Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications; Municipality of Skagway Borough

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
November 29, 2024

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 89 Issue 230 (Friday, November 29, 2024)</title>
</head>
<body><pre>
[Federal Register Volume 89, Number 230 (Friday, November 29, 2024)]
[Notices]
[Pages 94728-94729]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2024-27965]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 15381-000]


Preliminary Permit Application Accepted for Filing and Soliciting 
Comments, Motions To Intervene, and Competing Applications; 
Municipality of Skagway Borough

    On November 13, 2024, the Municipality of Skagway Borough filed an 
application for a preliminary permit, pursuant to section 4(f) of the 
Federal Power Act (FPA), proposing to study the feasibility of the 
Burro Creek Hydroelectric Project (or Project) to be located on Burro 
Creek, two miles southwest of Skagway, Alaska. The sole purpose of a 
preliminary permit, if issued, is to grant the permit holder priority 
to file a license application during the permit term. A preliminary 
permit does not authorize the permit holder to perform any land-
disturbing activities or otherwise enter upon lands or waters owned by 
others without the owners' express permission.
    The proposed project would consist of the following: (1) a 100-
foot-long, 10 foot-high reinforced concrete diversion dam; (2) a 0.5-
acre impoundment with a normal surface elevation of approximately 1,160 
feet above sea level; (3) a 12,300-foot-long, 2-foot-diameter penstock 
buried within an access road; (4) a 40-foot-long, 40-foot-wide 
powerhouse; (5) a 13,300-foot-long access road extending from the dam 
to tidewater at Burro Creek; (6) a 1,000-

[[Page 94729]]

foot-long underground transmission line from powerhouse to tidewater; 
(7) a 2-mile-long submarine cable laid on the floor of Lynn Canal 
extending from tidewater to the Ore dock facility in Skagway; and (8) 
appurtenant facilities. The estimated annual generation of the Project 
would be 24,800 megawatt-hours.
    Applicants Contact: Emily Deach, Municipality of Skagway, P.O. Box 
415, Skagway, AK 99840, (907) 612-8247.
    FERC Contact: Maryam Zavareh at <a href="/cdn-cgi/l/email-protection#3d705c4f445c5013475c4b5c4f58557d5b584f5e135a524b"><span class="__cf_email__" data-cfemail="3a775b48435b5714405b4c5b485f527a5c5f4859145d554c">[email&#160;protected]</span></a>.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at <a href="http://www.ferc.gov/docs-filing/efiling.asp">http://www.ferc.gov/docs-filing/efiling.asp</a>. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at <a href="http://www.ferc.gov/docs-filing/ecomment.asp">http://www.ferc.gov/docs-filing/ecomment.asp</a>. For 
assistance, please contact FERC Online Support at 
<a href="/cdn-cgi/l/email-protection#cb8d8e998884a5a7a2a5ae98bebbbba4b9bf8badaeb9a8e5aca4bd"><span class="__cf_email__" data-cfemail="fcbab9aebfb39290959299af898c8c938e88bc9a998e9fd29b938a">[email&#160;protected]</span></a>, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426. The first page of any filing should include 
docket number.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's website at <a href="http://www.ferc.gov/docs-filing/elibrary.asp">http://www.ferc.gov/docs-filing/elibrary.asp</a>. 
Enter the docket number in the docket number field to access the 
document. For assistance, contact FERC Online Support.

    Dated: November 21, 2024.
Debbie-Anne Reese,
Secretary.
[FR Doc. 2024-27965 Filed 11-27-24; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on November 29, 2024.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.