Spencer Mountain Hydropower, LLC; Notice of Revised Procedural Schedule for Environmental Assessment for the Proposed Project Relicense
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
May 19, 2025
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 90 Issue 95 (Monday, May 19, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 95 (Monday, May 19, 2025)]
[Notices]
[Page 21300]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-08836]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2607-016]
Spencer Mountain Hydropower, LLC; Notice of Revised Procedural
Schedule for Environmental Assessment for the Proposed Project
Relicense
On June 26, 2023, Spencer Mountain Hydropower, LLC (Spencer
Mountain Hydropower) filed an application to relicense the 0.64-
megawatt Spencer Mountain Hydroelectric Project No. 2607 (Spencer
Mountain Project or project). On March 24, 2025, Commission staff
issued a notice of intent to prepare an environmental assessment (EA)
to evaluate the effects of relicensing the Spencer Mountain Project.
The notice included an anticipated schedule for issuing the EA.\1\
---------------------------------------------------------------------------
\1\ For tracking purposes under the National Environmental
Policy Act, the unique identification number for documents relating
to this environmental review is EAXX-019-20-000-1742805952.
---------------------------------------------------------------------------
Staff is still evaluating the effects of relicensing the project;
therefore, the procedural schedule for completing the EA is being
revised as follows. Further revisions to the schedule may be made as
appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Issue EA.................................. February 17, 2026.
------------------------------------------------------------------------
Any questions regarding this notice may be directed to David Gandy
at 202-502-8560, or <a href="/cdn-cgi/l/email-protection#5034312639347e37313e342910363522337e373f26"><span class="__cf_email__" data-cfemail="4125203728256f26202f253801272433226f262e37">[email protected]</span></a>.
Dated: May 12, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-08836 Filed 5-16-25; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on May 19, 2025.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.