Notice2025-08052
Rover Pipeline, LLC; Notice of Revised Schedule for Environmental Review of the Rover-Bulger Compressor Station and Harmon Creek Meter Station Expansion Project
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
May 8, 2025
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 90 Issue 88 (Thursday, May 8, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 88 (Thursday, May 8, 2025)]
[Notices]
[Page 19481]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-08052]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP25-12-000]
Rover Pipeline, LLC; Notice of Revised Schedule for Environmental
Review of the Rover-Bulger Compressor Station and Harmon Creek Meter
Station Expansion Project
This notice identifies the Federal Energy Regulatory Commission
staff's revised schedule for the completion of the environmental
assessment (EA) for Rover Pipeline, LLC's (Rover) Rover-Bulger
Compressor Station and Harmon Creek Meter Station Expansion Project
(Project).\1\ The first notice of schedule, issued on December 30,
2024, identified May 5, 2025, as the EA issuance date. However, as
indicated in a filing dated April 30, 2025, Rover requires additional
time to respond to staff's April 24, 2025, environmental information
request, and subsequently, staff will require additional time to
process this response. As a result, staff has revised the schedule for
issuance of the EA. The EA will be issued for a 30-day comment period.
---------------------------------------------------------------------------
\1\ For tracking purposes under the National Environmental
Policy Act, the unique identification number for documents relating
to this environmental review is EAXX-019-20-000-1745398211.
---------------------------------------------------------------------------
Schedule for Environmental Review
Issuance of the EA: June 25, 2025
90-day Federal Authorization Decision Deadline: \2\ September 23, 2025
---------------------------------------------------------------------------
\2\ The Commission's deadline applies to the decisions of other
Federal agencies, and State agencies acting under federally
delegated authority, that are responsible for Federal
authorizations, permits, and other approvals necessary for proposed
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the
Commission's deadline for other agency's decisions applies unless a
schedule is otherwise established by Federal law.
If a schedule change becomes necessary, an additional notice will
be provided so that the relevant agencies are kept informed of the
project's progress.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription. This can
reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
community organizations, Tribal members and others, access publicly
available information and navigate Commission processes. For public
inquiries and assistance with making filings such as interventions,
comments, or requests for rehearing, the public is encouraged to
contact OPP at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#cf809f9f8fa9aabdace1a8a0b9"><span class="__cf_email__" data-cfemail="7b342b2b3b1d1e0918551c140d">[email protected]</span></a>.
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC website (<a href="http://www.ferc.gov">www.ferc.gov</a>). Using the ``eLibrary'' link, select
``General Search'' from the eLibrary menu, enter the selected date
range and ``Docket Number'' excluding the last three digits (i.e.,
CP25-12), and follow the instructions. For assistance with access to
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at <a href="/cdn-cgi/l/email-protection#8ccac9decfc3e2e0e5e2e9dff9fcfce3fef8cceae9feefa2ebe3fa"><span class="__cf_email__" data-cfemail="561013041519383a3f383305232626392422163033243578313920">[email protected]</span></a>. The eLibrary link on the FERC
website also provides access to the texts of formal documents issued by
the Commission, such as orders, notices, and rule makings.
Dated: May 2, 2025.
Carlos D. Clay,
Deputy Secretary.
[FR Doc. 2025-08052 Filed 5-7-25; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on May 8, 2025.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.