Notice2025-08052

Rover Pipeline, LLC; Notice of Revised Schedule for Environmental Review of the Rover-Bulger Compressor Station and Harmon Creek Meter Station Expansion Project

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
May 8, 2025

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 90 Issue 88 (Thursday, May 8, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 88 (Thursday, May 8, 2025)]
[Notices]
[Page 19481]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-08052]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP25-12-000]


Rover Pipeline, LLC; Notice of Revised Schedule for Environmental 
Review of the Rover-Bulger Compressor Station and Harmon Creek Meter 
Station Expansion Project

    This notice identifies the Federal Energy Regulatory Commission 
staff's revised schedule for the completion of the environmental 
assessment (EA) for Rover Pipeline, LLC's (Rover) Rover-Bulger 
Compressor Station and Harmon Creek Meter Station Expansion Project 
(Project).\1\ The first notice of schedule, issued on December 30, 
2024, identified May 5, 2025, as the EA issuance date. However, as 
indicated in a filing dated April 30, 2025, Rover requires additional 
time to respond to staff's April 24, 2025, environmental information 
request, and subsequently, staff will require additional time to 
process this response. As a result, staff has revised the schedule for 
issuance of the EA. The EA will be issued for a 30-day comment period.
---------------------------------------------------------------------------

    \1\ For tracking purposes under the National Environmental 
Policy Act, the unique identification number for documents relating 
to this environmental review is EAXX-019-20-000-1745398211.
---------------------------------------------------------------------------

Schedule for Environmental Review

Issuance of the EA: June 25, 2025
90-day Federal Authorization Decision Deadline: \2\ September 23, 2025
---------------------------------------------------------------------------

    \2\ The Commission's deadline applies to the decisions of other 
Federal agencies, and State agencies acting under federally 
delegated authority, that are responsible for Federal 
authorizations, permits, and other approvals necessary for proposed 
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the 
Commission's deadline for other agency's decisions applies unless a 
schedule is otherwise established by Federal law.

    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
community organizations, Tribal members and others, access publicly 
available information and navigate Commission processes. For public 
inquiries and assistance with making filings such as interventions, 
comments, or requests for rehearing, the public is encouraged to 
contact OPP at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#cf809f9f8fa9aabdace1a8a0b9"><span class="__cf_email__" data-cfemail="7b342b2b3b1d1e0918551c140d">[email&#160;protected]</span></a>.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (<a href="http://www.ferc.gov">www.ferc.gov</a>). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP25-12), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at <a href="/cdn-cgi/l/email-protection#8ccac9decfc3e2e0e5e2e9dff9fcfce3fef8cceae9feefa2ebe3fa"><span class="__cf_email__" data-cfemail="561013041519383a3f383305232626392422163033243578313920">[email&#160;protected]</span></a>. The eLibrary link on the FERC 
website also provides access to the texts of formal documents issued by 
the Commission, such as orders, notices, and rule makings.

    Dated: May 2, 2025.
Carlos D. Clay,
Deputy Secretary.
[FR Doc. 2025-08052 Filed 5-7-25; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on May 8, 2025.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.