Notice2025-05080

Notice of Schedule for the Preparation of an Environmental Assessment for the Transwestern Pipeline Company, LLC WT-0 Compressor Station Project

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
March 26, 2025

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 90 Issue 57 (Wednesday, March 26, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 57 (Wednesday, March 26, 2025)]
[Notices]
[Pages 13748-13749]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-05080]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP25-37-000]


Notice of Schedule for the Preparation of an Environmental 
Assessment for the Transwestern Pipeline Company, LLC WT-0 Compressor 
Station Project

    On December 20, 2024, Transwestern Pipeline Company, LLC 
(Transwestern) filed an application in Docket No. CP25-37-000 
requesting a Certificate of Public Convenience and Necessity pursuant 
to Section 7(c) of the Natural Gas Act to construct, own, operate, and 
maintain a new compressor station in Chaves County, New Mexico. This 
WT-0 Compressor Station Project (Project) would provide about 80,000 
million British thermal units per day of new firm transportation 
capacity, including receipts of natural gas in Transwestern's West 
Texas Lateral Central Zone and deliveries on the Transwestern Panhandle 
Lateral.
    On January 8, 2025, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
environmental document for the Project.
    This notice identifies Commission staff's intention to prepare an 
environmental assessment (EA) for the Project and the planned schedule 
for the completion of the environmental review.\1\ The EA will be 
issued for a 30-day comment period.
---------------------------------------------------------------------------

    \1\ For tracking purposes under the National Environmental 
Policy Act, the unique identification number for documents relating 
to this environmental review is EAXX-019-20-000-1742295781.
---------------------------------------------------------------------------

Schedule for Environmental Review

Issuance of EA--August 1, 2025
90-day Federal Authorization Decision Deadline \2\--October 30, 2025
---------------------------------------------------------------------------

    \2\ The Commission's deadline applies to the decisions of other 
federal agencies, and state agencies acting under federally 
delegated authority, that are responsible for federal 
authorizations, permits, and other approvals necessary for proposed 
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the 
Commission's deadline for other agency's decisions applies unless a 
schedule is otherwise established by federal law.

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    The WT-0 Compressor Station Project would consist of the following 
facilities in Chaves County, New Mexico:
    <bullet> a new WT-0 Compressor Station including one new 13,220-
horsepower Solar Mars 90 natural gas turbine-driven compressor;
    <bullet> metering facilities, including an inlet filter separator 
and fuel gas measurement skid;
    <bullet> tie-in to Transwestern's existing 24-inch-diameter dual 
lateral pipeline in its existing corridor; and
    <bullet> a new, permanent access road off Harriet Road extending 
into the compressor station site.

Background

    On February 3, 2025, the Commission issued a Notice of Scoping 
Period Requesting Comments on Environmental Issues for the Proposed WT-
0 Compressor Station Project (Notice of Scoping). The Notice of Scoping 
was sent to affected landowners; federal, state, and local government 
agencies; \3\ elected officials; environmental and public interest 
groups; Native American tribes; other interested parties; and local 
libraries and newspapers. In response to the Notice of Scoping, the 
Commission received comments from the Santa Clara Pueblo and the New 
Mexico Department

[[Page 13749]]

of Game and Fish. All substantive comments will be addressed in the EA.
---------------------------------------------------------------------------

    \3\ The new compressor station would be sited entirely on land 
managed by the U.S. Bureau of Land Management (BLM). The BLM has 
agreed to be a cooperating agency for the preparation of the EA.
---------------------------------------------------------------------------

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of formal issuances and submittals in specific dockets, the 
Commission offers a free service called eSubscription. This service 
provides automatic notification of filings made to subscribed dockets, 
document summaries, and direct links to the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
community organizations, Tribal members and others, access publicly 
available information and navigate Commission processes. For public 
inquiries and assistance with making filings such as interventions, 
comments, or requests for rehearing, the public is encouraged to 
contact OPP at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#fbb4ababbb9d9e8998d59c948d"><span class="__cf_email__" data-cfemail="df908f8f9fb9baadbcf1b8b0a9">[email&#160;protected]</span></a>.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (<a href="http://www.ferc.gov">www.ferc.gov</a>). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP25-37), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at <a href="/cdn-cgi/l/email-protection#cb8d8e998884a5a7a2a5ae98bebbbba4b9bf8badaeb9a8e5aca4bd"><span class="__cf_email__" data-cfemail="d89e9d8a9b97b6b4b1b6bd8bada8a8b7aaac98bebdaabbf6bfb7ae">[email&#160;protected]</span></a>. The eLibrary link on the FERC 
website also provides access to the texts of formal documents issued by 
the Commission, such as orders, notices, and rule makings.

    Dated: March 19, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-05080 Filed 3-25-25; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on March 26, 2025.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.