Notice2025-03704

White Pine Waterpower, LLC; Notice of Revised Schedule for White Pine Pumped Storage Project

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
March 7, 2025

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 90 Issue 44 (Friday, March 7, 2025)</title>
</head>
<body><pre>
[Federal Register Volume 90, Number 44 (Friday, March 7, 2025)]
[Notices]
[Pages 11529-11530]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2025-03704]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14851-003]


White Pine Waterpower, LLC; Notice of Revised Schedule for White 
Pine Pumped Storage Project

    This notice revises the Federal Energy Regulatory Commission's 
(Commission) schedule for processing White Pine Waterpower, LLC's 
license application for the White Pine Pumped Storage Project. A prior 
notice issued on November 15, 2023, identified an anticipated schedule 
for issuance of draft and final National Environmental Policy Act 
(NEPA) documents and a final order for the project. After the issuance 
of that notice, White Pine Waterpower, LLC requested an extension of 
time to complete its hydrogeologic study with a final study report to 
be filed by January 31, 2026. Commission staff issued a letter 
approving the extension of time on February 26, 2025. To account for 
the additional time needed for White Pine Waterpower, LLC to complete 
the study and file the study report, the application will be processed 
according to the following revised schedule.

Notice of Ready for Environmental Analysis: April 2026
Draft NEPA Document: January 2027
Final NEPA Document: July 23, 2027

    In addition, in accordance with title 41 of the Fixing America's 
Surface Transportation Act, enacted on December 4, 2015, agencies are 
to publish completion dates for all federal environmental reviews and

[[Page 11530]]

authorizations. This notice identifies the Commission's anticipated 
schedule for issuance of the final order for the project, which is 
based on the revised issuance date for the final NEPA document. 
Accordingly, we currently anticipate issuing a final order for the 
project no later than:

Issuance of Final Order: October 21, 2027

    If a schedule change becomes necessary, an additional notice will 
be provided so that interested parties and government agencies are kept 
informed of the project's progress.

    Dated: March 3, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-03704 Filed 3-6-25; 8:45 am]
BILLING CODE 6717-01-P