Notice2025-12264

Lewis Ridge Pumped Storage, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Request and Establishing Procedural Schedule for Licensing and a Deadline for Submission of Final Amendments

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
July 1, 2025

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 90 Issue 124 (Tuesday, July 1, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 124 (Tuesday, July 1, 2025)]
[Notices]
[Page 28738]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-12264]



[[Page 28738]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[P-15249-002]


Lewis Ridge Pumped Storage, LLC; Notice of Application Tendered 
for Filing With the Commission and Soliciting Additional Study Request 
and Establishing Procedural Schedule for Licensing and a Deadline for 
Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.

    a. Type of Application: Original Major License.
    b. Project No.: 15249-002.
    c. Date Filed: June 13, 2025.
    d. Applicant: Lewis Ridge Pumped Storage, LLC.
    e. Name of Project: Lewis Ridge Pumped Storage Project.
    f. Location: The proposed project would be located near the towns 
of Blackmont, Tejay, Balkan, and Callaway, in Bell County, Kentucky.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Sandy Slayton, Rye Development, 1455 SW 
Broadway Street, Suite 290, Portland, Oregon 97201; (503) 341-1425; 
email: <a href="/cdn-cgi/l/email-protection#92e1f3fcf6ebd2e0ebf7f6f7e4f7fefde2fff7fce6bcf1fdff"><span class="__cf_email__" data-cfemail="d8abb9b6bca198aaa1bdbcbdaebdb4b7a8b5bdb6acf6bbb7b5">[email&#160;protected]</span></a>.
    i. FERC Contact: Monte TerHaar at (202) 502-6035, or 
<a href="/cdn-cgi/l/email-protection#3c51535248591248594e545d5d4e7c5a594e5f125b534a"><span class="__cf_email__" data-cfemail="d3bebcbda7b6fda7b6a1bbb2b2a193b5b6a1b0fdb4bca5">[email&#160;protected]</span></a>.
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See 94 FERC ] 
61,076 (2001).
    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and serve a copy of 
the request on the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: on or before 5:00 p.m. Eastern Standard Time 
on August 12, 2025.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at <a href="https://ferconline.ferc.gov/FERCOnline.aspx">https://ferconline.ferc.gov/FERCOnline.aspx</a>. For assistance, please contact FERC Online Support at 
<a href="/cdn-cgi/l/email-protection#80c6c5d2c3cfeeece9eee5d3f5f0f0eff2f4c0e6e5f2e3aee7eff6"><span class="__cf_email__" data-cfemail="c1878493828eafada8afa492b4b1b1aeb3b581a7a4b3a2efa6aeb7">[email&#160;protected]</span></a>, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy. 
Submissions sent via the U.S. Postal Service must be addressed to: 
Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 
888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent 
via any other carrier must be addressed to: Debbie-Anne A. Reese, 
Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, 
Rockville, Maryland 20852. All filings must clearly identify the 
project name and docket number on the first page: Lewis Ridge Pumped 
Storage Project (P-15249-002).
    m. This application is not ready for environmental analysis at this 
time.
    n. Project Description: The proposed Lewis Ridge Pumped Storage 
Project would consist of the following: (1) a 48.2-acre upper reservoir 
created by a 8,241-foot-long, 50-foot-high rocky earth-fill dam with an 
integrated emergency overflow spillway; (2) a 4,174-foot-long 
aboveground penstock; (3) a powerhouse located 267 feet below ground, 
containing two 154 MW reversible pump-turbines with a total rated 
capacity of 308 MW; (4) a 51.6-acre lower reservoir created by a 1,120-
foot-long, 138-foot-high earth-fill dam, with an integrated emergency 
overflow spillway; (5) a permanent screened intake and pump station on 
the Cumberland River, connecting to a 4,724-foot-long, 24-inch diameter 
buried pipeline that passes flows to a stilling basin connected to the 
lower reservoir; (6) a 2.5-mile-long, 161-kilovolt transmission line 
with two switching stations, connecting the project to the existing 
Pineville-Harlan #1 transmission line; and (7) appurtenant facilities.
    o. In addition to publishing the full text of this notice in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this notice, as well 
as other documents in the proceeding (e.g., license application) via 
the internet through the Commission's Home Page (<a href="http://www.ferc.gov">http://www.ferc.gov</a>), 
using the ``eLibrary'' link. Enter the docket number, excluding the 
last three digits in the docket number field to access the document (P-
14796). For assistance, please contact FERC Online Support at 
<a href="/cdn-cgi/l/email-protection#3f797a6d7c70515356515a6c4a4f4f504d4b7f595a4d5c11585049"><span class="__cf_email__" data-cfemail="c4828196878baaa8adaaa197b1b4b4abb6b084a2a1b6a7eaa3abb2">[email&#160;protected]</span></a>, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY).
    You may also register online at <a href="https://ferconline.ferc.gov/FERCOnline.aspx">https://ferconline.ferc.gov/FERCOnline.aspx</a> to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    p. The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
community organizations, Tribal members and others, access publicly 
available information and navigate Commission processes. For public 
inquiries and assistance with making filings such as interventions, 
comments, or requests for rehearing, the public is encouraged to 
contact OPP at (202) 502-6595, or <a href="/cdn-cgi/l/email-protection#d897888898bebdaabbf6bfb7ae"><span class="__cf_email__" data-cfemail="e5aab5b5a583809786cb828a93">[email&#160;protected]</span></a>.
    q. Procedural schedule and final amendments: The application will 
be processed according to the following preliminary schedule. Revisions 
to the schedule will be made as appropriate.

------------------------------------------------------------------------
                 Milestone                           Target date
------------------------------------------------------------------------
Deficiency letter (if necessary)..........  September 2025.
Additional Information Request (if          November 2025.
 necessary).
Issue Scoping Document 1 for comments.....  February 2026.
Issue Scoping Document 2 (if necessary)...  April 2026.
Notice of Acceptance/Notice of Ready for    June 2026.
 Environmental Analysis.
------------------------------------------------------------------------

    r. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: June 26, 2025.
Carlos D. Clay,
Deputy Secretary.
[FR Doc. 2025-12264 Filed 6-30-25; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on July 1, 2025.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.