Notice2025-12655

Texas Eastern Transmission, LP; Notice of Schedule for the Preparation of an Environmental Assessment for the Longwall Mining Panel M1 Project

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
July 8, 2025

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 90 Issue 128 (Tuesday, July 8, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 128 (Tuesday, July 8, 2025)]
[Notices]
[Pages 30061-30062]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-12655]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP25-379-000]


Texas Eastern Transmission, LP; Notice of Schedule for the 
Preparation of an Environmental Assessment for the Longwall Mining 
Panel M1 Project

    On April 30, 2025, Texas Eastern Transmission, LP (Texas Eastern) 
filed an application in Docket No. CP25-379-000 requesting a 
Certificate of Public Convenience and Necessity pursuant to Section 
7(c) of the Natural Gas Act to excavate, elevate, replace, reroute, 
construct, and operate certain natural gas pipeline facilities. The 
proposed project is known as the Longwall Mining Panel M1 Project 
(Project) and would allow for the safe and efficient operation of Texas 
Eastern's natural gas transportation system in Greene County, 
Pennsylvania during sub-surface longwall mining activities.
    On May 14, 2025, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
environmental document for the Project.
    This notice identifies Commission staff's intention to prepare an 
environmental assessment (EA) for the Project and the planned schedule 
for the completion of the environmental review.\1\ The EA will be 
issued for a 30-day comment period.
---------------------------------------------------------------------------

    \1\ For tracking purposes under the National Environmental 
Policy Act, the unique identification number for documents relating 
to this environmental review is EA-019-20-000-1748513599.

---------------------------------------------------------------------------

[[Page 30062]]

Schedule for Environmental Review

Issuance of EA October 10, 2025
90-day Federal Authorization Decision Deadline \2\ January 8, 2026
---------------------------------------------------------------------------

    \2\ The Commission's deadline applies to the decisions of other 
federal agencies, and state agencies acting under federally 
delegated authority, that are responsible for federal 
authorizations, permits, and other approvals necessary for proposed 
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the 
Commission's deadline for other agency's decisions applies unless a 
schedule is otherwise established by federal law.

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    Texas Eastern proposes to excavate, elevate, replace, and reroute 
segments of its existing pipelines ranging in length between 
approximately 4,000 feet and 8,500 feet in Greene County, Richhill and 
Center Townships, Pennsylvania. Texas Eastern would also abandon by 
removal two segments of non-operational pipeline. Upon completion of 
the sub-surface mining activities, Texas Eastern would return two of 
the four pipelines to their original locations and easements. One 
pipeline would be partially rerouted into a new easement, and another 
would be rerouted into the existing easement of an abandoned pipeline 
just north of its original location. Texas Eastern anticipates these 
activities would occur between 2026 and 2028.

Background

    On May 30, 2025, the Commission issued a Notice of Scoping Period 
Requesting Comments on Environmental Issues for the Proposed Longwall 
Mining Panel M1 Project and Notice of Public Scoping Session (Notice of 
Scoping). The Notice of Scoping was sent to affected landowners; 
federal, state, and local government agencies; elected officials; 
environmental and public interest groups; Native American tribes; other 
interested parties; and local libraries and newspapers. In response to 
the Notice of Scoping, the Commission received comments from the United 
States Environmental Protection Agency. The primary issue raised by the 
commenter is to address the environmental effects that potential 
subsidence, from longwall mining, would have on nearby water resources. 
All substantive comments will be addressed in the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of formal issuances and submittals in specific dockets, the 
Commission offers a free service called eSubscription. This service 
provides automatic notification of filings made to subscribed dockets, 
document summaries, and direct links to the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
community organizations, Tribal members and others, access publicly 
available information and navigate Commission processes. For public 
inquiries and assistance with making filings such as interventions, 
comments, or requests for rehearing, the public is encouraged to 
contact OPP at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#26697676664043544508414950"><span class="__cf_email__" data-cfemail="bdf2ededfddbd8cfde93dad2cb">[email&#160;protected]</span></a>.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (<a href="http://www.ferc.gov">www.ferc.gov</a>). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP25-379), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at <a href="/cdn-cgi/l/email-protection#e4a2a1b6a7ab8a888d8a81b79194948b9690a482819687ca838b92"><span class="__cf_email__" data-cfemail="e7a1a2b5a4a8898b8e8982b4929797889593a781829584c9808891">[email&#160;protected]</span></a>. The eLibrary link on the FERC 
website also provides access to the texts of formal documents issued by 
the Commission, such as orders, notices, and rule makings.

    Dated: July 2, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-12655 Filed 7-7-25; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on July 8, 2025.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.