act of 1995, and the Office of Management and Budget (OMB) regulations, GSA invites the public to comment on an extension of a previously approved information collection requirement regarding OMB Control No. 3090-0320 Construction Manager as Constructor (CMc).
Full Text
<html>
<head>
<title>Federal Register, Volume 90 Issue 167 (Tuesday, September 2, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 167 (Tuesday, September 2, 2025)]
[Notices]
[Pages 42410-42411]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-16729]
=======================================================================
-----------------------------------------------------------------------
GENERAL SERVICES ADMINISTRATION
[OMB Control No. 3090-0320; Docket No. 2025-0001; Sequence No. 18]
Information Collection; General Services Administration
Acquisition Regulation; Construction Manager as Constructor (CMc)
AGENCY: Office of Acquisition Policy, General Services Administration
(GSA).
ACTION: Notice; request for comments.
-----------------------------------------------------------------------
SUMMARY: In accordance with the Paperwork Reduction Act of 1995, and
the Office of Management and Budget (OMB) regulations, GSA invites the
public to comment on an extension of a previously approved information
collection requirement regarding OMB Control No. 3090-0320 Construction
Manager as Constructor (CMc).
DATES: Submit comments on or before November 3, 2025.
ADDRESSES: Submit comments on this information collection to <a href="https://www.regulations.gov">https://www.regulations.gov</a>. Submit comments via the Federal eRulemaking portal
by searching for ``Information Collection 3090-0320''. Select the link
``Comment Now'' that corresponds with Information Collection 3090-0320.
Follow the instructions provided at the ``Comment Now'' screen. Please
include your name, company name (if any), and ``Information Collection
3090-0320'' on your attached document.
Instructions: Please submit comments only and cite ``Information
Collection 3090-0320'' in all correspondence related to this
collection. Comments received generally will be posted without change
to <a href="http://regulations.gov">regulations.gov</a>, including any personal and/or business confidential
information provided. To confirm receipt of your comment(s), please
check <a href="http://regulations.gov">regulations.gov</a> approximately two-to-three days after submission
to verify posting.
FOR FURTHER INFORMATION CONTACT: Ms. Amy Lara, 816-589-3783, General
Services Acquisition Policy Division, by email at <a href="/cdn-cgi/l/email-protection#5136223023213e3d383228113622307f363e27"><span class="__cf_email__" data-cfemail="81e6f2e0f3f1eeede8e2f8c1e6f2e0afe6eef7">[email protected]</span></a>.
SUPPLEMENTARY INFORMATION:
A. Purpose
The General Services Administration Acquisition Regulation (GSAR)
552.236-79, Construction-Contractor-as-Constructor, requires the
contractor to submit a proposal to establish the final estimated cost
of the work, to convert the contract to a firm-fixed-price, and to
determine the final settlement for construction-manager-as-constructor
(CMc) projects.
The CMc refers to a project management and contracting technique
that is one of three predominant methods used for acquiring
construction services by GSA. The other two methods are design-bid-
build and design-build. The private sector commonly uses a similar
construction project delivery method, which allows for early industry
engagement by the construction contractor to enable reduced cost
growth, reduced schedule growth, and administrative savings.
The information is used by contracting officers to evaluate
proposals and negotiate contract modifications during contract
administration. This collection supports the Government's shift toward
category management by providing a more robust playbook framework for
efficient procurement of construction services.
B. Annual Reporting Burden
Total public reporting burden for this collection of information is
estimated to average 400 total hours ($33,300) annually, including the
time for reviewing instructions, searching existing data sources,
gathering, and maintaining the data needed, and completing and
reviewing the collection of information. The estimated burden hours to
the public for the below clauses are as follows:
GSAR 552.236-79, Construction-Contractor-as-Constructor, requires
the contractor to submit a proposal to establish the final estimated
cost of the work, to convert the contract to a firm-fixed-price, and to
determine the final settlement.
Respondents: 10.
Responses per Respondent: 1.
Total Annual Responses: 10.
Hours per Response: 40.
Total Response Burden Hours: 400.
Cost per Hour: $83.25.
Estimated Cost Burden to the Public: $33,300.
GSAR 552.236-80, Accounting Records, contains a recordkeeping
requirement that is subject to the Paperwork Reduction Act (44 U.S.C.
3501, et seq.). The clause requires the contractor to keep all relevant
[[Page 42411]]
documents for a period of three years after the final payment. However,
the clause does not add burden to what is already estimated for the
existing FAR clause at 52.215-2, Audit and Records by a previous
information collection (see OMB Control Number 9000-0034).
C. Public Comments
Public comments are particularly invited on: Whether this
collection of information is necessary; whether it will have practical
utility; whether our estimate of the public burden of this collection
of information is accurate, and based on valid assumptions and
methodology; ways to enhance the quality, utility, and clarity of the
information to be collected; and ways in which we can minimize the
burden of the collection of information on those who are to respond,
through the use of appropriate technological collection techniques or
other forms of information technology.
Jeffrey A. Koses,
Senior Procurement Executive, Office of Acquisition Policy, Office of
Government-wide Policy.
[FR Doc. 2025-16729 Filed 8-29-25; 8:45 am]
BILLING CODE P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on September 2, 2025.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.