Notice2024-29097
Oswego Hydro Partners, LP; Notice of Revised Procedural Schedule
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
December 11, 2024
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 89 Issue 238 (Wednesday, December 11, 2024)</title>
</head>
<body><pre>
[Federal Register Volume 89, Number 238 (Wednesday, December 11, 2024)]
[Notices]
[Page 99855]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2024-29097]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 4113-067]
Oswego Hydro Partners, LP; Notice of Revised Procedural Schedule
This notice revises the Federal Energy Regulatory Commission's
(Commission) schedule for processing the relicense application for the
Phoenix Hydroelectric Project No. 4113, which was filed by Oswego Hydro
Partners, LP (Oswego Hydro) on February 27, 2024. On July 8, 2024,
Commission staff issued Scoping Document 1 (SD1), which included an
initial processing schedule with an issuance date of September 2024,
for a public notice indicating that the application is ready for
environmental analysis.
On August 7, 2024, Oswego Hydro notified the Commission that it is
actively engaged in settlement negotiations on potential protection,
mitigation, and enhancement measures at the project. On September 6,
2024, Oswego Hydro filed a letter stating that settlement discussions
with the New York State Department of Environmental Conservation and
the U.S. Fish and Wildlife Service have been productive and the parties
are making progress towards formalizing terms and conditions that would
resolve operational and environmental issues raised by the parties.
Oswego Hydro anticipated filing a Settlement Agreement with the
Commission by the end of 2024. On December 2, 2024, Oswego Hydro filed
an update on the settlement negotiations, stating that fish passage
discussions have been productive and that it now expects to file a
Settlement Agreement in the first quarter of 2025.
To provide additional time for the parties to conduct settlement
negotiations, the application will be processed according to the
following revised schedule.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Notice of Ready for Environmental Analysis May 2025.
Comments, Recommendations, and Agency June 2025.
Terms and Conditions/Prescriptions.
------------------------------------------------------------------------
If a schedule change becomes necessary, an additional notice will
be provided so that interested parties and government agencies are kept
informed of the project's progress.
Dated: December 5, 2024.
Carlos D. Clay,
Acting Deputy Secretary.
[FR Doc. 2024-29097 Filed 12-10-24; 8:45 am]