Tennessee Valley Authority; Sequoyah Nuclear Plant, Unit 2; Exemption
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Issuing agencies
Abstract
The U.S. Nuclear Regulatory Commission (NRC) has issued an exemption in response to a request dated November 27, 2024, from Tennessee Valley Authority. The exemption authorizes a one-time exemption for Sequoyah Nuclear Plant, Unit 2, to allow the use of the less restrictive work hour limitations described in NRC regulations for a 21-day period starting no earlier than January 6, 2025, and no later than January 31, 2025.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.