Notice2025-03925

Pacific Gas & Electric Company; Notice of Intent To Prepare an Environmental Assessment

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
March 14, 2025

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 90 Issue 49 (Friday, March 14, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 49 (Friday, March 14, 2025)]
[Notices]
[Pages 12157-12158]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-03925]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 1121-135]


Pacific Gas & Electric Company; Notice of Intent To Prepare an 
Environmental Assessment

    On September 9, 2022, as supplemented on October 2, 2023, and 
December 1, 2023, Pacific Gas & Electric Company (PG&E or licensee) 
filed an application for a non-capacity

[[Page 12158]]

amendment for the Battle Creek Hydroelectric Project No. 1121. The 
project is located on the mainstem Battle Creek, and on the North Fork 
and South Fork Battle Creek in Shasta and Tehama counties, California. 
The project occupies federal lands administered by the U.S. Forest 
Service and the Bureau of Land Management.
    PG&E is requesting that its license for the Battle Creek 
Hydroelectric Project be amended to support a new Phase 2 of the Battle 
Creek Salmon and Steelhead Restoration Project (Restoration Project). 
The Restoration Project is a collaborative effort to restore fish 
habitat on Battle Creek and some of its tributaries. The new Phase 2 
amendment requires the removal of the South Diversion Dam, Soap Creek 
Feeder Diversion Dam, Lower Ripley Creek Feeder Diversion Dam, and 
Coleman Diversion Dam, but does not include the tailrace connector 
tunnel from South Powerhouse to Inskip Canal. A Notice of Application 
Accepted for Filing and Soliciting Comments, Motions to Intervene, and 
Protest was issued on October 3, 2022.
    The original Phase 2 was evaluated in a 2005 Environmental Impact 
Statement; however, the new Phase 2 amendment request does not include 
the construction of one of the mitigation measures. This notice 
identifies Commission staff's intention to prepare an environmental 
assessment (EA) analyzing the recent changes to the proposed action. 
The planned schedule for the completion of the EA is April 7, 2025.\1\ 
Revisions to the schedule may be made as appropriate. The EA will be 
issued and made available for review by all interested parties. All 
comments filed on the EA will be reviewed by staff and considered in 
the Commission's final decision on the proceeding.
---------------------------------------------------------------------------

    \1\ The unique identification number for documents relating to 
this environmental review is EAXX-019-20-000-1741169216.
---------------------------------------------------------------------------

    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
community organizations, Tribal members and others, access publicly 
available information and navigate Commission processes. For public 
inquiries and assistance with making filings such as interventions, 
comments, or requests for rehearing, the public is encouraged to 
contact OPP at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#602f303020060512034e070f16"><span class="__cf_email__" data-cfemail="aae5fafaeacccfd8c984cdc5dc">[email&#160;protected]</span></a>.
    Any questions regarding this notice may be directed to Rebecca 
Martin at 202-502-6012 or <a href="/cdn-cgi/l/email-protection#5e0c3b3c3b3d3d3f70333f2c2a37301e383b2c3d70393128"><span class="__cf_email__" data-cfemail="31635453545252501f5c504345585f71575443521f565e47">[email&#160;protected]</span></a>.

(Authority: 42 U.S.C. 4321 et seq.)

    Dated: March 6, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-03925 Filed 3-13-25; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on March 14, 2025.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.