Northwest Pipeline, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Wild Trail Project
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
July 14, 2025
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 90 Issue 132 (Monday, July 14, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 132 (Monday, July 14, 2025)]
[Notices]
[Pages 31197-31199]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-13126]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP25-497-000]
Northwest Pipeline, LLC; Notice of Scoping Period Requesting
Comments on Environmental Issues for the Proposed Wild Trail Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental document that will discuss
the environmental impacts of the Wild Trail Project involving
construction and operation of facilities by Northwest Pipeline, LLC
(Northwest) in Dagget County, Utah. The Commission will use this
environmental document in its decision-making process to determine
whether the project is in the public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies regarding the project. As part of the National Environmental
Policy Act (NEPA) review process, the Commission takes into account
concerns the public may have about proposals and the environmental
impacts that could result from its action whenever it considers the
issuance of a Certificate of Public Convenience and Necessity. This
gathering of public input is referred to as ``scoping.'' The main goal
of the scoping process is to focus the analysis in the environmental
document on the important environmental issues. Additional information
about the Commission's NEPA process is described below in the NEPA
Process and Environmental Document section of this notice.
By this notice, the Commission requests public comments on the
scope of issues to address in the environmental document. To ensure
that your comments are timely and properly recorded, please submit your
comments so that the Commission receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on August 8, 2025. Comments may be
submitted in written form. Further details on how to submit comments
are provided in the Public Participation section of this notice.
Your comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. Your input will help the Commission staff determine what
issues they need to evaluate in the environmental document. Commission
staff will consider all written comments during the preparation of the
environmental document.
If you submitted comments on this project to the Commission before
the opening of this docket on May 21, 2025, you will need to file those
comments in Docket No. CP25-497-000 to ensure they are considered as
part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
Northwest provided landowners with a fact sheet prepared by the
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do
I Need To Know?'' which addresses typically asked questions, including
the use of eminent domain and how to participate in the Commission's
proceedings. This fact sheet along with other landowner topics of
interest are available for viewing on the FERC website (<a href="http://www.ferc.gov">www.ferc.gov</a>)
under the Natural Gas, Landowner Topics link.
Public Participation
There are three methods you can use to submit your comments to the
Commission. Please carefully follow these instructions so that your
comments are properly recorded. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or <a href="/cdn-cgi/l/email-protection#41072433220e2f2d282f24123431312e333501272433226f262e37"><span class="__cf_email__" data-cfemail="5c1a392e3f1332303532390f292c2c332e281c3a392e3f723b332a">[email protected]</span></a>.
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>)
under the link to FERC Online. Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>)
under the link to FERC Online. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; a comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (CP25-
497-000) on your letter. Submissions sent via the U.S. Postal Service
must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC
20426. Submissions sent via any other carrier must be addressed to:
Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville, MD 20852.
Additionally, the Commission offers a free service called
eSubscription which makes it easy to stay informed of all issuances and
submittals regarding the dockets/projects to which you subscribe. These
instant email notifications are the fastest way to receive notification
and provide a link to the document files which can reduce the amount of
time you spend researching proceedings. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
community organizations, Tribal members and others, access publicly
available information and navigate Commission processes. For public
inquiries and assistance with making filings such as interventions,
comments, or requests for rehearing, the public is encouraged to
contact OPP at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#baf5eaeafadcdfc8d994ddd5cc"><span class="__cf_email__" data-cfemail="4e011e1e0e282b3c2d60292138">[email protected]</span></a>.
Summary of the Proposed Project
Northwest proposes to construct and operate the Daggett Compressor
Station, adjacent to the existing Clay Basin Meter Station in Daggett
County, Utah. The Wild Trail Project would provide an additional 57,955
dekatherms a day of northbound firm transportation service from the
existing Wild Horse
[[Page 31198]]
Receipt Point to the Kern River Muddy Creek Delivery Point.
The Wild Trail Project would consist of the following facilities:
<bullet> the greenfield Daggett Compressor Station, adjacent to
existing Clay Basin Meter Station. The compressor station would consist
of one unit scrubber, a station power distribution building, unitized
power buildings, 500-kilowatt emergency generator, oily water sump tank
and pump, engine/compressor lube oil storage, hydrocarbon liquid
storage, and a new instrument air package with receiver and other
items;
<bullet> the addition of one low nitrogen oxides (NO<INF>X</INF>)-
emitting gas-fired turbine driven compressor unit with 11,110 nominal
horsepower;
<bullet> installation of 24-inch-diameter suction and discharge
yard piping to interconnect the Daggett Compressor Station to
Northwest's existing 26-inch-diameter Northwest Pipeline;
<bullet> installation of a 140-foot communication tower; and
<bullet> minor modifications to the existing Clay Basin Meter
Station.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
<a href="http://www.ferc.gov">www.ferc.gov</a> using the link called ``eLibrary.'' For instructions on
connecting to eLibrary, refer to the last page of this notice. For
assistance, contact FERC at <a href="/cdn-cgi/l/email-protection" class="__cf_email__" data-cfemail="83c5c6d1c0ccedefeaede6d0f6f3f3ecf1f7c3e5e6f1e0ade4ecf5">[email protected]</a> or call toll
free, (886) 208-3676 or TTY (202) 502-8659.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would occur immediately
adjacent to the existing Clay Basin Meter Station and would require
approximately 20.25 acres of land. The 20.25 acres includes 15.86 acres
that encompasses the proposed Daggett Compressor Station located on
land managed by the U.S. Bureau of Land Management, as well as
approximately 4.39 acres of temporary workspace located within the
Ashley National Forest, managed by the U.S. Forest Service. Following
construction, the 4.39 acres of U.S. Forest Service land would be
restored to pre-construction conditions, as well as the 9.09 acres of
construction workspace areas, leaving 6.77 acres of land converted to
natural gas use for the Daggett Compressor Station.
NEPA Process and the Environmental Document
Any environmental document issued by the Commission will discuss
impacts that could occur as a result of the construction and operation
of the proposed project under the relevant general resource areas:
<bullet> geology and soils;
<bullet> water resources and wetlands;
<bullet> vegetation and wildlife;
<bullet> threatened and endangered species;
<bullet> cultural resources;
<bullet> land use;
<bullet> socioeconomics;
<bullet> air quality and noise; and
<bullet> reliability and safety.
Commission staff will also evaluate reasonable alternatives to the
proposed project or portions of the project and make recommendations on
how to lessen or avoid impacts on the various resource areas. Your
comments will help Commission staff identify and focus on the issues
that might have an effect on the human environment and potentially
eliminate others from further study and discussion in the environmental
document.
Following this scoping period, Commission staff will determine
whether to prepare an Environmental Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the EIS will present Commission
staff's independent analysis of the issues. If Commission staff
prepares an EA, a Notice of Schedule for the Preparation of an
Environmental Assessment will be issued. The EA may be issued for an
allotted public comment period. The Commission would consider timely
comments on the EA before making its decision regarding the proposed
project. If Commission staff prepares an EIS, a Notice of Intent to
Prepare an EIS/Notice of Schedule will be issued, which will open up an
additional comment period. Staff will then prepare a draft EIS which
will be issued for public comment. Commission staff will consider all
timely comments received during the comment period on the draft EIS and
revise the document, as necessary, before issuing a final EIS. Any EA
or draft and final EIS will be available in electronic format in the
public record through eLibrary \2\ and the Commission's natural gas
environmental documents web page (<a href="https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents">https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents</a>). If eSubscribed, you
will receive instant email notification when the environmental document
is issued.
---------------------------------------------------------------------------
\2\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues of this project to formally cooperate in the
preparation of the environmental document.\3\ Agencies that would like
to request cooperating agency status should follow the instructions for
filing comments provided under the Public Participation section of this
notice. Currently, the BLM and U.S. Forest Service have agreed to
participate as cooperating agencies in the preparation of the
environmental document to satisfy their NEPA responsibilities related
to this project. The BLM states that it will use the EA to disclose and
analyze the environmental consequences of the proposed action to
support consideration of issuing of a right-of-way for the Wild Trail
Compressor Facility as proposed by Northwest. The purpose and need for
BLM action under Section 28 of the Mineral Leasing Act of 1920, as
amended (30 United States Code 195), is to review and provide a
decision for the right-of-way application.
---------------------------------------------------------------------------
\3\ Cooperating agency responsibilities are addressed in Section
107(a)(3) of NEPA (42 U.S.C. 4336(a)(3)).
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the Utah State Historic Preservation Office, and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the project's potential effects on
historic properties.\4\ The environmental document for this project
will document findings on the impacts on historic properties and
summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project and includes a mailing address with their
comments.
[[Page 31199]]
Commission staff will update the environmental mailing list as the
analysis proceeds to ensure that Commission notices related to this
environmental review are sent to all individuals, organizations, and
government entities interested in and/or potentially affected by the
proposed project.
If you need to make changes to your name/address, or if you would
like to remove your name from the mailing list, please complete one of
the following steps:
(1) Send an email to <a href="/cdn-cgi/l/email-protection#7334120023011c1916100732171701160000301b121d141633151601105d141c05"><span class="__cf_email__" data-cfemail="b5f2d4c6e5c7dadfd0d6c1f4d1d1c7d0c6c6f6ddd4dbd2d0f5d3d0c7d69bd2dac3">[email protected]</span></a> stating your
request. You must include the docket number CP25-497-000 in your
request. If you are requesting a change to your address, please be sure
to include your name and the correct address. If you are requesting to
delete your address from the mailing list, please include your name and
address as it appeared on this notice. This email address is unable to
accept comments.
OR
(2) Return the attached ``Mailing List Update Form'' (appendix 2).
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website at <a href="http://www.ferc.gov">www.ferc.gov</a> using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number
in the ``Docket Number'' field. Be sure you have selected an
appropriate date range. For assistance, please contact FERC Online
Support at <a href="/cdn-cgi/l/email-protection#84c2e1f6e7cbeae8edeae1d7f1f4f4ebf6f0c4e2e1f6e7aae3ebf2"><span class="__cf_email__" data-cfemail="5e183b2c3d11303237303b0d2b2e2e312c2a1e383b2c3d70393128">[email protected]</span></a> or (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of all formal documents issued by the Commission, such as orders,
notices, and rulemakings.
Public sessions or site visits will be posted on the Commission's
calendar located at <a href="https://www.ferc.gov/news-events/events">https://www.ferc.gov/news-events/events</a> along with
other related information.
Dated: July 9, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-13126 Filed 7-11-25; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on July 14, 2025.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.