Notice2025-09922

Nevada Power Company; Notice of Motion for Extension of Time To Comply

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
June 2, 2025

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 90 Issue 104 (Monday, June 2, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 104 (Monday, June 2, 2025)]
[Notices]
[Page 23333]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-09922]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. ER22-2304-000, ER22-2304-001]


Nevada Power Company; Notice of Motion for Extension of Time To 
Comply

    On May 5, 2025, Nevada Power Company and Sierra Pacific Power 
Company (together, Nevada Power) filed a motion for extension of time 
to comply with implementing the requirements of Order No. 881 and Order 
No. 881-A \1\ and the Commission's May 18, 2023 order,\2\ from July 12, 
2025, to October 15, 2027. Specifically, Nevada Power requests: an 
extension of time (1) to test critical vendor programs necessary for 
Nevada Power's Order No. 881 compliance on its own system and to align 
compliance with the Order No. 881 integration timelines proposed by 
California Independent System Operator Corporation (CAISO) for, among 
other markets, the Western Energy Imbalance Market; (2) to mitigate 
potential reliability, operational, and market concerns with starting 
new and minimally tested line ratings during the 2025 and 2026 peak 
summer loading periods and without full market integration by CAISO; 
and (3) to ensure there is appropriate time to train Nevada Power staff 
on the newly implemented programs, and to comply with the documentation 
requirements of Order No. 881.
---------------------------------------------------------------------------

    \1\ Managing Transmission Line Ratings, Order No. 881, 177 FERC 
] 61,179 (2021), order addressing arguments raised on reh'g, Order 
No. 881-A, 179 FERC ] 61,125 (2022).
    \2\ Nev. Power Co., 184 FERC ] 61,048 (2023).
---------------------------------------------------------------------------

    Answers to the motion must be filed by 5 p.m. Eastern Time on June 
17, 2025.

    Dated: May 27, 2025.
Carlos D. Clay,
Deputy Secretary.
[FR Doc. 2025-09922 Filed 5-30-25; 8:45 am]
BILLING CODE 6717-01-P


</pre></body>
</html>
Indexed from Federal Register on June 2, 2025.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.