Notice2024-28410
Commonwealth LNG, LLC; Notice of Schedule for the Preparation of a Supplemental Environmental Impact Statement for the Commonwealth LNG Project
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
December 4, 2024
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 89 Issue 233 (Wednesday, December 4, 2024)</title>
</head>
<body><pre>
[Federal Register Volume 89, Number 233 (Wednesday, December 4, 2024)]
[Notices]
[Pages 96242-96243]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2024-28410]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP19-502-000 and CP19-502-001]
Commonwealth LNG, LLC; Notice of Schedule for the Preparation of
a Supplemental Environmental Impact Statement for the Commonwealth LNG
Project
On November 17, 2022, the Federal Energy Regulatory Commission
(Commission or FERC) issued its Order Granting Authorization Under
Section 3 of the Natural Gas Act (Order) for Commonwealth LNG, LLC's
Commonwealth LNG Project (Project).\1\ On July 16, 2024, the U.S. Court
of Appeals for the District of Columbia Circuit issued an opinion
finding, as relevant here, that FERC failed to properly assess the
cumulative effects of the Project's nitrogen dioxide (NO<INF>2</INF>)
emissions, and remanded the Order to FERC for further proceedings.\2\
---------------------------------------------------------------------------
\1\ Commonwealth LNG, LLC, 181 FERC ] 61,143 (2022), order on
reh'g, 183 FERC ] 61,173 (2023).
\2\ Healthy Gulf v. FERC, 107 F.4th 1033 (D.C. Cir. 2024).
---------------------------------------------------------------------------
Schedule for Environmental Review
This notice identifies the planned schedule for completion of a
supplemental environmental impact statement (SEIS) for the Project to
address the issues related to the Commission's analysis of
NO<INF>2</INF>.\3\
---------------------------------------------------------------------------
\3\ In accordance with the Council on Environmental Quality's
regulations, the unique identification number for documents relating
to this environmental review is SEIS-019-20-000-1732105648. 40 CFR
1501.5(c)(4) (2024).
---------------------------------------------------------------------------
This planned schedule is based on an issuance of the draft SEIS in
February 2025, opening a 45-day comment period.
Issuance of Notice of Availability of the final SEIS May 16, 2025
This notice identifies the Commission's anticipated schedule for
issuance of the final order for the Project, which serves as the
Commission's record of decision. We currently anticipate issuing a
final order for the Project no later than:
Issuance of Final Order July 24, 2025
If a schedule change becomes necessary, additional notice will be
provided.
Project Description
The Project consists of two main components: (1) construction and
operation of the LNG export terminal, which includes six liquefied
natural gas (LNG) plant facilities to liquefy natural gas, six tanks to
store the LNG, an LNG carrier loading/berthing facility (marine
facility), and other appurtenant facilities; and (2) construction and
operation of approximately 3.0 miles of 42-inch-diameter pipeline and
one new meter station to deliver natural gas to the terminal. The
Project would produce 8.4 million metric tonnes per annum of LNG for
export on an average of 156 LNG carriers per year.
Background
On August 20, 2019, as amended July 8, 2021, Commonwealth LNG, LLC
filed an application in Docket No. CP19-502-000 requesting
authorization pursuant to section 3 of the Natural Gas Act (NGA) and
Part 153 of the Commission's regulations to construct and operate a
natural gas liquefaction and export facility, including an NGA section
3 natural gas pipeline, in Cameron Parish, Louisiana.
The Commission issued a Notice of Availability of the Draft
Environmental Impact Statement on March 31, 2022. On September 9, 2022,
the final EIS was issued. As noted above, on November 17, 2022, the
Commission issued an order granting authorization for the
[[Page 96243]]
Project and agreeing with the conclusions presented in the final EIS.
Additional Information
In order to receive notification of the issuance of the SEIS and to
keep track of formal issuances and submittals in specific dockets, the
Commission offers a free service called eSubscription. This service
provides automatic notification of filings made to subscribed dockets,
document summaries, and direct links to the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings, the public is
encouraged to contact OPP at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#ade2fdfdedcbc8dfce83cac2db"><span class="__cf_email__" data-cfemail="d39c838393b5b6a1b0fdb4bca5">[email protected]</span></a>.
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC website (<a href="http://www.ferc.gov">www.ferc.gov</a>). Using the ``eLibrary'' link, select
``General Search'' from the eLibrary menu, enter the selected date
range and ``Docket Number'' excluding the last three digits (i.e.,
CP19-502), and follow the instructions. For assistance with access to
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at <a href="/cdn-cgi/l/email-protection#f1b7b4a3b2be9f9d989f94a28481819e8385b197948392df969e87"><span class="__cf_email__" data-cfemail="ffb9baadbcb0919396919aac8a8f8f908d8bbf999a8d9cd1989089">[email protected]</span></a>. The eLibrary link on the FERC
website also provides access to the texts of formal documents issued by
the Commission, such as orders, notices, and rulemakings.
Dated: November 27, 2024.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2024-28410 Filed 12-3-24; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on December 4, 2024.