[Federal Register Volume 90, Number 64 (Friday, April 4, 2025)]
[Notices]
[Pages 14822-14823]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-05769]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP24-59-001]


WBI Energy Transmission, Inc.; Notice of Request for Extension of 
Time

    Take notice that on March 21, 2025, WBI Energy Transmission, Inc. 
(WBI Energy) requested that the Commission grant an extension of time, 
until December 31, 2025, to complete construction and place into 
service the Elk Basin--Billings Replacement Project (Project) located 
in Yellowstone County, Montana. On February 23, 2024, the Commission 
issued a Notice of Request Under Blanket Authorization, which 
established a 60-day comment period, ending on April 23, 2024, to file 
protests. No protests were filed during the comment period, and 
accordingly the project self-implemented on April 24, 2024, and by Rule 
should have been completed within one year.
    WBI Energy states it has successfully completed construction 
activities for Section 4 of the Project and has commenced construction 
activities at the North Yellowstone River Valve Setting. However, due 
to delays in receiving an easement from the Burlington Northern Santa 
Fe Railway (BNSF), WBI Energy has been unable to commence construction 
in Sections 1 through 3 of the Project.
    On March 12, 2025, WBI Energy received a draft easement agreement 
from BNSF and is currently reviewing the terms of the easement. Upon 
receiving a final easement agreement, WBI Energy anticipates 
construction of Sections 1 through 3 will take approximately five 
months. Construction activities in Sections 1 through 3 include: (1) 
replacement of pipeline including installation and removal activities; 
(2) completion of six guided bores; (3) aboveground facility work at 
the Monad Station, Streeter Valve Setting, Conoco Takeoff Valve 
Setting, T&E Lateral Valve Setting, Laurel Town Border Station, and 
Yost Farm Tap; (4) completion of construction activities at the North 
Yellowstone River Valve Setting; and (5) clean-up and seeding 
activities.
    This notice establishes a 15-calendar day intervention and comment 
period deadline. Any person wishing to comment on WBI Energy's request 
for an extension of time may do so. No reply comments or answers will 
be considered. If you wish to obtain legal status by becoming a party 
to the proceedings for this request, you should, on or before the 
comment date stated below, file a motion to intervene in accordance 
with the requirements of the Commission's Rules of Practice and 
Procedure (18 CFR 385.214 or 385.211) and the Regulations under the 
Natural Gas Act (NGA) (18 CFR 157.10).
    As a matter of practice, the Commission itself generally acts on 
requests for extensions of time to complete construction for NGA 
facilities when such requests are contested before order issuance. For 
those extension requests that are contested,\1\ the Commission will aim 
to issue an order acting on the request within 45 days.\2\ The 
Commission will address all arguments relating to whether the applicant 
has demonstrated there is good cause to grant the extension.\3\ The 
Commission will not consider arguments that re-litigate the issuance of 
the certificate order, including whether the Commission properly found 
the project to be in the public convenience and necessity and whether 
the Commission's environmental analysis for the certificate complied 
with the National Environmental Policy Act (NEPA).\4\ At the time a 
pipeline requests an extension of time, orders on certificates of 
public convenience and necessity are final and the Commission will not 
re-litigate their issuance.\5\ The Director of the Office of Energy 
Projects, or his or her designee, will act on all of those extension 
requests that are uncontested.
---------------------------------------------------------------------------

    \1\ Contested proceedings are those where an intervenor disputes 
any material issue of the filing. 18 CFR 385.2201(c)(1).
    \2\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40 
(2020).
    \3\ Id. at P 40.
    \4\ Similarly, the Commission will not re-litigate the issuance 
of an NGA section 3 authorization, including whether a proposed 
project is not inconsistent with the public interest and whether the 
Commission's environmental analysis for the permit order complied 
with NEPA.
    \5\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40 
(2020).
---------------------------------------------------------------------------

    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (<a href="https://www.ferc.gov">https://www.ferc.gov</a>). 
From the Commission's Home Page on the internet, this information is 
available on eLibrary. The full text of this document is available on 
eLibrary in PDF and Microsoft Word format for viewing, printing, and/or 
downloading. To access this document in eLibrary, type the docket 
number excluding the last three digits of this document in the docket 
number field.
    User assistance is available for eLibrary and the Commission's 
website

[[Page 14823]]

during normal business hours from FERC Online Support at (202) 502-6652 
(toll free at 1-866-208-3676) or email at <a href="/cdn-cgi/l/email-protection#a6c0c3d4c5c9c8cacfc8c3d5d3d6d6c9d4d2e6c0c3d4c588c1c9d0"><span class="__cf_email__" data-cfemail="b4d2d1c6d7dbdad8dddad1c7c1c4c4dbc6c0f4d2d1c6d79ad3dbc2">[email&#160;protected]</span></a>, 
or the Public Reference Room at (202) 502-8371, TTY (202) 502-8659. 
Email the Public Reference Room at <a href="/cdn-cgi/l/email-protection#ed9d988f81848ec39f888b889f88838e889f828280ad8b889f8ec38a829b"><span class="__cf_email__" data-cfemail="403035222c29236e3225262532252e2325322f2f2d00262532236e272f36">[email&#160;protected]</span></a>.
    The Commission strongly encourages electronic filings of comments 
in lieu of paper using the ``eFile'' link at <a href="http://www.ferc.gov">http://www.ferc.gov</a>. In 
lieu of electronic filing, you may submit a paper copy which must 
reference the Project docket number.
    To file via USPS: Debbie-Anne A. Reese, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426.
    To file via any other courier: Debbie-Anne A. Reese, Secretary, 
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, 
Maryland 20852.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
community organizations, Tribal members and others, access publicly 
available information and navigate Commission processes. For public 
inquiries and assistance with making filings such as interventions, 
comments, or requests for rehearing, the public is encouraged to 
contact OPP at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#054a555545636077662b626a73"><span class="__cf_email__" data-cfemail="c08f909080a6a5b2a3eea7afb6">[email&#160;protected]</span></a>.
    Comment Date: 5:00 p.m. Eastern Time on April 14, 2025.

    Dated: March 28, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-05769 Filed 4-3-25; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on April 4, 2025.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.