Notice2025-04480

Eastern Gas Transmission and Storage, Inc.; Notice of Schedule for the Preparation of an Environmental Assessment for the Capital Area Project

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
March 19, 2025

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 90 Issue 52 (Wednesday, March 19, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 52 (Wednesday, March 19, 2025)]
[Notices]
[Page 12721]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-04480]



[[Page 12721]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP25-29-000]


Eastern Gas Transmission and Storage, Inc.; Notice of Schedule 
for the Preparation of an Environmental Assessment for the Capital Area 
Project

    On December 11, 2024, Eastern Gas Transmission and Storage, Inc. 
(EGTS), filed an application in Docket No. CP25-29-000 requesting an 
authorization pursuant to section 7(c) of the Natural Gas Act and the 
regulations under part 157 of the Federal Energy Regulatory Commission 
(Commission) to construct, operate and maintain certain interstate 
natural gas pipeline facilities located in Clinton, Centre and Franklin 
Counties, Pennsylvania; and Loudoun County, Virginia. The proposed 
project is known as the Capital Area Project (Project) and would enable 
EGTS to deliver an additional 67,500 dekatherms per day of natural gas 
from an existing upstream pipeline interconnect in Clinton County, 
Pennsylvania, for delivery to local natural gas utilities in Frederick 
County, Maryland, and Loudoun County, Virginia.
    On December 23, 2024, the Commission issued its Notice of 
Application for the Project. Among other things, that notice alerted 
agencies issuing Federal authorizations of the requirement to complete 
all necessary reviews and to reach a final decision on a request for a 
Federal authorization within 90 days of the date of issuance of the 
Commission staff's environmental document for the Project.
    This notice identifies Commission staff's intention to prepare an 
environmental assessment (EA) for the Project and the planned schedule 
for the completion of the environmental review.\1\ The EA will be 
issued for a 30-day comment period.
---------------------------------------------------------------------------

    \1\ For tracking purposes under the National Environmental 
Policy Act, the unique identification number for documents relating 
to this environmental review is EAXX-019-20-000-1741616931.
---------------------------------------------------------------------------

Schedule for Environmental Review

Issuance of EA--August 8, 2025
90-day Federal Authorization Decision Deadline \2\--November 6, 2025
---------------------------------------------------------------------------

    \2\ The Commission's deadline applies to the decisions of other 
Federal agencies, and State agencies acting under federally 
delegated authority, that are responsible for Federal 
authorizations, permits, and other approvals necessary for proposed 
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the 
Commission's deadline for other agency's decisions applies unless a 
schedule is otherwise established by Federal law.

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    The Project would increase natural gas capacity on EGTS' existing 
PL-1 pipeline system through the addition of compression and facility 
modifications at its existing Finnefrock, Centre, and Chambersburg 
Compressor Stations in Pennsylvania and Leesburg Compressor Station in 
Virginia. Specifically, the Project would add one 6,130 horsepower (hp) 
gas-fired turbine compressor unit and ancillary facilities at Centre 
Compressor Station in Centre County, Pennsylvania; add one 11,110 hp 
gas-fired turbine compressor unit and ancillary facilities at 
Chambersburg Compressor Station in Franklin County, Pennsylvania; add 
one 5,000 hp electric-driven compressor unit and ancillary facilities 
at Leesburg Compressor Station in Loudoun County, Virginia; and replace 
gas coolers and headers and cold recycle piping, and install new check 
valves, at Finnefrock Compressor Station in Clinton County, 
Pennsylvania.

Background

    On February 4, 2025, the Commission issued a ``Notice of Scoping 
Period Requesting Comments on Environmental Issues for the Proposed 
Capital Area Project'' (Notice of Scoping). The Notice of Scoping was 
sent to affected landowners; Federal, State, and local government 
agencies; elected officials; environmental and public interest groups; 
Native American tribes; other interested parties; and local libraries 
and newspapers.
    In response to the Notice of Scoping, the Commission received 27 
comments. Twenty of these comments were in favor of the Project 
emphasizing its critical importance in meeting the growing energy needs 
of residents and business in Pennsylvania, Maryland and Virginia. The 
Virginia Department of Environmental Quality suggested that that 
consideration should be given for the possibility of preparing an 
Environmental Impact Statement (EIS) for this Project, since it 
requires more stringent public participation requirements than an EA. 
Piedmont Environmental Council and the Chesapeake Bay Foundation also 
requested that a full EIS be completed. The Virginia Department of 
Wildlife Resources searched its Biotics Data System and confirmed that 
no natural heritage resources have been documented within the Project 
boundary including a 100-foot buffer. One landowner near the Leesburg 
Compressor Station noted air quality concerns with the station and the 
proposed expansion. The Loudoun County Office of Emergency Management 
suggested that EGTS conduct a community meeting for nearby residents.
    All substantive comments will be addressed in the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of formal issuances and submittals in specific dockets, the 
Commission offers a free service called eSubscription. This service 
provides automatic notification of filings made to subscribed dockets, 
document summaries, and direct links to the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
community organizations, Tribal members and others, access publicly 
available information and navigate Commission processes. For public 
inquiries and assistance with making filings such as interventions, 
comments, or requests for rehearing, the public is encouraged to 
contact OPP at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#3e716e6e7e585b4c5d10595148"><span class="__cf_email__" data-cfemail="5a150a0a1a3c3f2839743d352c">[email&#160;protected]</span></a>.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (<a href="http://www.ferc.gov">www.ferc.gov</a>). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP25-29-000), and follow the instructions. For assistance with access 
to eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 
502-8659, or at <a href="/cdn-cgi/l/email-protection#41070413020e2f2d282f24123431312e333501272433226f262e37"><span class="__cf_email__" data-cfemail="2d6b687f6e6243414443487e585d5d425f596d4b485f4e034a425b">[email&#160;protected]</span></a>. The eLibrary link on the 
FERC website also provides access to the texts of formal documents 
issued by the Commission, such as orders, notices, and rule makings.

    Dated: March 12, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-04480 Filed 3-18-25; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>