Notice2024-24802
Black Canyon Hydro, LLC; Notice of Revised Schedule for the Seminoe Pumped Storage Project
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
October 25, 2024
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 89 Issue 207 (Friday, October 25, 2024)</title>
</head>
<body><pre>
[Federal Register Volume 89, Number 207 (Friday, October 25, 2024)]
[Notices]
[Page 85190]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2024-24802]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 14787-004]
Black Canyon Hydro, LLC; Notice of Revised Schedule for the
Seminoe Pumped Storage Project
This notice revises the Federal Energy Regulatory Commission's
(Commission) schedule for processing Black Canyon Hydro, LLC's license
application for the Seminoe Pumped Storage Project. A prior notice
issued on January 10, 2024, identified an anticipated schedule for
issuance of draft and final National Environmental Policy Act (NEPA)
documents and a final order for the project. On September 4, 2024,
Black Canyon Hydro, LLC requested an extension of time to file its
historic properties management plan by October 31, 2024. Commission
staff issued a letter approving the extension of time on September 11,
2024. To account for the additional time needed for Black Canyon Hydro,
LLC to file the required information, the application will be processed
according to the following revised schedule.
Notice of Ready for Environmental Analysis: January 2025.
Draft NEPA Document: September 2025.
Final NEPA Document: April 13, 2026.
In addition, in accordance with title 41 of the Fixing America's
Surface Transportation Act, enacted on December 4, 2015, agencies are
to publish completion dates for all federal environmental reviews and
authorizations. This notice identifies the Commission's anticipated
schedule for issuance of the final order for the project, which is
based on the revised issuance date for the final NEPA document.
Accordingly, we currently anticipate issuing a final order for the
project no later than:
Issuance of Final Order: July 16, 2026.
If a schedule change becomes necessary, an additional notice will
be provided so that interested parties and government agencies are kept
informed of the project's progress.
Dated: October 18, 2024.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2024-24802 Filed 10-24-24; 8:45 am]
BILLING CODE 6717-01-P