Notice2025-16565

Sugar River Hydro II, LLC; Notice of Intent To Prepare an Environmental Assessment

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
August 28, 2025

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 90 Issue 165 (Thursday, August 28, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 165 (Thursday, August 28, 2025)]
[Notices]
[Pages 42001-42002]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-16565]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 10934-035]


Sugar River Hydro II, LLC; Notice of Intent To Prepare an 
Environmental Assessment

    On June 22, 2023, and supplemented on January 24, 2024, and June 
20, 2025, Sugar River Hydro II, LLC, licensee, filed an application for 
surrender of its license for the Sugar River II Hydroelectric Project 
No. 10934. The project is located on the Sugar River in Sullivan 
County, New Hampshire. The project does not occupy federal lands.
    To surrender the project, the licensee proposes to disconnect all 
generator leads, remove all transformers and other project electrical 
equipment, remove all hydraulic and governor fluids and reservoirs, 
remove project related operating equipment and monitors, such as 
impoundment sensors, from the dam, and secure the powerhouse. 
Additionally, the licensee plans to close the penstock at its intake, 
and intends to work with the U.S. Fish and Wildlife Service and the New 
Hampshire Department of Environmental Services Dam Bureau to develop 
the formal penstock closure plan. The dam and its gates would remain in 
place, including the emergency backup system with a dedicated 
generator. The licensee does not anticipate any new ground disturbance 
activity while securing the powerhouse, and closing the penstock 
intake.
    On July 2, 2025, the Commission issued a public notice for the 
surrender application. The public comment period closed on August 1, 
2025. On July 31, 2025, the Connecticut River Conservancy filed 
comments to express

[[Page 42002]]

their support for the surrender of the license.
    This notice identifies Commission staff's intention to prepare an 
environmental assessment (EA) under the National Environmental Policy 
Act (42 U.S.C. 4321 et seq) for the project.\1\ Commission staff plans 
to issue an EA by March 2, 2026. Revisions to the schedule may be made 
as appropriate. The EA will be issued for a 30-day comment period. All 
comments filed on the EA will be reviewed by staff and considered in 
the Commission's final decision on the proceeding.
---------------------------------------------------------------------------

    \1\ The unique identification number for documents relating to 
this environmental review is EAXX-019-20-000-1756114888.
---------------------------------------------------------------------------

    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
community organizations, Tribal members, and others to access publicly 
available information and navigate Commission processes. For public 
inquiries and assistance with making filings such as interventions, 
comments, or requests for rehearing, the public is encouraged to 
contact OPP at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#28677878684e4d5a4b064f475e"><span class="__cf_email__" data-cfemail="ce819e9e8ea8abbcade0a9a1b8">[email&#160;protected]</span></a>.
    Any questions regarding this notice may be directed to Aneela 
Mousam, (202) 502-8357 or <a href="/cdn-cgi/l/email-protection#65040b000009044b080a1016040825030017064b020a13"><span class="__cf_email__" data-cfemail="46272823232a27682b293335272b062023342568212930">[email&#160;protected]</span></a>.

    Dated: August 25, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-16565 Filed 8-27-25; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on August 28, 2025.