Notice2025-09921

Deseret Generation & Transmission Co-operative, Inc.; Notice of Request for Deferral of Effective Date

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
June 2, 2025

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 90 Issue 104 (Monday, June 2, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 104 (Monday, June 2, 2025)]
[Notices]
[Page 23333]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-09921]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. ER22-2162-001, ER22-2162-002]


Deseret Generation & Transmission Co-operative, Inc.; Notice of 
Request for Deferral of Effective Date

    On May 19, 2025, Deseret Generation & Transmission Co-operative, 
Inc. (Deseret) filed a request for deferral of the July 12, 2025 
effective date of its Open Access Transmission Tariff (Tariff) 
Attachment T--Transmission Line Ratings accepted by the Commission \1\ 
in compliance with Order Nos. 881 and 881-A.\2\ Deseret requests that 
the Commission grant an extension of the deadline to implement its 
Tariff revisions from July 12, 2025 to a future date that aligns with 
California Independent System Operator Corporation's (CAISO) and the 
Western Area Power Administration's (Western) ability to integrate 
Ambient Adjusted Rates (AAR's) into their respective network models. 
Deseret states that it must work with third-party vendors to design and 
implement systems that will be compatible with systems in CAISO and 
Western that are under development and that will not be functional to 
meet its compliance deadline.
---------------------------------------------------------------------------

    \1\ Deseret Generation & Transmission Co-operative, Inc., 184 
FERC ] 61,174 (2023).
    \2\ Managing Transmission Line Ratings, Order No. 881, 177 FERC 
] 61,179 (2021), order addressing arguments raised on reh'g, Order 
No. 881-A, 179 FERC ] 61,125 (2022).
---------------------------------------------------------------------------

    Answers to the motion must be filed by 5 p.m. Eastern Time on June 
2, 2025.

    Dated: May 27, 2025.
Carlos D. Clay,
Deputy Secretary.
[FR Doc. 2025-09921 Filed 5-30-25; 8:45 am]
BILLING CODE 6717-01-P