Notice2025-10106
Midcontinent Independent System Operator, Inc.; Notice of Motion for Extension of Effective Date, Motion for Shortened Response Period, and Request for Expedited Action
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
June 4, 2025
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 90 Issue 106 (Wednesday, June 4, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 106 (Wednesday, June 4, 2025)]
[Notices]
[Page 23684]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-10106]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. ER24-2046-000]
Midcontinent Independent System Operator, Inc.; Notice of Motion
for Extension of Effective Date, Motion for Shortened Response Period,
and Request for Expedited Action
On May 23, 2025, pursuant to Rules 212 and 2008 of the Commission's
Rules of Practice and Procedure,\1\ the Midcontinent Independent System
Operator, Inc. (MISO) filed a motion for extension of the requested
effective date of MISO's proposed revisions of its Open Access
Transmission, Energy and Operating Reserve Markets Tariff and pro forma
agreements submitted in compliance of Order Nos. 2023 and 2023-A,\2\ a
motion for a shorter answer period, and a request for expedited action
on its extension motion. MISO requests that the Commission extend
MISO's originally requested effective date from June 1, 2025 to 30 days
after the date on which the Commission accepts MISO's compliance filing
in the above referenced docket.
---------------------------------------------------------------------------
\1\ 18 C.F. Deputy Secretary. R. Sec. Sec. 385.212, 385.2008
(2024).
\2\ Improvements to Generator Interconnection Procs. &
Agreements, Order No. 2023, 184 FERC ] 61,054, order on reh'g, 185
FERC ] 61,063 (2023), order on reh'g, Order No. 2023-A, 186 FERC ]
61,199, errata notice, 188 FERC ] 61,134 (2024).
---------------------------------------------------------------------------
Answers to the motion must be filed by 5:00 p.m. Eastern Time on
Monday, June 9, 2025.
Dated: May 28, 2025.
Carlos D. Clay,
Deputy Secretary.
[FR Doc. 2025-10106 Filed 6-3-25; 8:45 am]
BILLING CODE 6717-01-P
</pre></body>
</html>Indexed from Federal Register on June 4, 2025.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.