Notice2025-07764
GridLiance Heartland LLC; Notice of Motion for Extension of Time
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
May 5, 2025
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 90 Issue 85 (Monday, May 5, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 85 (Monday, May 5, 2025)]
[Notices]
[Pages 18975-18976]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-07764]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. ER22-2355-000]
GridLiance Heartland LLC; Notice of Motion for Extension of Time
On November 8, 2024, GridLiance Heartland LLC (GridLiance
Heartland)
[[Page 18976]]
filed a motion for an extension of time to submit a compliance filing
explaining the timelines for calculating or submitting ambient-adjusted
ratings (AAR) in compliance with Order Nos. 881 and 881-A \1\ and the
Commission's July 27, 2023, order \2\ to implement GridLiance
Heartland's compliance revisions in Attachment T to its Open Access
Transmission Tariff (OATT).\3\
---------------------------------------------------------------------------
\1\ Managing Transmission Line Ratings, Order No. 881, 177 FERC
] 61,179 (2021), order addressing arguments raised on reh'g, Order
No. 881-A, 179 FERC ] 61,125 (2022).
\2\ GridLiance Heartland LLC, 184 FERC ] 61,043 (2023) (July
2023 Order).
\3\ Motion, Transmittal Letter at 1.
---------------------------------------------------------------------------
GridLiance Heartland states that it no longer retains operational
control over any of its transmission facilities and no longer provides
transmission service for any transmission lines under the GridLiance
Heartland OATT.\4\ GridLiance Heartland explains that because all of
its facilities are now under the operational control of the
Midcontinent Independent System Operator, Inc. (MISO), AARs for its
transmission lines will be submitted directly to MISO in accordance
with the timelines required by the MISO procedures, rather than being
calculated and posted pursuant to Attachment T of the GridLiance
Heartland OATT.\5\ GridLiance Heartland therefore requests an extension
of time to submit the further compliance filing required by the July
2023 Order until such time as GridLiance Heartland acquires
transmission lines that are governed by the GridLiance Heartland
OATT.\6\
---------------------------------------------------------------------------
\4\ Id. at 1-2.
\5\ Id. at 2-3.
\6\ Id. at 3.
---------------------------------------------------------------------------
Answers to the motion must be filed by 5:00 p.m. Eastern Time on
Tuesday, May 6, 2025.
Dated: April 29, 2025.
Carlos D. Clay,
Deputy Secretary.
[FR Doc. 2025-07764 Filed 5-2-25; 8:45 am]
BILLING CODE 6717-01-P
</pre></body>
</html>Indexed from Federal Register on May 5, 2025.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.