Rule2024-24528

Compensation for Reactive Power Within the Standard Power Factor Range

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
November 26, 2024
Effective
January 27, 2025

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Abstract

In this final determination, the Federal Energy Regulatory Commission (Commission) finds that allowing transmission providers to charge transmission customers for a generating facility's provision of reactive power within the standard power factor range is unjust and unreasonable. The Commission, therefore, is revising Schedule 2 of its pro forma open-access transmission tariff (OATT), section 9.6.3 of its pro forma large generator interconnection agreement (LGIA), and section 1.8.2 of its pro forma small generator interconnection agreement (SGIA) to prohibit the inclusion in transmission rates of any charges related to the provision of reactive power within the standard power factor range by generating facilities.

Full Text

<html>
<head>
<title>Federal Register, Volume 89 Issue 228 (Tuesday, November 26, 2024)</title>
</head>
<body><pre>
[Federal Register Volume 89, Number 228 (Tuesday, November 26, 2024)]
[Rules and Regulations]
[Pages 93410-93456]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2024-24528]



[[Page 93409]]

Vol. 89

Tuesday,

No. 228

November 26, 2024

Part II





Department of Energy





-----------------------------------------------------------------------





Federal Energy Regulatory Commission





-----------------------------------------------------------------------





18 CFR Part 35





Compensation for Reactive Power Within the Standard Power Factor Range; 
Final Rule

Federal Register / Vol. 89, No. 228 / Tuesday, November 26, 2024 / 
Rules and Regulations

[[Page 93410]]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

18 CFR Part 35

[Docket No. RM22-2-000; Order No. 904]


Compensation for Reactive Power Within the Standard Power Factor 
Range

AGENCY: Federal Energy Regulatory Commission.

ACTION: Final determination.

-----------------------------------------------------------------------

SUMMARY: In this final determination, the Federal Energy Regulatory 
Commission (Commission) finds that allowing transmission providers to 
charge transmission customers for a generating facility's provision of 
reactive power within the standard power factor range is unjust and 
unreasonable. The Commission, therefore, is revising Schedule 2 of its 
pro forma open-access transmission tariff (OATT), section 9.6.3 of its 
pro forma large generator interconnection agreement (LGIA), and section 
1.8.2 of its pro forma small generator interconnection agreement (SGIA) 
to prohibit the inclusion in transmission rates of any charges related 
to the provision of reactive power within the standard power factor 
range by generating facilities.

DATES: Effective January 27, 2025.

FOR FURTHER INFORMATION CONTACT: 
Paul Robinson (Technical Information), Office of Energy Market 
Regulation, 888 First Street NE, Washington, DC 20426, (202) 502-8460, 
<a href="/cdn-cgi/l/email-protection#f4a4958198daa69b969d9a879b9ab492918697da939b82"><span class="__cf_email__" data-cfemail="eebe8f9b82c0bc818c87809d8180ae888b9c8dc0898198">[email&#160;protected]</span></a>
Jennifer Enos (Legal Information), Office of the General Counsel, 888 
First Street NE, Washington, DC 20426, (202) 502-6247, 
<a href="/cdn-cgi/l/email-protection#86cce3e8e8efe0e3f4a8c3e8e9f5c6e0e3f4e5a8e1e9f0"><span class="__cf_email__" data-cfemail="5c16393232353a392e721932332f1c3a392e3f723b332a">[email&#160;protected]</span></a>

SUPPLEMENTARY INFORMATION:

Table of Contents

------------------------------------------------------------------------
                                                               Paragraph
                                                                 Nos.
------------------------------------------------------------------------
I. Background...............................................           3
    A. Historical Framework Including Order Nos. 888 and               3
     2003...................................................
    B. Notice of Inquiry and Notice of Proposed Rulemaking..          16
II. Discussion..............................................          20
    A. Need for Reform......................................          27
    1. Comments.............................................          29
    2. Commission Determination.............................          49
    B. Cost of Producing Reactive Power.....................          62
    1. Comments.............................................          66
    2. Commission Determination.............................          89
    C. Cost Recovery........................................         109
    1. Comments.............................................         113
    2. Commission Determination.............................         141
    D. Reliability..........................................         155
    1. Comments.............................................         157
    2. Commission Determination.............................         165
    E. Investment...........................................         170
    1. Comments.............................................         171
    2. Commission Determination.............................         178
    F. Additional Comments..................................         187
    1. Comments.............................................         187
    2. Commission Determination.............................         201
III. Compliance Procedures..................................         202
    A. Revisions to Eliminate Compensation for Reactive              202
     Power Supply Within the Standard Power Factor Range....
    1. Revise Schedule 2 of the Commission's Pro Forma OATT.         203
    2. Revise Section 9.6.3 of the Pro Forma Large Generator         204
     Interconnection Agreement..............................
    3. Revise Section 1.8.2 of the Pro Forma Small Generator         205
     Interconnection Agreement..............................
    4. Compliance Procedures................................         206
    B. Transition Period....................................         207
    1. Comments.............................................         210
    2. Commission Determination.............................         224
IV. Information Collection Statement........................         228
V. Environmental Analysis...................................         242
VI. Regulatory Flexibility Act..............................         243
VII. Document Availability..................................         247
VIII. Effective Date and Congressional Notification.........         250
------------------------------------------------------------------------

    1. In this final determination, pursuant to section 206 of the 
Federal Power Act (FPA), the Federal Energy Regulatory Commission finds 
that allowing public utility transmission providers (transmission 
providers) \1\ to charge transmission customers for a generating 
facility's provision of reactive power within the standard power factor 
range is unjust and unreasonable. The Commission, therefore, is 
revising Schedule 2 of the

[[Page 93411]]

Commission's pro forma OATT to prohibit transmission providers from 
including in their transmission rates any charges associated with the 
provision of reactive power within the standard power factor range from 
generating facilities and requiring transmission providers to make 
compliance filings to update Schedule 2 of their OATTs accordingly.\2\ 
The final determination further revises the Commission's pro forma LGIA 
and pro forma SGIA to remove the requirement that a transmission 
provider pay an interconnection customer for reactive power within the 
standard power factor range if the transmission provider pays its own 
or affiliated generating facilities for the same service, and the final 
determination requires transmission providers to make compliance 
filings to update their pro forma interconnection agreements 
accordingly. As a result of this final determination, transmission 
providers will be required to pay an interconnection customer for 
reactive power only when the transmission provider requests or directs 
the interconnection customer to operate its facility outside the 
standard power factor range set forth in its interconnection agreement.
---------------------------------------------------------------------------

    \1\ Section 201(e) of the FPA, 16 U.S.C. 824(e), defines 
``public utility'' to mean ``any person who owns or operates 
facilities subject to the jurisdiction of the Commission under this 
subchapter.'' As stated in the Order No. 888 pro forma OATT, 
``transmission provider'' is a ``public utility (or its Designated 
Agent) that owns, controls, or operates facilities used for the 
transmission of electric energy in interstate commerce and provides 
transmission service under the Tariff.'' Promoting Wholesale 
Competition Through Open Access Non-Discriminatory Transmission 
Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. & 
Transmitting Utils., Order No. 888, FERC Stats. & Regs. ] 31,036 
(1996) (cross-referenced at 75 FERC ] 61,080), order on reh'g, Order 
No. 888-A, FERC Stats. & Regs. ] 31,048 (cross-referenced at 78 FERC 
] 61,220), order on reh'g, Order No. 888-B, 81 FERC ] 61,248 (1997), 
order on reh'g, Order No. 888-C, 82 FERC ] 61,046 (1998), aff'd in 
relevant part sub nom. Transmission Access Pol'y Study Grp. v. FERC, 
225 F.3d 667 (D.C. Cir. 2000), aff'd sub nom. N.Y. v. FERC, 535 U.S. 
1 (2002); Pro forma OATT section I.1 (Definitions). The term 
``transmission provider'' includes a public utility transmission 
owner when the transmission owner is separate from the transmission 
provider, as is the case in regional transmission organizations 
(RTO) and independent system operators (ISO).
    \2\ Operating ``inside the standard power factor range'' refers 
to a generating facility providing reactive power within the power 
factor range set forth in the generating facility's interconnection 
agreement when the unit is online and synchronized to the 
transmission system. The standard power factor range is sometimes 
referred to as the ``deadband.'' Compensation for Reactive Power 
Within the Standard Power Factor Range, Notice of Proposed 
Rulemaking, 89 FR 21,454 (Mar. 28, 2024) (cross-referenced at 186 
FERC ] 61,203, at P 2 n.1) (NOPR).
---------------------------------------------------------------------------

    2. As discussed below, the Commission has a statutory duty to 
ensure that transmission rates are and remain just and reasonable. We 
find that this reform will ensure that transmission providers do not 
pass onto transmission customers unjust and unreasonable charges that 
lack a sufficient economic basis or justification and yield no 
commensurate benefit for ratepayers.

I. Background

A. Historical Framework Including Order Nos. 888 and 2003

    3. Almost all bulk electric power is generated, transported, and 
consumed in alternating current (AC) networks. Reactive power, which is 
measured in megavolt-amperes reactive (MVAr),\3\ is a critical 
component of operating an AC electricity system and is required to 
control system voltage within appropriate ranges for efficient and 
reliable operation of the transmission system. Reactive power supports 
the voltages that must be controlled to provide for delivery of real 
power and for system reliability. Reactive power can be produced or 
absorbed \4\ by generating facilities, power electronic equipment such 
as flexible AC transmission system devices, transmission lines and 
equipment, and load. As relevant here, generating facilities must 
either produce or absorb reactive power for the transmission system to 
maintain voltage levels required to reliably supply real power from 
generation to load.
---------------------------------------------------------------------------

    \3\ MVAr is the typical unit of measurement for reactive power.
    \4\ A generating facility's leading reactive power indicates its 
ability to absorb reactive power, and its lagging reactive power 
indicates its ability to produce reactive power.
---------------------------------------------------------------------------

    4. In Order No. 888, the Commission required that reactive supply 
and voltage control from generating facilities be offered as a discrete 
ancillary service by transmission providers and, to the extent 
feasible, charged for on the basis of the amount required.\5\ The 
Commission explained that there are two ways of supplying reactive 
power and controlling voltage. One is to install facilities as part of 
the transmission system, the cost of which is part of the cost of basic 
transmission service. The second is to use generating facilities to 
supply reactive power and voltage control, which must be unbundled from 
basic transmission service.
---------------------------------------------------------------------------

    \5\ Order No. 888, FERC Stats. & Regs. ] 31,036, at 31,705-07 & 
n.359.
---------------------------------------------------------------------------

    5. With respect to compensation, the Commission stated that the 
transmission provider's ``rates for ancillary services should be cost-
based.'' \6\ The Commission expected, however, that transmission 
customers would be able to change the amount of reactive power service 
they required. The Commission also identified the possibility that 
reactive power could potentially be supplied by ``a competitive market 
for such service'' if ``technology or industry changes'' made such a 
market possible.\7\
---------------------------------------------------------------------------

    \6\ Id. at 31,720.
    \7\ Id. at 31,707 & n.359.
---------------------------------------------------------------------------

    6. The Commission's policy on reactive power compensation has 
evolved since issuing Order No. 888 in 1996.\8\ In Order No. 2003, the 
Commission adopted a standard agreement for the interconnection of 
large generating facilities (the pro forma LGIA), and specifically 
addressed the circumstances under which a transmission provider must 
pay an interconnection customer for reactive power depending upon 
whether such reactive power was inside or outside the standard power 
factor range.\9\ This standard agreement included the requirement that 
interconnection customers maintain a composite power delivery at a 
continuous rate of power output at the generating facility's point of 
interconnection at a power factor within the range of 0.95 leading to 
0.95 lagging when synchronized to the transmission system, unless the 
transmission provider has established a different power factor 
range.\10\ Order No. 2003 required that a transmission provider 
compensate an interconnection customer for reactive power when the 
transmission provider requests that the interconnection customer 
operate its generating facility outside the established power factor 
range. With respect to reactive power within the established power 
factor range, the Commission concluded in Order No. 2003 that the 
interconnection customer should not be compensated for reactive power 
when operating within the range established in the interconnection 
agreement because doing so ``is only meeting [the generating 
facility's] obligation.'' \11\ However, in Order No. 2003-A, the 
Commission clarified that ``if the Transmission Provider pays its own 
or its affiliated generators for reactive power within the established 
range, it must also pay the Interconnection Customer.'' \12\ This 
standard is generally referred to as the ``comparability standard.'' 
\13\
---------------------------------------------------------------------------

    \8\ Id. at 31,705-07 & n.359.
    \9\ Standardization of Generator Interconnection Agreements & 
Procs., Order No. 2003, 68 FR 49846 (Aug. 19, 2003), 104 FERC ] 
61,103, at P 546 (2003), order on reh'g, Order No. 2003-A, 69 FR 
15932 (Mar. 26, 2004), 106 FERC ] 61,220, order on reh'g, Order No. 
2003-B, 70 FR 265 (Jan. 4, 2005), 109 FERC ] 61,287 (2004), order on 
reh'g, Order No. 2003-C, 70 FR 37661 (June 30, 2005), 111 FERC ] 
61,401 (2005), aff'd sub nom. Nat'l Ass'n of Regul. Util. Comm'rs v. 
FERC, 475 F.3d 1277 (D.C. Cir. 2007).
    \10\ The power factor is the ratio of a generating facility's 
real power to its apparent power, where apparent power is the total 
power output of the system (both real and reactive power). Power 
factors can range from 1.0 to 0.0, with 1.0 representing only real 
power and 0.0 representing only reactive power.
    \11\ Order No. 2003, 104 FERC ] 61,103 at P 546.
    \12\ Order No. 2003-A, 106 FERC ] 61,220 at P 416. Order No. 
2003-A also exempted wind generating facilities from maintaining the 
established power factor range. Id. P 34.
    \13\ In Order No. 2006, the Commission adopted identical power 
factor and compensation requirements for small generating facilities 
(those with a capacity of 20 MW or less) and initially exempted 
small wind generating facilities from the reactive power requirement 
before Order No. 827 eliminated such exemptions. Reactive Power 
Requirements for Non-Synchronous Generation, Order No. 827, 81 FR 
40793 (June 23, 2016), 155 FERC ] 61,277, order on clarification and 
reh'g, 157 FERC ] 61,003 (2016); Standardization of Small Generator 
Interconnection Agreements & Procs., Order No. 2006, 111 FERC ] 
61,220, order on reh'g, Order No. 2006-A, 70 FR 71760 (Nov. 30, 
2005), 113 FERC ] 61,195 (2005), order granting clarification, Order 
No. 2006-B, 71 FR 42587 (July 27, 2006), 116 FERC ] 61,046 (2006).

---------------------------------------------------------------------------

[[Page 93412]]

    7. Order No. 661 established technical requirements for 
interconnecting large wind resources and maintained the exemption from 
providing reactive power, except where the transmission provider 
showed, through a system impact study, that reactive power capability 
was required to ensure safety or reliability.\14\ In Order No. 
2006,\15\ the Commission adopted identical power factor and 
compensation requirements for small generating facilities (facilities 
that have a capacity of no more than 20 megawatts (MW)) but exempted 
small wind generating facilities from the reactive power requirement. 
Subsequently, in Order No. 827,\16\ the Commission eliminated the 
exemptions for both small and large wind generating facilities, thus 
requiring those facilities to provide reactive power. The Commission 
explained that it had previously exempted wind generators from the 
uniform reactive power requirement because, historically, the costs to 
design and build a wind generator that could provide reactive power 
were high and could have created an obstacle to the development of wind 
generation. But the Commission found in Order No. 827 that, due to 
technological advancements since the establishment of those exemptions, 
the cost of providing reactive power no longer presented an obstacle to 
the development of wind generation, and therefore found that the 
exemptions had become unjust and unreasonable.\17\ The Commission 
therefore required all newly interconnecting non-synchronous generating 
facilities to provide reactive power within the range of 0.95 leading 
to 0.95 lagging at the high-side of the generator substation 
transformer as a condition of interconnection.
---------------------------------------------------------------------------

    \14\ Interconnection for Wind Energy, Order No. 661, 70 FR 34993 
(June 16, 2005), 111 FERC ] 61,353, order on reh'g, Order No. 661-A, 
70 FR 75005 (Dec. 19, 2005), 113 FERC ] 61,254 (2005).
    \15\ Order No. 2006, 111 FERC ] 61,220.
    \16\ Order No. 827, 155 FERC ] 61,277.
    \17\ See also PJM Interconnection, L.L.C., 151 FERC ] 61,097, at 
P 28 (2015) (finding that, since Order No. 661, the cost of the 
technology necessary for a non-synchronous resource to provide 
reactive power has lessened such that the cost of installing 
equipment that is capable of providing reactive power is comparable 
to the costs of a traditional generator).
---------------------------------------------------------------------------

    8. In sum, ``Order Nos. 2003 and 2003-A establish a reactive power 
compensation policy that, in the first instance, treats the provision 
of reactive power inside the [standard power factor range] as an 
obligation of good utility practice rather than as a compensable 
service and permits compensation inside the [standard power factor 
range] only as a function of comparability.'' \18\ ``Put differently, 
reactive support by generating facilities operating within the standard 
power factor range ensures that when these facilities inject real 
power--the product that their facilities exist to create and sell--onto 
the grid under normal conditions, they can do their part to maintain 
adequate voltages and to not threaten reliability.'' \19\ By contrast, 
reactive power provided outside of the standard power factor range is 
considered an ancillary service for transmitting power across the 
transmission system to serve load,\20\ and thus, the Commission has 
required compensation for such service.
---------------------------------------------------------------------------

    \18\ Bonneville Power Admin. v. Puget Sound Energy, Inc., 120 
FERC ] 61,211 (2007) (BPA), order denying reh'g and granting 
clarification, 125 FERC ] 61,273, at P 18 (2008) (BPA Rehearing 
Order). See also BPA Rehearing Order, 125 FERC ] 61,273 at P 15 & 
n.24 (``[N]either affiliated nor non-affiliated generators have an 
inherent right to any compensation for reactive power inside the 
deadband.''). Accord., Midcontinent Indep. Sys. Operator, Inc., 182 
FERC ] 61,033 (MISO), order on reh'g, 184 FERC ] 61,022, at P 23 
(2023) (MISO Rehearing Order); Sw. Power Pool, Inc., 119 FERC ] 
61,199 (SPP), order on reh'g, Sw. Power Pool, Inc., 121 FERC ] 
61,196, at 61,968 (2007) (SPP Order on Rehearing) (``[R]eactive 
power is required for an interconnecting generator to deliver its 
power and reactive power produced within the deadband and is, 
therefore, generally not compensable.''); Mich. Elec. Transmission 
Co., 97 FERC ] 61,187, at 61,852-53 (2001) (METC Rehearing Order) 
(``Providing reactive power within design limitations is not 
providing an ancillary service; it is simply ensuring that a 
generator lives up to its obligations.''); Consumers Energy Co., 94 
FERC ] 61,230, at 61,834 (2000) (affirming the Commission's 
rejection of generators' request for reactive power compensation 
when operating within a facility's reactive power design limitation, 
stating that as a condition of interconnecting to the transmission 
provider's system, ``to ensure system security,'' the generator was 
required to provide equipment, ``at its own cost, to meet its 
reactive power obligations as provided for in [its interconnection 
agreement].''(emphasis added)); cf. Dynegy Midwest Generation, Inc., 
125 FERC ] 61,280, at P 16 (2008) (``Reactive power is a localized 
service that is quickly used by transmission system components and 
cannot be transported over long distances.'').
    \19\ MISO Rehearing Order, 184 FERC ] 61,022 at P 23.
    \20\ See, e.g., id. at PP 23-24 (citing METC Rehearing Order, 97 
FERC at 61,852-53).
---------------------------------------------------------------------------

    9. Consistent with Order Nos. 2003 and 2003-A and Commission 
precedent that pre-dated those Orders, the Commission has permitted 
transmission providers to eliminate separate compensation for 
generating facilities providing reactive power within the standard 
power factor range.\21\ In these cases, the Commission affirmed its 
determination that the provision of reactive power within the standard 
power factor range is not compensable except as a matter of 
comparability. For example, in BPA, the Commission granted a complaint 
filed by Bonneville Power Administration (BPA) arguing that the rate 
schedules of certain independent power producers (IPP) for reactive 
power within the standard power factor range, often referred to as a 
``deadband,'' were no longer just and reasonable given BPA's decision 
to no longer pay its own or affiliated generators for providing this 
service.\22\ The Commission found that ``Commission policy clearly 
allows BPA to discontinue paying all its merchants for inside the 
deadband reactive power service,'' explaining that ``[t]he Commission's 
policy is not new; we confirmed it in Order No. 2003, when we stated 
that an interconnecting generator `should not be compensated for 
reactive power when operating its Generating Facility within the 
established power factor range, since it is only meeting its 
obligation.'' \23\
---------------------------------------------------------------------------

    \21\ See, e.g., MISO, 182 FERC ] 61,033 at PP 52-53; MISO 
Rehearing Order, 184 FERC ] 61,022 at PP 26-27; Pub. Serv. Co. of 
N.M., 178 FERC ] 61,088, at PP 29-31 (2022) (PNM); Nev. Power Co., 
179 FERC ] 61,103, at PP 20-21 (2022); BPA, 120 FERC ] 61,211 at P 
20; E.ON U.S. LLC, 119 FERC ] 61,340, at P 15 (2007); Entergy 
Servs., Inc., 113 FERC ] 61,040, at P 38 (2005).
    \22\ BPA, 120 FERC ] 61,211 at PP 19-20; BPA Rehearing Order, 
125 FERC ] 61,273 at PP 10-11.
    \23\ BPA, 120 FERC ] 61,211 at PP 19-20 (citing Order No. 2003, 
FERC Stats. & Regs. ] 31,146 at P 546); METC Rehearing Order, 97 
FERC at 61,852 (``Providing reactive power within design limitations 
is not providing an ancillary service; it is simply ensuring that a 
generator lives up to its obligations.'').
---------------------------------------------------------------------------

    10. The Commission has also found that a transmission provider's 
decision to end compensation for reactive power within the standard 
power factor range does not compromise a generating facility's ability 
to recover costs that it may incur in producing reactive power within 
this range.\24\ For example, the Commission has observed that 
generating facilities ``may be able to recover the costs for reactive 
power within the deadband in other ways--such as through higher power 
sales rates of their own.'' \25\ In response to arguments by certain 
independent power producers that such recovery is infeasible because of 
competition, the Commission has found that ``since the incremental cost 
of reactive power service within the deadband is minimal, the 
infeasibility argument lacks plausibility. The purpose for which 
generation assets are built (including reactive power capability to 
maintain voltage levels for generation entering the grid) is to make 
sales of real power.'' \26\
---------------------------------------------------------------------------

    \24\ Id. PP 19-22.
    \25\ Id. P 21 (citing Sw. Power Pool, Inc., 119 FERC ] 61,199, 
at P 39).
    \26\ Id.
---------------------------------------------------------------------------

    11. The Commission made similar findings in MISO, wherein it 
accepted an FPA section 205 application by

[[Page 93413]]

Midcontinent Independent System Operator, Inc. (MISO) transmission 
owners to end generator compensation for the provision of reactive 
power within the standard power factor range.\27\ In accepting MISO 
transmission owners' proposal, the Commission reiterated its 
longstanding policy ``that the provision of reactive power within the 
standard power factor range is, in the first instance, an obligation of 
the interconnecting generator and good utility practice,'' such that 
``MISO [transmission owners] do not have an obligation to continue to 
compensate an independent generator for reactive power within the 
standard power factor range when its own or affiliated generators are 
no longer being compensated.'' \28\ The Commission also rejected any 
reliance arguments, reasoning in part that the provision of reactive 
power within the standard power factor range required little or no 
incremental investment given that, for both synchronous and non-
synchronous generating facilities,\29\ the same equipment is used for 
the production of real power and reactive power.\30\ In addition, the 
Commission found that generating facilities have other opportunities, 
beyond Schedule 2, to seek to recover their costs of providing reactive 
power.\31\
---------------------------------------------------------------------------

    \27\ MISO, 182 FERC ] 61,033 at P 53 (``Bearing in mind that the 
provision of reactive power within the standard power factor range 
is, in the first instance, an obligation of the interconnecting 
generator and good utility practice, MISO [transmission owners] do 
not have an obligation to continue to compensate an independent 
generator for reactive power within the standard power factor range 
when its own or affiliated generators are no longer being 
compensated.'' (citation omitted)); see also PNM, 178 FERC ] 61,088 
at PP 29, 33 (accepting PNM's revisions to eliminate compensation 
for reactive service under Schedule 2 and rejecting generators' 
arguments that it is ``just and reasonable for it to be compensated 
for investments made'' to provide reactive support consistent with 
interconnection requirements even though PNM elected to no longer 
pay its own or affiliated generators for such reactive power).
    \28\ MISO, 182 FERC ] 61,033 at P 53. The Commission found 
``those protests that challenge these well-established policies to 
be collateral attacks on these earlier determinations.'' Id.
    \29\ Synchronous generating facilities (e.g., coal, gas, nuclear 
resources) produce electricity in sync with the transmission system 
at the system frequency. Non-synchronous generating facilities 
(e.g., solar, wind, battery storage resources) produce electricity 
that is initially not in sync with the transmission system and use 
inverters to convert their electrical output to synchronize with the 
transmission system. See FERC, Payment for Reactive Power, 7 (Apr. 
22, 2014) (2014 Staff Report), <a href="https://www.ferc.gov/sites/default/files/2020-05/04-11-14-reactive-power.pdf">https://www.ferc.gov/sites/default/files/2020-05/04-11-14-reactive-power.pdf</a>.
    \30\ MISO Rehearing Order, 184 FERC ] 61,022 at PP 29-30 (citing 
S. Co. Servs., Inc., 80 FERC ] 61,318, at 62,091 (1997) (noting also 
that the primary function of a generating plant is to produce real 
power; thus, if costs were allocated based on the ``predominant'' 
function of the equipment, ``all of the costs of generation would 
thus be assigned to real power production and there would be no 
basis for any separate reactive power charge''); BPA, 120 FERC ] 
61,211 at P 21 (finding that the incremental cost of reactive power 
service within the standard power factor range is minimal); METC 
Rehearing Order, 97 FERC at 61,852-53 (``[R]eactive power provided, 
not as an ancillary service, but rather as a `no cost' service 
within reactive design limitations, may therefore, be provided 
without compensation.'').
    \31\ MISO Rehearing Order, 184 FERC ] 61,022 at PP 40-42; SPP, 
119 FERC ] 61,199 at P 39 (stating that IPPs ``are free to negotiate 
rates that they charge their customers for real power that are 
sufficient to compensate them for any costs that they may incur in 
producing reactive power within their deadbands, just as affiliated 
generators may seek to negotiate rates that they charge their 
customers that are sufficient to compensate them for the costs of 
any reactive power that they provide within their deadbands.'').
---------------------------------------------------------------------------

    12. Consistent with Order Nos. 2003 and 2003-A and other Commission 
precedent, multiple RTOs/ISOs and non-RTO/ISO transmission providers 
have elected not to compensate generating facilities for providing 
reactive power within the standard power factor range under Schedule 2 
of their OATTs.\32\
---------------------------------------------------------------------------

    \32\ See, e.g., MISO, 182 FERC ] 61,033 at PP 52-53; MISO 
Rehearing Order, 184 FERC ] 61,022 at P 26; PNM, 178 FERC ] 61,088 
at PP 29-31; Nev. Power Co., 179 FERC ] 61,103 at PP 20-21; BPA, 120 
FERC ] 61,211 at P 20; E.ON U.S. LLC, 119 FERC ] 61,340 at P 15; 
Entergy Servs., Inc., 113 FERC ] 61,040 at P 38.
---------------------------------------------------------------------------

    13. Of the six Commission-jurisdictional RTOs/ISOs, only three 
currently compensate generating facilities for reactive power provided 
within the standard power factor range. Generating facilities in PJM 
Interconnection, L.L.C. (PJM) \33\ generally use the cost-based AEP 
Methodology to calculate cost-of-service rates for the production of 
reactive power.\34\ Because the same generation equipment contributes 
to the production of both real power and reactive power, the AEP 
Methodology allocates the costs of each piece of equipment to real 
power service and reactive power service by assigning the cost of each 
piece of equipment to either real power service, reactive power 
service, or both. ISO New England Inc. (ISO-NE) \35\ and New York 
Independent System Operator, Inc. (NYISO) \36\ compensate generating 
facilities for reactive power under flat rate designs that are adjusted 
for inflation.\37\
---------------------------------------------------------------------------

    \33\ PJM Interconnection, L.L.C., Intra-PJM Tariffs, OATT 
Schedule 2, (Reactive Supply and Voltage Control from Generation or 
Other Sources Service) (4.0.0).
    \34\ The AEP Methodology derives its name from Opinion No. 440, 
where the Commission approved AEP's, a vertically integrated 
utility, method for calculating the costs of synchronous generation 
equipment associated with the production of reactive power. See Am. 
Elec. Power Serv. Corp., Opinion No. 440, 88 FERC ] 61,141 (1999), 
order on reh'g, 92 FERC ] 61,001 (2000). In WPS Westwood, the 
Commission recommended that all generating facilities that have 
actual cost data and support documentation use the AEP Methodology. 
See WPS Westwood Generation, LLC, 101 FERC ] 61,290, at P 14 (2002).
    \35\ ISO New England Inc., ISO New England Inc. Transmission, 
Markets and Services Tariff, Schedule 2 (Reactive Supply and Voltage 
Control Service) (8.0.0).
    \36\ New York Independent System Operator, Inc., NYISO Tariffs, 
NYISO OATT, Sec.  6.2 OATT Schedule 2 (Charges For Voltage Support 
Service) (6.0.0).
    \37\ Both ISO-NE and NYISO proposed their respective reactive 
power capability compensation mechanisms pursuant to section 205 
filings. See ISO New England Inc., 122 FERC ] 61,056, at P 1 (2008) 
(settling, in part, for a new flat rate in $/kVAR-yr). N.Y. Indep. 
Sys. Operator, Inc., Docket No. ER02-617-000 (Feb. 5, 2002) 
(delegated order accepting NYISO's amended Rate Schedule 2 of the 
Market Administration and Control Area Services Tariff).
---------------------------------------------------------------------------

    14. California Independent System Operator Corporation (CAISO),\38\ 
Southwest Power Pool, Inc. (SPP),\39\ and MISO \40\ do not pay 
separately for reactive power within the standard power factor range.
---------------------------------------------------------------------------

    \38\ CAISO never provided compensation for reactive power within 
the standard power factor range. See Cal. Indep. Sys. Operator 
Corp., 160 FERC ] 61,035, at P 7 (2017) (explaining that CAISO 
considered the possibility of compensating generating facilities for 
reactive power in its stakeholder process, but decided against it, 
reasoning that the ability to provide reactive power is part of a 
generator's fixed costs, which are recovered through power purchase 
agreements).
    \39\ SPP, 119 FERC ] 61,199 at P 30.
    \40\ MISO, 182 FERC ] 61,033 at PP 52-66; MISO Rehearing Order, 
184 FERC ] 61,022 at PP 23-55.
---------------------------------------------------------------------------

    15. Outside the RTOs/ISOs, transmission providers that pay for the 
provision of reactive power within the standard power factor range 
generally use the AEP Methodology to set reactive power compensation on 
an individual generating facility basis. Many non-RTO/ISO transmission 
providers do not pay separately for reactive power provided within the 
standard power factor range.\41\
---------------------------------------------------------------------------

    \41\ See, e.g., Arizona Public Service Company, FERC Electric 
Tariff Vol. No. 2, Schedule 2 (Reactive Supply and Voltage Control 
from Generation or Other Sources Service) (6.0.0) (``This service 
will be provided at no charge until [Arizona Public Service Company] 
has developed a rate that has been filed with the Commission and 
allowed to be implemented; however, Transmission Customers taking 
service at transmission voltage levels shall be responsible for 
maintaining a power factor of <plus-minus> 95.0%, and Transmission 
Customers taking service at distribution voltage levels shall 
maintain a power factor of not less than 90% lagging but in no event 
leading, unless agreed to by [Arizona Public Service Company].''); 
Public Service Company of New Mexico, PNM Open Access Transmission 
Tariff, Schedule 2 (Reactive Supply and Voltage Control from 
Generation or Other Sources Service) (2.1.0) (``As of October 1, 
2021, the Effective Date of this Schedule 2, the Transmission 
Provider is not charging for Reactive Supply and Voltage Control 
from Generation or Other Sources Service from its own resources. As 
a result, there will be no separate charge for such service.'').

---------------------------------------------------------------------------

[[Page 93414]]

B. Notice of Inquiry and Notice of Proposed Rulemaking

    16. On November 18, 2021, the Commission issued a Notice of Inquiry 
(NOI) \42\ in this proceeding, seeking comment on various issues 
regarding reactive power compensation and market design as a result of 
the significant changes that have taken place in the electric industry 
in the last two decades, including changes in the generation resource 
mix and a general shift away from cost-of-service rates for generating 
facilities selling into Commission-jurisdictional markets. Generally, 
the Commission sought to ``examine whether the current regime for 
reactive power capability compensation requires revisions to ensure 
that payments for reactive power capability accurately reflect the 
costs associated with reactive power capability.'' \43\
---------------------------------------------------------------------------

    \42\ Reactive Power Capability Compensation, Notice of Inquiry, 
177 FERC ] 61,118 (2021) (NOI).
    \43\ Id. P 19.
---------------------------------------------------------------------------

    17. On March 21, 2024, the Commission issued a NOPR in this same 
proceeding. Based on a review of the comments submitted in response to 
the Commission's NOI in the instant docket, as well as the Commission's 
experience in the years since the issuance of Order Nos. 2003 and 2003-
A, the NOPR preliminarily found that where transmission providers 
require transmission customers to pay for the provision of reactive 
power within the standard power factor range, transmission rates may be 
unjust and unreasonable, as they include costs without a sufficient 
economic basis or justification. In support of such preliminary 
finding, the NOPR explained that generating facilities provide reactive 
power within the standard power factor range at no cost or de minimis 
cost, and that providing reactive power within the standard power 
factor range is already an obligation of the generating facility as an 
interconnection customer and consistent with good utility practice.\44\ 
The NOPR also stated that current compensation may result in undue 
compensation or other market distortions. The NOPR proposed, pursuant 
to FPA section 206,\45\ that a just and reasonable replacement rate was 
to prohibit transmission providers from including in their transmission 
rates any charges associated with the supply of reactive power within 
the standard power factor range from a generating facility.
---------------------------------------------------------------------------

    \44\ Real power, which accomplishes useful work (e.g., runs 
motors), is typically measured in MWs.
    \45\ 16 U.S.C. 824e.
---------------------------------------------------------------------------

    18. Specifically, the NOPR proposed to add the following sentence 
to the end of Schedule 2 of the pro forma OATT: \46\ ``However, such 
rates shall not include compensation to generating facilities for the 
supply of reactive power within the power factor range specified in its 
interconnection agreement.'' Second, the NOPR proposed to remove the 
following clause from section 9.6.3 of the pro forma LGIA: \47\ 
``provided that if Transmission Provider pays its own or affiliated 
generators for reactive power service within the specified range, it 
must also pay Interconnection Customer.'' Third, the NOPR proposed to 
remove the following sentence from section 1.8.2 of the pro forma SGIA: 
\48\ ``In addition, if the Transmission Provider pays its own or 
affiliated generators for reactive power service within the specified 
range, it must also pay the Interconnection Customer.''
---------------------------------------------------------------------------

    \46\ See pro forma OATT, Schedule 2.
    \47\ See pro forma LGIA, Sec.  9.6.3.
    \48\ See pro forma SGIA, Sec.  1.8.2.
---------------------------------------------------------------------------

    19. Comments on the NOPR were due on June 26, 2024. Thirty-one 
parties filed comments.\49\ Comments were submitted by RTOs/ISOs and 
other transmission providers, generating facilities, generation 
developers, transmission owners, load-serving entities (LSE), 
Monitoring Analytics, LLC, acting in its capacity as the Independent 
Market Monitor for PJM (PJM IMM), trade associations representing 
specific generation technologies, and consumer advocates. Of these, and 
with few exceptions, transmission owners, LSEs, the PJM IMM, 
independent filers,\50\ and consumer advocates supported or did not 
oppose the NOPR proposal to eliminate compensation in the standard 
power factor range,\51\ while generating facilities, generation 
developers, and trade associations representing specific generation 
technologies oppose the NOPR proposal.\52\
---------------------------------------------------------------------------

    \49\ See app. A.
    \50\ C T Gaunt states that reactive power cannot be delivered 
and also that it cannot be lost in transmission through a 
transformer or power system. Thus, C T Gaunt claims that there are 
no grounds for arguing against the Commission's determination in the 
NOPR. C T Gaunt Reply Comments at 2-3.
    \51\ American Electric Power Service Corporation (AEP) (on 
behalf of itself and its affiliates, including Appalachian Power 
Company, Indiana Michigan Power Company, Kentucky Power Company, 
Kingsport Power Company, Ohio Power Company, Wheeling Power Company, 
Public Service Company of Oklahoma, Southwestern Electric Power 
Company, AEP Appalachian Transmission Company, Inc., AEP Indiana 
Michigan Transmission Company, Inc., AEP Kentucky Transmission 
Company, Inc., AEP Ohio Transmission Company, Inc., AEP West 
Virginia Transmission Company, Inc., AEP Oklahoma Transmission 
Company, Inc., and AEP Southwestern Transmission Company, Inc.); 
Ameren Service Company (Ameren) (on behalf of Ameren Illinois 
Company d/b/a Ameren Illinois, Union Electric Company d/b/a Ameren 
Missouri and Ameren Transmission Company of Illinois); C T Gaunt; 
New England Consumer Advocates (consisting of the Office of 
Massachusetts Attorney General Andrea Joy Campbell, the Connecticut 
Office of Consumer Counsel, the Maine Office of Public Advocate, the 
New Hampshire Office of Consumer Advocate, and the Rhode Island 
Division of Public Utilities and Carriers); Joint Consumer Advocates 
(including the Illinois Attorney General, Illinois Citizens Utility 
Board, Maryland Office of People's Counsel, the New Jersey Division 
of Rate Counsel, the North Carolina Utilities Commission Public 
Staff, the Office of the People's Counsel for the District of 
Columbia, and the West Virginia Consumer Advocate Division of the 
Public Service Commission), Joint Customers (including Old Dominion 
Electric Cooperative, Northern Virginia Electric Cooperative, Inc., 
and Dominion Energy Services, Inc. on behalf of Virginia Electric 
and Power Company d/b/a Dominion Energy Virginia); Liberty Utilities 
(Granite State Electric) Corp. d/b/a Liberty (Liberty); MISO; MISO 
Transmission Owners (including Ameren, as agent for Union Electric 
Company d/b/a Ameren Missouri, Ameren Illinois Company d/b/a Ameren 
Illinois, and Ameren Transmission Company of Illinois; Arkansas 
Electric Cooperative Corporation; City Water, Light & Power; 
Cooperative Energy; Dairyland Power Cooperative; East Texas Electric 
Cooperative; Entergy Arkansas, LLC; Entergy Louisiana, LLC; Entergy 
Mississippi, LLC; Entergy Texas, Inc.; Great River Energy; 
Indianapolis Power & Light Company; Lafayette Utilities System; 
MidAmerican Energy Company; Minnesota Power (and its subsidiary 
Superior Water, L&P); Missouri River Energy Services; Montana-Dakota 
Utilities Co.; Northern States Power Company, a Minnesota 
corporation, and Northern States Power Company, a Wisconsin 
corporation, subsidiaries of Xcel Energy Inc.; Northwestern 
Wisconsin Electric Company; Otter Tail Power Company; Prairie Power, 
Inc.; Southern Indiana Gas & Electric Company (d/b/a CenterPoint 
Energy Indiana South); and Southern Minnesota Municipal Power 
Agency); the Ohio Office of the Federal Energy Advocate of the 
Public Utilities Commission of Ohio (Ohio FEA); Portland General 
Electric Company (PGE); PJM; the PJM IMM; the Transmission Access 
Policy Study Group (TAPS) (an association of transmission dependent 
utilities in 35 states). For convenience, we have listed each 
commenter and the parties they represent. For brevity, for the 
remainder of this rule, we will refer to each commenter by their 
abbreviated names as defined in this footnote.
    \52\ The American Council on Renewable Energy (ACORE); Calpine 
Corporation (Calpine); Eagle Creek Reactive Generators (including 
Mahoning Creek Hydroelectric Company, LLC, York Haven Power Company, 
LLC, Eagle Creek Reusens Hydro, LLC, Great Falls Hydroelectric 
Company Limited Partnership, Lake Lynn Generation, LLC, PE Hydro 
Generation, LLC, Black River Hydroelectric, LLC, All Dams 
Generation, LLC, and Eagle Creek Hydro Power, LLC); EDP Renewables 
North America LLC (EDPR); Elevate Renewables F7, LLC (Elevate); 
Generation Developers (including Vistra Corp. and Dynegy Marketing 
and Trade, LLC); Glenvale LLC (Glenvale); Indicated Reactive Power 
Suppliers (including KMC Thermo, LLC, Bitter Ridge Wind Farm, LLC, 
Guernsey Power Station LLC, Moxie Freedom LLC, Safe Harbor Water 
Power Corporation, BIF III Holtwood LLC, Brookfield Power Piney & 
Deep Creek LLC, Erie Boulevard Hydropower, L.P., Carr Street 
Generating Station, L.P., Bear Swamp Power Company LLC, Brookfield 
White Pine Hydro LLC, Brookfield Renewable Trading and Marketing LP, 
and Reworld Waste, LLC f/k/a Covanta; Independent Power Producers of 
New York, Inc. (IPPNY); Indicated Trade Associations (including 
Electric Power Supply Association, The PJM Power Providers Group the 
New England Power Generators Association, Inc., Independent Power 
Producers of New York, Inc., the Coalition of Midwest Power 
Producers); ISO-NE; Middle River Power LLC (including Coalition of 
Midwest Power Producers, the Electric Power Supply Association, the 
PJM Power Providers Group, the New England Power Generators 
Association, Inc., and the Independent Power Producers of New York, 
Inc.); National Hydropower Association (NHA) (a national trade 
association with over 320 member companies); New England Power 
Generators Association, Inc. (NEPGA); New England Power Pool 
(NEPOOL); New England States Committee on Electricity (NESCOE); 
Nuclear Energy Institute (NEI); North American Generator Forum 
(NAGF); NYISO; Onward Energy Holdings, LLC (Onward Energy); PSEG 
(including Public Service Electric and Gas Company, PSEG Power LLC, 
and PSEG Energy Resources & Trade LLC, and each wholly owned, direct 
or indirect subsidiaries of Public Service Enterprise Group 
Incorporated) (PSEG); Reactive Service Providers (including CIP, D. 
E. Shaw Renewable Investments, L.L.C., Invenergy Renewables LLC, 
Leeward Renewable Energy, LLC, Lightsource Renewable Energy 
Operations, LLC, NextEra Energy Resources, LLC,1 [Oslash]rsted Wind 
Power North America, LLC, and RWE Clean Energy, LLC); Clean Energy 
Associations (including Solar Energy Industries Association (SEIA) 
and American Clean Power Association (ACP)). For brevity, for the 
remainder of this rule, we will refer to each commenter by their 
abbreviated names as defined in this footnote.

---------------------------------------------------------------------------

[[Page 93415]]

II. Discussion

    20. In this final determination, the Commission adopts the NOPR as 
proposed, except with respect to the timing of the compliance 
procedures and implementation. Based on our review of the record, we 
find there is substantial evidence to support the conclusion that 
allowing transmission providers to charge transmission customers for a 
generating facility's provision of reactive power within the standard 
power factor range results in unjust and unreasonable transmission 
rates. As explained in the NOPR, generating facilities providing 
reactive power within the standard power factor range are only meeting 
their obligations under their interconnection agreements and in 
accordance with good utility practice, and in doing so, incur no or at 
most de minimis variable costs beyond the cost of providing real power. 
Moreover, providing compensation for the provision of reactive power 
within the standard power factor range risks overcompensation and 
market distortion in ways that did not exist prior to the existence of 
organized markets.
    21. We find that these reforms will not adversely impact 
reliability. We also find that generating facilities have the 
opportunity to seek to recover any costs associated with providing 
reactive power within the standard power factor range through their 
rates for selling real power, including energy or capacity sales, 
whether in organized or bilateral markets. Given that the primary 
function of a generating facility is to produce real power and that the 
provision of reactive power within the standard power factor range is 
necessary for the provision of real power, we find that the existing 
means of cost recovery for real power are not only reasonable but also 
the most logical outcome.
    22. Based on more than two decades of experience since Order No. 
2003, and the record developed in this proceeding, we find that, even 
as a function of comparability, charging transmission customers under 
Schedule 2 for the provision of reactive power within the standard 
power factor range has become unjust and unreasonable. As explained 
above and for the reasons discussed below, in Order No. 2003, the 
Commission found generators should not receive compensation for the 
provision of reactive power within the standard power factor as it was 
an obligation of good utility practice. Based on rehearing requests, in 
Order No. 2003-A, the Commission agreed that where vertically 
integrated transmission owners continued to have rate schedules 
providing payment to their affiliated generating facilities for 
reactive power service within the standard power factor range, such 
transmission owners were also required to pay non-affiliated 
interconnection customers for the same provision of reactive power. At 
the time of Order Nos. 2003 and 2003-A, functional unbundling of 
transmission service \53\ and the development of organized wholesale 
electricity markets \54\ were relatively nascent, and so too was the 
Commission's experience with the impacts of establishing the 
comparability standard for the provision of reactive power within the 
standard power factor range. At the time, establishing the 
comparability standard appeared consistent with Order No. 2003's stated 
intent of ``minimiz[ing] opportunities for undue discrimination and 
expedit[ing] the development of new generation, while protecting 
reliability and ensuring that rates are just and reasonable.'' \55\
---------------------------------------------------------------------------

    \53\ Order No. 888, FERC Stats. & Regs. ] 31,036 at 31,654 (``We 
conclude that functional unbundling of wholesale services is 
necessary to implement non-discriminatory open access 
transmission.'').
    \54\ Regional Transmission Orgs., Order No. 2000, FERC Stats. & 
Regs. ] 31,089 (1999) (cross-referenced at 89 FERC ] 61,285) (``We 
conclude that properly structured RTOs throughout the United States 
can provide significant benefits in the operation of the 
transmission grid.''), order on reh'g, Order No. 2000-A, FERC Stats. 
& Regs. ] 31,092 (2000) (cross-referenced at 90 FERC ] 61,201), 
aff'd sub nom. Pub. Util. Dist. No. 1 of Snohomish Cty. v. FERC, 272 
F.3d 607 (D.C. Cir. 2001).
    \55\ See, e.g., Order No. 2003, 104 FERC ] 61,103 at P 12 
(explaining that standard interconnection procedures and a standard 
agreement will: ``(1) limit opportunities for Transmission Providers 
to favor their own generation; (2) facilitate market entry for 
generation competitors by reducing interconnection costs and time; 
and (3) encourage needed investment in generator and transmission 
infrastructure'').
---------------------------------------------------------------------------

    23. Since Order No. 2003, however, many industry changes have 
occurred. Some vertically integrated utilities have divested their 
generation. Competitive markets have developed, leading many generators 
to recover their costs through market-based rather than cost-based 
rates. The development of competitive markets makes even more 
challenging any allocation of costs between real power production, 
under market-based rates, and reactive power service, under cost of 
service rates.\56\ When rates are market-based, challenges in 
allocation will affect the competitive positions of the entities.\57\ 
New technologies have developed that provide reactive power through 
different means and to which the AEP Methodology that predates these 
technologies does not squarely apply. With fewer vertically integrated 
utilities, the continued development of competitive markets, and new 
technologies, the initial justification for compensation (i.e., that 
the Commission required separate compensation on a comparable basis 
because vertically integrated transmission owners continued to have 
rate schedules providing payment to their affiliated generating 
facilities for reactive power service) is no longer broadly applicable. 
Indeed, the wide-ranging rates for reactive power resulting from cost-
of-service proceedings further undermine the principle of comparability 
as some generating facilities now receive substantially higher rates 
for the provision of reactive power within the

[[Page 93416]]

standard power factor range than others.\58\
---------------------------------------------------------------------------

    \56\ See In re Permian Basin Area Rate Cases, 390 U.S. at 804 
(``There is ample support for the Commission's judgment that the 
apportionment of actual costs between two jointly produced 
commodities, only one of which is regulated by the Commission, is 
intrinsically unreliable.''); A.A. Poultry Farms, Inc. v. Rose Acre 
Farms, Inc., 881 F.2d 1396, 1400 (7th Cir. 1989) (``How does one 
allocate the cost of activities that have joint products? Agencies 
engaged in ratemaking struggle with these problems for years, even 
decades, without producing clear answers.''); Richard A. Posner, 
Natural Monopoly and Its Regulation, 21 Stan. L. Rev. 548, 595 
(1969) (``where services involve joint or common costs a rational 
allocation is impossible even in theory. How much of the cost of a 
telephone handset is assignable to local and how much to interstate 
telephone service?'').
    \57\ When both real power and reactive power rates were cost-
based, the only effect of the allocation was to change the 
allocation of costs and the rates for transmission and generation 
service; the transmission provider would not exceed its total 
revenue requirement.
    \58\ The PJM IMM notes that total settled reactive power revenue 
requirements for oil-fueled steam units average $993/MW-year whereas 
other units have settled reactive power revenue requirements as high 
as $18,750/MW-year. IMM Initial Comments at 5.
---------------------------------------------------------------------------

    24. All of these changes taken together, coupled with the record 
developed here, make clear that separate compensation for the provision 
of reactive power within the standard power factor range results in 
unjust and unreasonable rates to transmission customers, because such 
compensation is not necessary for comparability or to ensure continued 
investment in the capability of generating facilities to provide 
reactive power within the standard power factor range.\59\ We 
acknowledge that this final determination represents a change in 
policy,\60\ a change we find appropriate based on the record before us, 
as explained in detail herein.\61\
---------------------------------------------------------------------------

    \59\ See, e.g., PJM IMM Initial Comments at 11-12 (``The salient 
difference between PJM and CAISO, SPP, and MISO is that PJM 
customers paid $388,044,837.00 in out of market payments for 
reactive capability in 2023, and customers in CAISO, SPP and MISO, 
paid $0.00''); For Schedule 2 service in 2023, PJM paid $388 
million, NYISO paid $75 million, and ISO-NE paid $18 million. See 
PJM 2023 Annual Report at 5, <a href="https://services.pjm.com/annualreport2023/">https://services.pjm.com/annualreport2023/</a>); 2023 NYISO Voltage Support Service Rates, 
<a href="https://www.nyiso.com/documents/20142/35126567/2023-OATT-MST-Schedule-2-VSS-Rates-FINAL-for-posting.pdf/f59317b0-41c6-9f41-5d61-e7f502af82c2">https://www.nyiso.com/documents/20142/35126567/2023-OATT-MST-Schedule-2-VSS-Rates-FINAL-for-posting.pdf/f59317b0-41c6-9f41-5d61-e7f502af82c2</a>); 2023 Annual Markets Report at 154, <a href="http://iso-ne.com/static-assets/documents/100011/2023-annual-markets-report.pdf">iso-ne.com/static-assets/documents/100011/2023-annual-markets-report.pdf</a>.
    \60\ See Order No. 2003-C, 111 FERC ] 61,401 at P 42 (finding 
that because providing reactive power within the established range 
is an ``important service,'' payment for such service does not 
constitute a ``windfall'').
    \61\ PJM Power Providers Grp. v. FERC, 88 F.4th 250, 271-72 (3d 
Cir. 2023), amended sub nom. PJM Power Provisers Grp. v. FERC, No. 
21-3068, 2024 WL 259448 (3d Cir. Jan. 24, 2024) (``An agency may 
alter its `view of what is in the public interest.' The fact that 
contrary agency precedent exists `gives us no more power than usual 
to question the Commission's substantive determinations.' The agency 
need not establish that `the reasons for the new policy are better 
than the reasons for the old one; it suffices that the new policy is 
permissible under the statute, that there are good reasons for it, 
and that the agency believes it to be better.' '') (citing FCC v. 
Fox Television Stations, Inc., 556 U.S. 502, 515 (2009)); In re 
Permian Basin Area Rate Cases, 390 U.S. 747, 784 (1968) (Permian 
Basin); see also Motor Vehicle Mfrs. Ass'n of U.S., Inc. v. State 
Farm Mut. Auto. Ins. Co., 463 U.S. 29, 42 (1983) (``[W]e fully 
recognize that regulatory agencies do not establish rules of conduct 
to last forever.'') (internal quotations omitted); Greater Bos. 
Television Corp. v. FCC, 444 F.2d 841, 852 (D.C. Cir. 1970) (an 
agency may change its course as long as it ``suppl[ies] a reasoned 
analysis indicating that prior policies and standards are being 
deliberately changed, not casually ignored.''), cert. denied, 403 
U.S. 923 (1971)).
---------------------------------------------------------------------------

    25. Accordingly, we are modifying Schedule 2 of the pro forma OATT, 
section 9.6.3 of the pro forma LGIA, and section 1.8.2 of the pro forma 
SGIA, and we are requiring transmission providers to make corresponding 
revisions to their OATTs and pro forma interconnection agreements, to 
prohibit transmission providers from including in their transmission 
rates any charges associated with the provision of reactive power 
within the standard power factor range from generating facilities.
    26. We discuss below the issues raised in the comments.

A. Need for Reform

    27. The NOPR preliminarily found that where transmission providers 
require transmission customers to pay for generating facilities' 
provision of reactive power within the standard power factor range, 
transmission rates may be unjust and unreasonable, as such rates may 
include costs without a sufficient economic basis or justification and 
such costs may not result in transmission customers receiving 
commensurate reliability benefits.\62\ In support of the need for 
reform, the NOPR preliminarily found that generating facilities 
providing reactive power within the standard power factor range are 
only meeting their obligations under their interconnection agreements 
and in accordance with good utility practice, and in doing so, incur no 
or at most a de minimis increase in variable costs beyond the cost of 
providing real power.\63\ The NOPR also highlighted various adverse 
impacts of the Commission's policy on reactive power compensation, 
which have been exacerbated by the increasing volume of filings for 
reactive power compensation and in turn, increasing reactive power-
related costs to transmission customers.\64\ For example, in many 
regions, generating facilities are sited without regard to where there 
is a geographic need for reactive power, which is significant given 
that unlike real power, reactive power cannot be efficiently 
transmitted long distances.\65\ Additionally, adjudicating cost-of-
service reactive power rates has become increasingly administratively 
burdensome and may result in inconsistent rate treatment across 
generating facilities.\66\ Furthermore, in regions where generating 
facilities may seek to recover their costs by participating in 
organized competitive wholesale markets, providing separate 
compensation for the provision of reactive power within the standard 
power factor range risks overcompensation and market distortion in ways 
that did not exist prior to the existence of organized markets.\67\ 
Finally, as explained in the NOPR, the costs to transmission customers 
have increased substantially without any commensurate increase in 
benefits.\68\
---------------------------------------------------------------------------

    \62\ NOPR, 186 FERC ] 61,203 at PP 25, 40.
    \63\ Id. PP 28-33.
    \64\ Id. PP 34-40.
    \65\ Id. P 35.
    \66\ Id. PP 36-38.
    \67\ Id. P 39.
    \68\ Id. P 40.
---------------------------------------------------------------------------

    28. The NOPR also preliminarily found that cessation of payments 
for reactive power within the standard power factor range for 
generating facilities does not compromise a generating facility's 
ability to recover costs-if any-that it may incur in producing reactive 
power within such range because generating facilities have the 
opportunity to seek to recover such costs in other ways, such as 
through energy or capacity sales.\69\
---------------------------------------------------------------------------

    \69\ Id. P 42.
---------------------------------------------------------------------------

1. Comments
    29. AEP, Ameren, Joint Consumer Advocates, Joint Customers, MISO 
Transmission Owners, New England Consumer Advocates, Ohio FEA, PGE, 
PJM, the PJM IMM, and TAPS agree there is a need for reform and, 
accordingly, support the NOPR proposal to eliminate compensation for 
reactive power within the standard power factor range.\70\
---------------------------------------------------------------------------

    \70\ AEP Initial Comments at 1-2; Ameren Initial Comments at 2-
3; Joint Consumer Advocates Initial Comments at 1; Joint Customers 
Initial Comments at 2; MISO Transmission Owners Initial Comments at 
1, 5; New England Consumer Advocates Initial Comments at 6; Ohio FEA 
Initial Comments at 3; PGE Initial Comments at 1; PJM Initial 
Comments at 1, 3; PJM IMM Initial Comments at 2; TAPS Initial 
Comments at 1.
---------------------------------------------------------------------------

    30. Many commenters argue that there is substantial evidence to 
support the conclusion that allowing transmission providers to charge 
transmission customers for a generating facility's provision of 
reactive power from within the standard power factor range results in 
unjust and unreasonable transmission rates.\71\ They also agree that 
current generator compensation for the provision of reactive power 
within the standard power factor range lacks sufficient economic basis 
or justification,\72\ and that customers may

[[Page 93417]]

not be receiving commensurate reliability benefits.\73\
---------------------------------------------------------------------------

    \71\ See, e.g., Joint Customers Reply Comments at 10-11 
(``Standing on its own, the record in this proceeding is sufficient 
to justify the conclusion that compensating generators, any 
generators, for reactive service within the standard power factor 
range is not just and reasonable. Through the NOI comments, the 
development of the NOPR, and comments to the NOPR, the Commission 
has supported its conclusions and addressed potential concerns.'').
    \72\ Joint Consumer Advocates Initial Comments at 1, 5; Joint 
Customers Initial Comments at 5-6; Joint Customers Reply Comments at 
1-2; MISO Transmission Owners Reply Comments at 2; PGE Initial 
Comments at 5; TAPS Initial Comments at 3.
    \73\ Joint Customers Initial Comments at 13-17; MISO 
Transmission Owners Reply Comments at 8, 19; New England Consumer 
Advocates Initial Comments at 4-6; TAPS Initial Comments at 3.
---------------------------------------------------------------------------

    31. Joint Customers maintain, for example, that the NOPR builds on 
longstanding Commission policy, reaffirmed since Order No. 2003, that 
no compensation is appropriate for reactive service within the standard 
power factor range and that challenges to the sufficiency of the record 
or the process are unfounded.\74\ Joint Customers explain that ``[t]he 
only change the Commission is making in the NOPR is to determine that 
transmission providers no longer should have the option to compensate, 
affiliate and non-affiliate alike. And for that discrete change, that 
the exception to the general rule on compensation should be closed, the 
Commission has plainly created a sufficient record.'' \75\
---------------------------------------------------------------------------

    \74\ Joint Customers Reply Comments at 10-11.
    \75\ Id. at 11 (emphasis in original).
---------------------------------------------------------------------------

    32. PJM supports the NOPR and asserts that it would largely 
eliminate the problems with the current reactive power compensation 
regime in PJM, including the resource-intensive administrative burdens 
of reactive power rate proceedings and the ``black box'' settlements 
that ``seem[ ] at odds with the Commission's general precedent on 
efficient energy and ancillary service price formation.'' \76\ MISO 
explains that it has not experienced reliability concerns since 
eliminating compensation for reactive power within the standard power 
factor range in December 2022 \77\ and that it would not expect to see 
any effect on reliability through eliminating compensation for reactive 
power within the standard power factor range.\78\
---------------------------------------------------------------------------

    \76\ PJM Initial Comments at 1-3.
    \77\ MISO Initial Comments at 2.
    \78\ Id.
---------------------------------------------------------------------------

    33. MISO Transmission Owners support the need for reform, arguing 
that the current framework for reactive power compensation is neither 
just nor reasonable given that it results in transmission customers 
being required to pay for a service that generators already are 
required to provide and that costs them little or nothing to 
provide.\79\
---------------------------------------------------------------------------

    \79\ MISO Transmission Owners Initial Comments at 5.
---------------------------------------------------------------------------

    34. Many commenters agree that the current reactive power framework 
does not result in commensurate reliability benefits.\80\ First, many 
commenters agree that compensation for providing reactive power within 
the standard power factor range is unnecessary to maintain 
reliability.\81\ Second, many commenters also agree with the NOPR that 
under the current framework, compensation for reactive power within the 
standard power factor range is not tied to whether there is a 
particular geographic need for reactive power.\82\ TAPS, for example, 
contends that the existing approach to reactive power capability 
compensation does not adequately consider a generator's actual 
contribution to reliability or lack thereof and thus requires consumers 
to pay excessive charges for reactive power that may not be needed or 
is in the wrong location.\83\ Similarly, Joint Customers contend that 
``[t]his incentive structure to provide payment based on reactive 
capability results in the building of unnecessary capabilities in 
locations it is not or may not be needed and does not allocate the 
costs associated with reactive capability in a manner that is at least 
roughly commensurate with the benefits received.'' \84\
---------------------------------------------------------------------------

    \80\ Joint Customers Initial Comments at 12; MISO Transmission 
Owners Initial Comments at 19; MISO Transmission Owners Reply 
Comments at 3-5; New England Consumer Advocates Initial Comments at 
4-6; TAPS Initial Comments at 3-5.
    \81\ See, e.g., PJM IMM Initial Comments at 11-12 (``There will 
be no adverse reliability impacts in PJM (or other similarly 
situated regions) for the same reasons that . . . there have been no 
observable impacts in regions that do not compensate generating 
facilities for the supply of reactive power with the standard power 
factor range. As in the case of CAISO, SPP and MISO, new and 
existing generating facilities in PJM are required to provide 
reactive power within the standard power factor range as a condition 
of obtaining and maintaining interconnection service. There is no 
evidence that expanding the just and reasonable approach to 
compensation already in place in CAISO, SPP and MISO to PJM will 
have any adverse impact on reliability in PJM.''); MISO Transmission 
Owners Initial Comments at 13 (``When the MISO Transmission Owners 
proposed to eliminate compensation for producing reactive power 
within the deadband, the most common protest from generators was 
that it would impact the reliability of the grid. However, such 
claims are not supported by evidence and distract from the 
underlying fact that generators are obligated to provide reactive 
power within the deadband whether or not they are compensated for 
it.'' (citations omitted)).
    \82\ See, e.g., Ohio FEA Initial Comments at 5 (``As a result, 
in areas like PJM, generators currently receive compensation 
regardless of proximity to locations on the transmission system 
where there is an actual need for additional reactive power.''); 
Joint Customers Initial Comments at 17 (``Further, the failure to 
account for transmission system needs or grid geography in the 
current regime in regions like PJM undermine the reliability 
benefits of generators that interconnect to the system with reactive 
capabilities, whether meeting or exceeding their baseline 
interconnection requirements. The current paradigm has resulted in 
the development and deployment of generator based reactive 
capability that is ill-suited to the needs of the transmission 
system, and specifically that is well in excess of needs. 
Eliminating the incentive to overbuild reactive capability will not 
negatively impact reliability.'').
    \83\ TAPS Initial Comments at 4-5.
    \84\ Joint Customers Initial Comments at 12 (citing Ill. Com. 
Comm'n. v. FERC, 576 F.3d 470, 477 (7th Cir. 2009)).
---------------------------------------------------------------------------

    35. Further, like PJM, many commenters agree with the NOPR 
regarding the administrative burden for all parties to determine 
Schedule 2 rates.\85\ Joint Consumer Advocates argue that ``the 
existing compensation framework for generators that supply reactive 
power has led to unjust and unreasonable rates'' and note that ``[d]ue 
to limited resources, the [Joint Consumer Advocates] have generally 
been unable to participate in the numerous reactive proceedings and 
assist the Commission with the review and scrutiny of generator 
submissions. But such review and scrutiny are essential given the sheer 
number of filings and the absence of standardized accounting for the 
costs claimed in them by generators.'' \86\
---------------------------------------------------------------------------

    \85\ AEP Initial Comments at 4-6; Joint Customers Initial 
Comments at 1-5; PJM IMM Initial Comments at 9.
    \86\ Joint Consumer Advocates Initial Comments at 7. See also 
PJM IMM Initial Comments at 9 (``Applying cost of service rules is 
costly, burdensome and unnecessary. Most reactive proceedings for 
generators in PJM are resolved in black box settlements that require 
substantial time and resources from all parties, fail to address the 
merits of the cost support provided, result from an unsupported 
split the difference approach, and that produce a wide, unreasonable 
and discriminatory disparity among the rates per paid per MW-year 
for the same service.''); Joint Customers Initial Comments at 7 
(``As well documented in comments to the NOI and described in the 
NOPR, the current individualized consideration of reactive filings 
purporting to apply the AEP [M]ethodology places a heavy burden on 
customers, Transmission Providers, and the Commission while 
resulting in customer charges with dubious connection to any clear 
benefits to the customers paying those charges. This combination 
created an intolerable condition necessitating Commission action to 
reform the compensation structure.'').
---------------------------------------------------------------------------

    36. AEP states that it supports the Commission's proposal to 
prospectively terminate reactive power compensation to generators for 
maintaining the ability to produce reactive power within the standard 
power factor range because it ``will more equitably balance the 
interests of customers and generators, ensure that reactive power will 
continue to be provided as a requirement of interconnection, and 
significantly decrease the administrative burdens associated with 
individualized, opaque, and inconsistent cost-of-service reactive power 
rate proceedings.'' \87\
---------------------------------------------------------------------------

    \87\ AEP Initial Comments at 4-5.
---------------------------------------------------------------------------

    37. Similarly, New England Consumer Advocates state that 
``[t]ransmission rates have been rising in recent years and costs are 
only expected to increase in the near term to accommodate projected 
future transmission system

[[Page 93418]]

needs. At this time of increasingly onerous retail energy costs, 
particularly in New England, the Commission must ensure that 
transmission providers are passing on to consumers only those costs 
which are just and reasonable, and for which consumers receive 
commensurate benefit.'' \88\
---------------------------------------------------------------------------

    \88\ New England Consumer Advocates Initial Comments at 3-4. See 
also PJM IMM Initial Comments at 5 (``Most recent cases settled 
prior to issuance of the NOPR have settled for costs well in excess 
of the average cost and well in excess of the ARR offset amount. The 
issue is growing in significance.''); MISO Transmission Owners 
Initial Comments at 5 (``The Commission's preliminary findings that 
led to the changes proposed in the NOPR are accurate. The current 
framework for reactive power compensation can result in transmission 
customers being required to pay for a service that generators 
already are required to provide and that costs them little or 
nothing to provide. Therefore, the current framework allows for 
compensation that is neither just nor reasonable.'').
---------------------------------------------------------------------------

    38. The PJM IMM argues that opposing comments come largely from 
generation owners opposed to the removal of subsidies that have 
benefited them, even though such subsidies are primarily the result of 
the ``nonsensical, wasteful and unworkable'' attempts to allocate a 
portion of costs recoverable in markets to a guaranteed reactive 
payment based on an outdated and arbitrary cost-of-service approach 
referred to as the AEP Methodology.\89\
---------------------------------------------------------------------------

    \89\ PJM IMM Reply Comments at 1-2.
---------------------------------------------------------------------------

    39. Other commenters opposed the NOPR, arguing that existing 
reactive power rates remain just and reasonable.\90\ Reactive Service 
Providers argue that ``changes to cost allocation'' following Order No. 
888 (i.e., functional unbundling) do not warrant a change to reactive 
power compensation.\91\ Reactive Service Providers contend that 
reactive power supply being unaffected in regions where transmission 
providers no longer pay for reactive power is not evidence that 
reactive power compensation is unjust and unreasonable,\92\ that the 
``comparability'' policy cannot be used as a basis to end 
compensation,\93\ that administrative burden is not a basis to find 
that compensation is unjust and unreasonable,\94\ and that inconsistent 
rate treatment across generating facilities does not mean that 
compensation is unjust and unreasonable.\95\
---------------------------------------------------------------------------

    \90\ Clean Energy Associations Initial Comments at 2-3; 
Indicated Trade Associations Reply Comments at 16; NEI Initial 
Comments at 1.
    \91\ Reactive Service Providers Initial Comments at 4, 29-34.
    \92\ Id. at 41-43.
    \93\ Id. at 43-48.
    \94\ Id. at 48-52.
    \95\ Id. at 53-54.
---------------------------------------------------------------------------

    40. Reactive Service Providers argue that the Commission should 
study individual generating facilities to determine if reactive power 
is still needed.\96\ Reactive Service Providers also argue that the 
Commission must ensure that compensation for providing reactive power 
outside the standard power factor range is adequate.\97\
---------------------------------------------------------------------------

    \96\ Id. at 76-77.
    \97\ Id. at 77.
---------------------------------------------------------------------------

    41. Indicated Trade Associations assert that the NOPR would grant 
transmission providers unlawfully preferential treatment, creating a 
preference for higher cost transmission solutions, and suggest that the 
Commission should withdraw the NOPR proposal and refocus its efforts on 
improving the methodologies used to determine reactive power rates.\98\ 
Further, Indicated Trade Associations assert that concerns raised about 
the AEP Methodology being burdensome and a lack of refund protections 
for customers do not justify eliminating reactive power compensation 
within the standard power factor range altogether.\99\
---------------------------------------------------------------------------

    \98\ Indicated Trade Associations Reply Comments at 16-17.
    \99\ Id. at 8-9.
---------------------------------------------------------------------------

    42. ISO-NE argues that ISO-NE's Schedule 2 VAR compensation program 
should not be disturbed.\100\ ISO-NE asserts that its treatment of 
reactive power is distinct from its energy and capacity markets.\101\ 
ISO-NE further states that its VAR service is not based on cost-of-
service and is different from the standard AEP Methodology but is 
instead based on a resource's capability to provide reactive power. 
ISO-NE explains that its VAR service compensates resources at a uniform 
payment rate (i.e., a single rate for reactive power provided within 
and outside of the standard power factor range) and is not resource-
intensive to calculate.\102\ ISO-NE adds that total VAR payments 
amounted to 0.25% of the total energy, ancillary services, and capacity 
markets combined (or approximately 18-20 million dollars) for the same 
given period. NEPOOL argues that one of the reasons Schedule 2 has 
worked well for New England is that it provides a simple fixed rate for 
the main component of VAR service, which pays part of the costs of a 
reactive power resource's capability to provide VAR service to the 
transmission system when needed. NEPOOL explains that this same fixed 
rate is provided to all qualified resources without further analysis 
of, or dispute about, resource-specific costs.\103\ NEPOOL argues that 
one of the reasons Schedule 2 has worked well for New England is that 
it provides a simple fixed rate for the main component of VAR service, 
which pays part of the costs of a reactive power resource's capability 
to provide VAR service to the transmission system when needed, without 
further analysis of, or dispute about, resource-specific costs.\104\
---------------------------------------------------------------------------

    \100\ ISO-NE Initial Comments at 1-2, NESCOE Reply Comments at 
2; NEPGA Reply Comments at 6-7; NEPOOL Reply Comments at 6-7. ISO-NE 
explains that its VAR service consists of four components: (1) the 
fixed Capacity Cost (CC) rate, under which Qualified Reactive 
Resources are eligible to receive VAR payments for their measurable 
capability to provide VAR service to the New England Transmission 
System; (2) the variable Lost Opportunity Cost, which compensates 
for the value of a resource's lost opportunity in the wholesale 
energy market in situations where a resource that would otherwise be 
economically dispatched is directed by the ISO to reduce real power 
output to provide more reactive power; (3) the variable Cost of 
Energy Consumed, which compensates for the cost of energy consumed 
by the resource solely to provide reactive power; and (4) the Cost 
of Energy Produced, which compensates for the difference between the 
locational marginal price and a resource's offer price, if the 
locational marginal price is lower than the offer price, for each 
hour the resource provides reactive power. ISO-NE Initial Comments 
at 3-4. ISO-NE notes that the components other than the CC component 
may occur infrequently and are far less than the CC rate component. 
ISO-NE Initial Comments at 4 n.5.
    \101\ ISO-NE Initial Comments at 1-2.
    \102\ Id. at 3-5, 14. The ISO New England Ancillary Service 
Schedule 2 Business Procedure is available on the ISO-NE website: 
<a href="https://www.iso-ne.com/static-assets/documents/rules_proceds/operating/gen_var_cap/schedule_2_var_business_procedure.pdf">https://www.iso-ne.com/static-assets/documents/rules_proceds/operating/gen_var_cap/schedule_2_var_business_procedure.pdf</a>. 
Operating Procedures include primarily: ISO New England Operating 
Procedure No. 12--Voltage and Reactive Control, available at <a href="https://www.iso-ne.com/static-assets/documents/rules_proceds/operating/isone/op12/op12_rto_final.pdf">https://www.iso-ne.com/static-assets/documents/rules_proceds/operating/isone/op12/op12_rto_final.pdf</a>; and ISO New England Operating 
Procedures No. 23--Generating Resource Auditing, available at <a href="http://www.iso-ne.com/static-assets/documents/rules_proceds/operating/isone/op23/op23_rto_final.pdf">http://www.iso-ne.com/static-assets/documents/rules_proceds/operating/isone/op23/op23_rto_final.pdf</a>.
    \103\ NEPOOL Reply Comments at 6-7.
    \104\ Id. at 6-7.
---------------------------------------------------------------------------

    43. NYISO challenges the Commission's preliminary conclusion that 
compensating generating facilities for providing reactive power within 
the standard power factor range has resulted in unjust and unreasonable 
transmission rates and urges the Commission to allow NYISO to maintain 
its current reactive power compensation program.\105\ NYISO states that 
it supports the NOPR's objective to avoid administratively burdensome 
processes and procedures to determine individualized cost-of-service 
reactive power rates for generation facilities. NYISO adds that NYISO's 
existing reactive power and Voltage Support Service (VSS) compensation 
structure, which uses a flat dollars per MVAr-year structure, is just 
and reasonable.\106\ NYISO maintains that this structure aligns costs 
directly with services provided, ensures reliability benefits

[[Page 93419]]

commensurate with expenses,\107\ provides market-like incentives, and 
encourages resources to offer reactive power cost-effectively by 
rewarding increased capability and maintaining necessary 
equipment,\108\ which reduces the need for complex, individualized 
cost-based payments and integrates reactive power support efficiently 
into the broader market framework, promoting economic efficiency and 
reliability.\109\ NYISO contends that a uniform implementation approach 
is not suitable given the varying regional needs and existing effective 
compensation frameworks.\110\
---------------------------------------------------------------------------

    \105\ NYISO Initial Comments at 1.
    \106\ Id. at 2; IPPNY Reply Comments at 1-2.
    \107\ NYISO Initial Comments at 2-5.
    \108\ Id. at 7-8.
    \109\ Id. at 7-8.
    \110\ Id. at 14.
---------------------------------------------------------------------------

    44. Indicated Trade Associations, Generation Developers, NEI and 
PSEG raise constitutional claims with respect to the NOPR proposal. 
Indicated Trade Associations argue that the proposed rule violates the 
Takings Clause of the Fifth Amendment to the United States 
Constitution.\111\ They argue that public utilities have the statutory 
and constitutional right to compensation for the services they provide, 
including reactive power, and the Commission cannot deprive public 
utilities of just and reasonable compensation simply by characterizing 
the provision of reactive power as a condition of interconnection, 
particularly where it was the Commission that established this 
condition. Similarly, Generation Developers argue that forcing 
generators to supply an identifiable portion of the reactive power they 
generate, without any compensation, as a condition of interconnection 
to the transmission system, falls squarely within the kinds of takings 
prohibited by the Takings Clause.\112\ PSEG states that, in accordance 
with the FPA and the Supreme Court precedent in Hope, the Commission 
has a duty to protect public utilities from rates that are 
confiscatory.\113\ PSEG argues that the proposed rule, not unlike the 
Commission denying transmission owners the opportunity to earn a return 
on network upgrades in Ameren, essentially compels generators to 
provide a service without the ability to recover their fixed associated 
costs, which is unjust and unreasonable, unduly discriminatory, and 
confiscatory and in violation of the FPA and judicial precedent.\114\
---------------------------------------------------------------------------

    \111\ Indicated Trade Associations Initial Comments at 22-24 
(citing Smyth v. Ames, 169 U.S. 466, 546 (1898)).
    \112\ Generation Developers Initial Comments at 26 (citing Horne 
v. Dept. of Ag., 576 U.S. 350, 359, 367 (2015); FPC v. Hope Nat. Gas 
Co., 320 U.S. 591, 603 (1944); Bluefield Waterworks & Improvement 
Co. v. Pub. Serv. Comm'n, 262 U.S. 679, 690 (1923)).
    \113\ PSEG Initial Comments at 18-19 (citing Bluefield 
Waterworks & Improvement Co. v. Pub. Serv. Comm'n, 262 U.S. at 690; 
Duquesne Light Co. v. Barash, 488 U.S. 299, 308 (1989) (``If the 
rate does not afford sufficient compensation, the State has taken 
the use of the utility property without paying just 
compensation.'')).
    \114\ PSEG Initial Comments at 19-20 (citing Ameren Servs. Co. 
v. FERC, 880 F.3d 571, 581-82 (D.C. Cir. 2018)).
---------------------------------------------------------------------------

    45. MISO Transmission Owners disagree with commenters arguing that 
the NOPR proposal constitutes an unconstitutional taking.\115\ They 
contend that the commenters' claim that the Order No. 2003 requirement 
for generators to provide reactive power within the standard power 
factor range violates the Takings Clause of the U.S. Constitution is a 
collateral attack on Order No. 2003. They contend that, while some 
contractual rights are considered ``property'' within the meaning of 
the Takings Clause of the Fifth Amendment, the contractual relationship 
entered into when a generator interconnects with a transmission system 
does not implicate a taking that must be compensated.\116\ MISO 
Transmission Owners state that the Commission determined in Order No. 
2003 that generators ``should not be compensated for reactive power 
when operating [their] Generating Facilit[ies] within the established 
power factor range, since [they are] only meeting [their] obligation.'' 
Moreover, they state that ``as `legislation [that] readjust[s] rights 
and burdens is not unlawful solely because it upsets otherwise settled 
expectations,' the Commission's action implementing the changes in the 
NOPR would not constitute an unconstitutional taking just because the 
changes would `impact the benefits and burdens' of the agreement 
entered into by generators interconnecting with the Transmission 
System.'' \117\ They contend that ``[g]enerators have only a unilateral 
expectation of payment for the provision of reactive power and not a 
legitimate claim of entitlement to compensation.'' \118\
---------------------------------------------------------------------------

    \115\ MISO Transmission Owners Reply Comments at 12 n.33.
    \116\ Id. (citing Transmission Plan. & Cost Allocation by 
Transmission Owning & Operating Pub. Utils., Order No. 1000-A, 77 FR 
32184 (May 31, 2012), 139 FERC ] 61,132, at P 368 (citing Connolly 
v. Pension Guar. Corp., 475 U.S. 211, 224 (1986)), order on reh'g 
and clarification, Order No. 1000-B, 77 FR 64890 (Oct. 24, 2012), 
141 FERC ] 61,044 (2012), aff'd sub nom. S.C. Pub. Serv. Auth. v. 
FERC, 762 F.3d 41 (D.C. Cir. 2014)).
    \117\ Id. (citing Order No. 1000-A, 139 FERC ] 61,132 at P 369 
(citing Connolly v. Pension Guar. Corp., 475 U.S. at 223)).
    \118\ Id. (citing Bd. of Regents of State Coll. v. Roth, 408 
U.S. 564, 577 (1972) (``To have a property interest in a benefit, a 
person clearly must have more than an abstract need or desire for 
it. He must have more than a unilateral expectation of it. He must, 
instead, have a legitimate claim of entitlement to it.''); Del. 
Riverkeeper Network v. FERC, 895 F.3d 102, 108-09 (D.C. Cir. 2018) 
(citing Town of Castle Rock, Colo. v. Gonzales, 545 U.S. 748, 756 
(2005)).
---------------------------------------------------------------------------

    46. Eagle Creek and the NHA both assert that existing reactive 
service rates enjoy the Mobile-Sierra presumption. The NHA asserts 
that, in order for the Commission to disallow the existing reactive 
service rates, each rate on-file must be demonstrated by the Commission 
to ``seriously harm the public interest.'' \119\ Eagle Creek and the 
NHA both note that, given the highly localized nature of reactive 
power, it is unclear how the Commission could assess these individual 
contracts without conducting a case-by-case analysis through individual 
section 206 proceedings.\120\ Eagle Creek and the NHA claim that absent 
such proceedings, generating facilities would be deprived of their 
current just and reasonable compensation and previous investments made 
by generating facilities would be compromised.\121\ The NHA and Eagle 
Creek assert that, by relying on a generic rulemaking to effectively 
cancel all reactive power rates, the NOPR is an ``act of convenience'' 
and ``an indirect attempt to strip the value of existing rates without 
facing the legal challenge that the Mobile-Sierra doctrine presents.'' 
\122\
---------------------------------------------------------------------------

    \119\ Eagle Creek Initial Comments at 4; NHA Initial Comments at 
8-9.
    \120\ Eagle Creek Initial Comments at 4; NHA Initial Comments at 
8.
    \121\ Eagle Creek Initial Comments at 4-5; NHA Initial Comments 
at 8.
    \122\ NHA Initial Comments at 8-9; see also Eagle Creek Initial 
Comments at 4-5.
---------------------------------------------------------------------------

    47. Joint Customers disagree with Eagle Creek and the NHA's 
argument that the Commission cannot eliminate compensation within the 
standard power factor range without initiating individual rate 
proceedings.\123\ Joint Customers explain that precedent cases, such as 
PNM and MISO, demonstrate that changes to the underlying Schedule 2 
tariff provisions effectively eliminate compensation for third-party 
generators without separate rate challenges.\124\
---------------------------------------------------------------------------

    \123\ Joint Customers Reply Comments at 13-14.
    \124\ Id. (``There is no validity to the argument that 
individual rate challenges must be pursued by the Commission or 
complainants, and it is well established that a change to the 
underlying Schedule 2 in a transmission provider's tariff, as 
proposed by the Commission in the NOPR, will contemporaneously end 
compensation to third-party generators with no further action 
required.''); see also PJM IMM Initial Comments at 9 (``The NOPR 
does not propose a new Commission policy. Rather, it extends and 
makes uniform policies that have long applied in jurisdictional 
markets.'').
---------------------------------------------------------------------------

    48. Reactive Service Providers and Generation Developers argue that 
the NOPR violates the D.C. Circuit's holding

[[Page 93420]]

in Atlantic City.\125\ They assert that by using the Commission's 
authority under section 206 of the FPA to eliminate reactive power 
compensation, the NOPR essentially strips generating facilities of 
their ability to make filings under section 205 of the FPA to recover 
the costs of the reactive power service that they provide.\126\
---------------------------------------------------------------------------

    \125\ Atl. City Elec. Co. v. FERC, 295 F.3d 1 (D.C. Cir. 2002) 
(Atl. City).
    \126\ Generation Developers Initial Comments at 31-32 (citing 
Atl. City, 295 F.3d at 9-10); Reactive Service Providers Initial 
Comments at 54.
---------------------------------------------------------------------------

2. Commission Determination
    49. Based on our review of the record, we find that there is 
substantial evidence to support the conclusion that transmission rates 
are unjust and unreasonable to the extent they include charges 
associated with the provision of reactive power within the standard 
power factor range. We therefore adopt the preliminary findings in the 
NOPR concerning the need for reform \127\ and, pursuant to section 206 
of the FPA, conclude that certain revisions to Schedule 2 of the pro 
forma OATT, pro forma LGIA, and pro forma SGIA are necessary to ensure 
rates that are just, reasonable, and not unduly discriminatory or 
preferential.
---------------------------------------------------------------------------

    \127\ NOPR, 186 FERC ] 61,203 at PP 24-27, 28.
---------------------------------------------------------------------------

    50. We agree with commenters that the current framework allows for 
transmission rates that are ``neither just nor reasonable'' and ``can 
result in transmission customers being required to pay for a service 
that generators already are required to provide and that costs them 
little or nothing to provide.'' \128\ As reflected in the record, 
absent reform, transmission customers would be required to continue to 
pay charges associated with generating facilities' provision of 
reactive power within the standard power factor range even though such 
charges are without a sufficient economic basis and do not result in 
transmission customers receiving commensurate reliability benefits. The 
need for reform is particularly acute given that ``transmission rates 
have been rising in recent years and costs are only expected to 
increase in the near term to accommodate projected future transmission 
system needs.'' \129\
---------------------------------------------------------------------------

    \128\ See, e.g., MISO Transmission Owners Initial Comments at 5; 
Joint Customers Initial Comments at 6-16, PJM IMM Initial Comments 
at 1-4, 6-9; PJM IMM Reply Comments at 2-3, 6-7; Ameren Initial 
Comments 2-3; AEP Initial Comments at 4-5; Ohio FEA Initial Comments 
at 5-6; TAPs Initial Comments at 1, 3-8; PGE Initial Comments at 3-
4.
    \129\ See, e.g., New England Consumer Advocates Initial Comments 
at 3 & n.7 (citing, e.g., Massachusetts Attorney General Maura 
Healey, Initial Comments, Docket No. RM21-17-000, at 28 (filed Aug. 
17, 2022); see also New England States Committee on Electricity, New 
England States' Vision for a Clean, Affordable, and Reliable 21st 
Century Regional Electric Grid (2020), <a href="https://nescoe.com/resource-center/vision-stmt-oct2020/">https://nescoe.com/resource-center/vision-stmt-oct2020/</a>).
---------------------------------------------------------------------------

    51. As described below, most commenters agree or do not dispute 
that real and reactive power are provided as joint products,\130\ with 
joint costs.\131\ Similarly, most commenters agree or do not dispute 
that, under their interconnection agreements and in accordance with 
good utility practice, generating facilities have a long-standing 
obligation to provide reactive power within the standard power factor 
range in order to interconnect reliably to the transmission system. 
Most commenters agree or do not dispute that generating facilities must 
produce reactive power within the standard power factor range to allow 
the generating facilities' real power to reliably flow to load.\132\ As 
such, we disagree with some commenters who challenge the Commission's 
preliminary finding that providing reactive power within the standard 
power factor range has no or de minimis costs \133\ and find, as 
discussed in greater detail below, that there is substantial evidence 
to conclude that in satisfying such obligations generating facilities 
incur no incremental investment, or fixed costs, and at most de minimis 
variable costs over and above those needed to provide real power.\134\ 
This is because no additional equipment is required to provide reactive 
power; rather the same equipment that is needed to produce, and is used 
to produce, real power also provides reactive power functions, at no 
additional capital cost. Variable costs, if any, are limited to the 
fuel costs (in synchronous facilities) or the cost of foregone direct 
current power (in non-synchronous facilities) necessary to provide the 
reactive power and to reliably inject real power into the transmission 
system.\135\ For example, in Panda Stonewall the annual revenue 
requirement of $2,051,894 included just $10,018 of identified variable 
costs.\136\ In light of this evidence, we find that charging 
transmission customers for the provision of reactive power within the 
standard power factor range results in unjust and unreasonable 
rates.\137\
---------------------------------------------------------------------------

    \130\ See PSC VSMPO-Avisma Corp. v. U.S., 688 F.3d 751, 756 
(Fed. Cir. 2012) (``[J]oint products [are] two dissimilar end 
products that are produced from a single production process.'') 
(citing Robert A. Anthony & James S. Reece, Accounting Principles 
442 (5th ed. 1983).
    \131\ A joint cost is an expenditure that benefits more than one 
product, and for which it is not possible to separate the 
contribution to each product. Permian Basin, 390 U.S. at 761 n.25 
(citing Accounting Tools, The Supply and Price of Natural Gas 25 
(1962)) (``Joint costs `are incurred when products cannot be 
separately produced.'''); <a href="https://www.accountingtools.com/articles/joint-cost">https://www.accountingtools.com/articles/joint-cost</a>.
    \132\ See SPP, 119 FERC ] 61,199, at P 28 (``[I]f a generator is 
to sell (and be able to deliver) its power to a customer, reactive 
power is essential to the transaction. Thus, it is hardly surprising 
that the Commission has concluded, . . . , that the provision of 
sufficient reactive power is an obligation of a generator 
interconnected to the system, and that, . . . , a generator is not 
entitled to separate compensation for providing reactive power 
within its deadband.'').
    \133\ See, e.g., Eagle Creek Initial Comments at 3-4; Indicated 
Trade Associations Initial Comments at 7; ACORE Initial Comments at 
2; Elevate Renewables Initial Comments at 9-12; Generation 
Developers Initial Comments at 13; Glenvale Initial Comments at 9-
10; Indicated Reactive Power Suppliers Initial Comments at 2, 9-10; 
Indicated Trade Associations Initial Comments at 2, 6; Middle River 
Power Initial Comments at 2-3; NEI Initial Comments at 4-5, 8-9; NHA 
Initial Comments at 2, 4-5.
    \134\ Although the Commission found in the MISO Rehearing Order, 
and earlier, that ``Reactive Service requires little or no 
incremental investment'' see, e.g., MISO Rehearing Order, 184 FERC ] 
61,022 at P 29 (emphasis added), we note that beyond vague 
assertions that incremental fixed costs are incurred, no evidence of 
investment or fixed costs specific to providing reactive power was 
provided in response to requests for such costs in the MISO 
Rehearing Order, the NOI, or the NOPR. As such, the Commission 
concludes below that there are no incremental or fixed costs to 
provide reactive power beyond those to provide real power.
    \135\ Under certain transmission system conditions, the 
generating facility may operate at a power factor of 1.0, which 
represents zero incremental variable costs and thus zero total costs 
of providing reactive power. A generating facility operating at any 
reactive power level (i.e., a power factor other than 1.0) will 
incur some amount of incremental fuel cost, but the Commission 
generally considers these costs de minimis within the standard power 
factor range. See, e.g., APS, 94 FERC at 61,080 (``We note that 
operating a generating unit within the proposed [standard power 
factor range] does not affect the generation output of a unit.''); 
Commission Staff Report, Principles for Efficient and Reliable 
Reactive Power Supply and Consumption, Docket No. AD05-1-000, at 96 
(2005 Staff Report) (2005) (``The marginal cost of providing 
reactive power from within a generator's capability curve (D-curve) 
is near zero.'').
    \136\ Panda Stonewall, LLC, 176 FERC ] 61,072, at P 6 n.9 
(2021). We note that the heating losses component reflects the 
incremental fuel cost of providing reactive power. See, e.g., Panda 
Stonewall, LLC, 174 FERC ] 61,266, at P 155 (2021) (``The AEP 
methodology already has a means in place to provide compensation for 
the small amount of additional fuel used during the production of 
reactive power, which is a heating loss calculation based on the MW-
hours of actual reactive power production and the usage charges for 
fuel.'').
    \137\ See Belmont Mun. Light Dep't v. FERC, 38 F.4th at 173, 
179, 186 (2022) (finding that the Commission's approval of a portion 
of ISO-NE's Inventoried Energy Program ``was not reasoned 
decisionmaking'' and ``thwart[ed] the [Commission's] own 
`longstanding policy that rate incentives must be prospective and 
that there must be a connection between the incentive and the 
conduct meant to be induced''' because it would compensate market 
participants for conduct they already engage in as part of standard 
business operations).
---------------------------------------------------------------------------

    52. ISO-NE and NYISO oppose the NOPR and seek flexibility to 
preserve their existing reactive power compensation regimes. We deny 
their requests. ISO-NE and NYISO principally argue that their flat-rate

[[Page 93421]]

compensation regimes are transparent, not administratively burdensome, 
designed to prevent double-recovery, and able to procure significant 
reliability benefits at ``reasonable'' or ``low'' cost. However, these 
arguments ignore the preliminary findings of the NOPR, namely that 
generating facilities providing reactive power within the standard 
power factor range are only meeting their obligations under their 
interconnection agreements in accordance with good utility practice, 
and in doing so incur no or at most a de minimis increase in variable 
costs beyond the cost of providing real power. As explained in this 
final determination and decades of prior Commission precedent, in order 
to reliably interconnect to the transmission system and deliver real 
power to customers, generating facilities must be capable of 
maintaining voltage levels for injecting real power into the 
transmission system.\138\ As relevant here, these findings apply 
equally to flat-rate compensation regimes like ISO-NE's and NYISO's, as 
well as the compensation regimes of PJM and certain non-RTO regions. 
Thus, the ISO-NE and NYISO regimes, while easier to implement 
administratively, also impose unreasonable and unsupportable costs on 
transmission customers.
---------------------------------------------------------------------------

    \138\ See, e.g., BPA, 120 FERC ] 61,211 at P 21 (``The purpose 
for which generation assets are built (including reactive power 
capability to maintain voltage levels for generation entering the 
grid) is to make sales of real power.''); SPP, 119 FERC ] 61,199 at 
P 28 (``[I]f a generator is to sell (and be able to deliver) its 
power to a customer, reactive power is essential to the 
transaction''). See also PJM Interconnection, L.L.C., 145 FERC ] 
61,280, at P 17 (2013) (approving tariff revisions that require 
interconnection customers to pay for upgraded telecommunication 
equipment (phasor measurement units) as the ``data is integral to 
improved communication and to the reliability of the system and, as 
such, benefits both the system and the generators'').
---------------------------------------------------------------------------

    53. ISO-NE's and NYISO's claims regarding transparency, 
administrative burden, and preventing double recovery all presuppose 
that compensation is due, and thus that a compensation method is 
needed. But, where compensation is found to be unjust and unreasonable, 
as we find here, such a compensation methodology will necessarily 
result in unjust and unreasonable rates and thus is not permissible.
    54. Additionally, we agree with New England Consumer 
Advocates,\139\ who argue that any payment for reactive power 
capability within the standard power factor range must yield some 
roughly commensurate incremental benefit above and beyond that which 
would accrue absent payment.\140\ As discussed below,\141\ ISO-NE and 
NYISO allude generally to reliability benefits from reactive power 
compensation over the full range of a resource's capability to provide 
reactive power--that is, both within and outside of the standard power 
factor range--rather than the narrower focus of this final 
determination. And, in both ISO-NE (except for certain circumstances as 
explained by ISO-NE) \142\ and NYISO, as everywhere, generating 
facilities must provide reactive power within the standard power factor 
range to make sales of real power regardless of whether they receive 
separate compensation.\143\
---------------------------------------------------------------------------

    \139\ New England Consumer Advocates Initial Comments at 5 (``To 
the extent . . . benefits are achieved by compliance with a 
generating facility's interconnection agreement and/or as `good 
utility practice,' [New England Consumer Advocates] agree[] with the 
Commission that ratepayers should not be paying separately for the 
costs to produce a joint reactive power product.'').
    \140\ See, e.g., Ill. Com. Comm'n. v. FERC, 576 F.3d at 476 
(``[The Commission] is not authorized to approve a pricing scheme 
that requires a group of utilities to pay for facilities from which 
its members derive no benefits, or benefits that are trivial in 
relation to the costs sought to be shifted to its members.'').
    \141\ See infra II.D.2.
    \142\ ISO-NE notes that not all generating facilities are 
obligated to provide reactive power within the standard power factor 
range. ISO-NE Initial Comments at 9. Specifically, ISO-NE notes that 
several older generating facilities in New England have 
interconnection agreements that pre-date the obligation to provide 
reactive power within the standard power factor range. Id. ISO-NE 
states that these resources choose to participate in the Schedule 2 
VAR compensation program, incurring an obligation to maintain and 
provide VAR service in New England. Id. Any generating facilities 
with individualized bilateral contracts providing for reactive power 
compensation within the standard power factor range may pursue 
claims that they have an independent contractual right to reactive 
power compensation within the standard power factor range, but we 
express no opinion here as to whether any such generator would be 
entitled to such compensation.
    \143\ See, e.g., BPA, 120 FERC ] 61,211 at P 21 (``The purpose 
for which generation assets are built (including reactive power 
capability to maintain voltage levels for generation entering the 
grid) is to make sales of real power.''); SPP Order on Rehearing, 
121 FERC ] 61,196 at P 15 (``As we have previously explained, 
reactive power is required for an interconnecting generator to 
deliver its power and reactive power produced within the [standard 
power factor range] and is, therefore, generally not compensable.'' 
(emphasis added)).
---------------------------------------------------------------------------

    55. We do not dispute that the provision of reactive power within 
the standard power factor range provides reliability benefits, only 
that there are no incremental fixed costs other than joint costs that 
are also associated with the production of real power and at most de 
minimis incremental variable costs that would warrant a separate 
compensation mechanism. We also find that there is substantial evidence 
to conclude that, under the current reactive power compensation 
framework, reactive power-related transmission charges are not tied to 
geographic need and result in excess reactive power capability that is 
not required for interconnection and does not provide transmission 
customers with commensurate reliability benefits.\144\ Accordingly, we 
deny ISO-NE's and NYISO's respective requests for flexibility to 
include in transmission rates charges associated with the provision of 
reactive power within the standard power factor range.
---------------------------------------------------------------------------

    \144\ Joint Customers Initial Comments at 12 (``This incentive 
structure to provide payment based on reactive capability results in 
the building of unnecessary capabilities in locations it is not or 
may not be needed and does not allocate the costs associated with 
reactive capability in a manner that is at least roughly 
commensurate with the benefits received.'' (citing Ill. Com. Comm'n. 
v. FERC, 576 F.3d at 477)); MISO Transmission Owners Initial 
Comments at 8 (``Moreover, the capability-based compensation 
methodology currently permitted by the Commission . . . allows and 
even incentivizes generators to add as much reactive equipment as 
they desire, i.e., to gold plate a facility's reactive capability, 
regardless of whether that reactive support is needed at that point 
on the grid.''); TAPS Initial Comments at 4-5 (``Nor can customers 
be assured they are receiving reliability benefits commensurate to 
the reactive power compensation paid under the current approach. The 
existing approach to reactive power capability compensation does not 
adequately consider a generator's actual contribution to 
reliability, or lack thereof. For example, that approach does not 
account for relevant factors such as location, the need for reactive 
power, deliverability to where reactive power may be needed, 
possible degradation in generator performance or other changes over 
time. The result is that the current approach to reactive power 
compensation requires consumers to pay excessive charges for 
reactive power that may not be needed or is in the wrong location.'' 
(citations omitted)). See Belmont Mun. Light Dep't v. FERC, 38 F.4th 
at 187-90 (finding that the Commission's acceptance of ISO-NE's 
Inventoried Energy Program ``was not reasoned decision making'' 
because record evidence indicated that certain types of generating 
facilities ``would not change their behavior in response to 
payments.'').
---------------------------------------------------------------------------

    56. We reject commenters' arguments that the final determination 
violates the Fifth and Fourteenth Amendments of the U.S. Constitution. 
The final determination's elimination of reactive power payments for 
the provision of reactive power within the standard power factor range 
is not confiscatory and would not amount to a taking of property. As 
noted above, generating facilities incur no or at most a de minimis 
increase in variable costs beyond the cost of providing real power and 
have the opportunity to seek recovery of any costs they do incur. In 
addition, commenters' arguments that the obligation to provide reactive 
power within the standard power factor range is unconstitutional are 
impermissible

[[Page 93422]]

collateral attacks on our prior determinations and unpersuasive.\145\
---------------------------------------------------------------------------

    \145\ MISO Transmission Owners Reply Comments at 12 n.33 
(``Moreover, as `legislation [that] readjust[s] rights and burdens 
is not unlawful solely because it upsets otherwise settled 
expectations,' the Commission's action implementing the changes in 
the NOPR would not constitute an unconstitutional taking just 
because the changes would `impact the benefits and burdens' of the 
agreement entered into by generators interconnecting with the 
Transmission System. Generators have only a unilateral expectation 
of payment for the provision of reactive power and not a legitimate 
claim of entitlement to compensation.'') (citations omitted). See 
also MISO, 182 FERC ] 61,033 at P 62; MISO Rehearing Order, 184 FERC 
] 61,022 at PP 52-54 (``Vistra has not persuaded us that it has a 
property interest in continued Reactive Service compensation under 
the Tariff, nor that MISO TOs' proposal would unconstitutionally 
deprive generators of that putative property interest under the 
Takings Clause or Due Process Clause of the Fifth Amendment.'').
---------------------------------------------------------------------------

    57. The Commission has repeatedly held that ``the provision of 
sufficient reactive power is an obligation of a generator 
interconnected to the system, and . . . as a general matter, a 
generator is not entitled to separate compensation for providing 
reactive power within its deadband.'' \146\ A generating facility must 
in fact produce reactive power to move real power from the generating 
facility to the transmission system to deliver its real power to 
customers, while maintaining system reliability.\147\ It is only by 
virtue of comparability that generating facilities were previously 
entitled to reactive power compensation.\148\
---------------------------------------------------------------------------

    \146\ See, e.g., MISO, 182 FERC ] 61,033 at P 62 (citing SPP, 
119 FERC ] 61,199 at P 28); MISO Rehearing Order, 184 FERC ] 61,022 
at P 52 (finding that protesters constitutional claims were 
impermissible collateral attacks on the Commission's prior 
determinations given ``[t]he obligation to provide Reactive Service 
exists independent of, and was not altered by, MISO TOs' proposal: 
it was stated in Order No. 2003 and applies to individual generators 
through their GIAs.'').
    \147\ See, e.g., MISO Rehearing Order, 184 FERC ] 61,022 at P 53 
(``[T]he function of generators' Reactive Service is to ensure that 
generators' real power can enter the transmission grid while 
maintaining system reliability.''); SPP, 119 FERC ] 61,199 at P 28 
(explaining that if a generator is to sell (and be able to deliver) 
its power to a customer, reactive power is essential to the 
transaction).
    \148\ NOPR, 186 FERC ] 61,203 at P 4 (citing Order No. 2003-A, 
106 FERC ] 61,220 at P 416). See also MISO Rehearing Order, 184 FERC 
] 61,022 at P 26 (``On rehearing, we continue to reject, as 
collateral attacks on that longstanding policy, arguments that 
stand-alone compensation for Reactive Service is generically 
required--for example, to ensure that generators can recover their 
costs for Reactive Service capability. These arguments would negate 
the conclusions in Order Nos. 2003 and 2003-A that such compensation 
should not be provided, except as required by the comparability 
standard.'').
---------------------------------------------------------------------------

    58. Simply stated, the obligation to provide reactive power within 
the standard power range exists independent of, and was not altered by, 
the NOPR's proposal: it was stated in Order No. 2003 and applies to 
individual generating facilities through their interconnection service 
agreements. This final determination changes only the allowance for 
transmission providers to provide compensation at their discretion to 
their own and affiliated generating facilities, and then to third-party 
generating facilities under the comparability standard for the 
provision of reactive power within the standard power factor range. 
This change eliminates a stream of revenue under Schedule 2, but we 
find here that such elimination is just and reasonable given that the 
record demonstrates that generating facilities incur no or at most a de 
minimis increase in variable costs beyond the cost of providing real 
power.\149\ Moreover, to the extent that generating facilities have any 
costs associated with providing reactive power within the standard 
power factor range, generating facilities may seek to recover these 
costs through energy or capacity sales.\150\ Accordingly, and 
consistent with precedent, commenters have not persuaded us that they 
have a property interest in continued compensation under Schedule 2, or 
that this final determination would unconstitutionally deprive 
generating facilities of that putative property interest under the 
Takings Clause or Due Process Clause of the Fifth Amendment.
---------------------------------------------------------------------------

    \149\ See MISO Transmission Owners Initial Comments at 6 (``The 
MISO Transmission Owners' experience supports the Commission's 
preliminary finding that providing reactive power within the 
standard power factor range requires little or no cost to 
generators. Generators incur little or no costs beyond what is 
already needed to produce real power because the same equipment used 
to produce real power includes reactive power functions.'' 
(citations omitted)); PJM IMM Reply Comments at 3 (``Neither the 
[Indicated Trade Associations] nor any other opposing commenter, nor 
any of the precedent relied upon by opposing commenters, identify 
any additional costs or more than de minimis costs incurred by 
generators in order to provide reactive capability.'').
    \150\ MISO Rehearing Order, 184 FERC ] 61,022 at P 53; BPA, 120 
FERC ] 61,211 at P 20; BPA Rehearing Order, 125 FERC ] 61,273 at P 
11; see also NOPR, 186 FERC ] 61,203 at P 24; see also MISO 
Transmission Owners Initial Comments at 6; PJM IMM Reply Comments at 
3.
---------------------------------------------------------------------------

    59. We disagree with Eagle Creek's and the NHA's assertions that 
most reactive service rate schedules on file enjoy the Mobile-Sierra 
presumption and as a result, in order for the Commission to disallow 
the existing reactive service rates, each rate on file must be 
demonstrated by the Commission to ``seriously harm the public 
interest.'' \151\ While the Mobile-Sierra doctrine establishes a more 
rigorous application of the just and reasonable standard when the 
Commission proposes to change an individual contract negotiated at 
arms-length,\152\ reactive power-related transmission rates are not 
individually negotiated contract rates, but rather transmission owner 
tariff-based rates of general applicability reflected in the 
transmission owner's Schedule 2.\153\ The fact that the Commission has 
accepted generating facilities' rate filings setting forth reactive 
power rates covering the provision of reactive power within the 
standard power factor range establishes only the rate at which the 
generating facility is obligated to sell reactive power to a 
transmission provider; that rate does not establish an obligation for 
the transmission provider to purchase such reactive power. Those 
individual rates establish only the charges that transmission providers 
will include in transmission rates if, and only if the transmission 
providers' OATTs require the payment of compensation for reactive 
power.\154\
---------------------------------------------------------------------------

    \151\ Eagle Creek Initial Comments at 4; NHA Initial Comments at 
8-9.
    \152\ The Commission has explained that the Mobile-Sierra 
``public interest'' presumption applies to an agreement only if the 
agreement has certain characteristics that justify the presumption. 
In ruling on whether the characteristics necessary to justify a 
Mobile-Sierra presumption are present, the Commission must determine 
whether the agreement at issue embodies either: (1) individualized 
rates, terms, or conditions that apply only to sophisticated parties 
who negotiated them freely at arm's length; or (2) rates, terms, or 
conditions that are generally applicable or that arose in 
circumstances that do not provide the assurance of justness and 
reasonableness associated with arm's-length negotiations. Unlike the 
latter, the former constitute contract rates, terms, or conditions 
that necessarily qualify for a Mobile-Sierra presumption. E.g., 
Linden VFT, LLC v. Pub. Serv. Elec. & Gas Co., 161 FERC ] 61,264, at 
P 27 (2017); PJM Interconnection, L.L.C., 161 FERC ] 61,262, at P 18 
(2017); Sw. Power Pool, Inc., 144 FERC ] 61,059, at P 127 (2013), 
order on reh'g and compliance, 149 FERC ] 61,048, at P 94 (2014) 
(citations omitted); Midwest Indep. Transmission Sys. Operator, 
Inc., 142 FERC ] 61,215, at P 177 (2013), order on reh'g and 
compliance, 147 FERC ] 61,127, at P 108 (2014) (citations omitted).
    \153\ See, e.g., Wabash Valley Power Ass'n, Inc. v. FERC, 45 
F.4th 115, 120 (D.C. Cir. 2022) (``[A] contract requiring the 
purchaser to pay a utility's `going rate' on file with FERC, without 
more, does not eliminate review under the ordinary just-and-
reasonable standard.'').
    \154\ Cf. Whitetail Solar 3, LLC, Opinion No. 583, 184 FERC ] 
61,145, at P 45 (2023) (affirming the Presiding Judge's finding that 
Schedule 2, not Applicants' interconnection agreements, determines 
whether generating facilities are eligible for compensation, 
therefore, ``there is no reason for the Commission to amend the 
[interconnection agreements] of all existing distribution-connected 
generation, as Applicants suggest would be necessary in light of the 
Initial Decision.''); see also MISO, 182 FERC ] 61,033 at P 63 (``As 
described above, MISO [Transmission Owners] have the unilateral 
right to change Schedule 2 through an FPA section 205 filing and by 
doing so, they automatically change the rate payable for Reactive 
Service that generators contractually agreed to in section 9.6.3 of 
their GIAs.'' (citations omitted)).
---------------------------------------------------------------------------

    60. As discussed above, the final determination requires revisions 
to

[[Page 93423]]

Schedule 2 to prohibit the inclusion in transmission rates of charges 
associated with reactive power in the standard power factor range and, 
for consistency, also requires conforming revisions to the pro forma 
LGIA and pro forma SGIA to remove language related to the comparability 
standard. Since Schedule 2 is a tariff-based rate, that rate can be 
modified under the ordinary just and reasonable standard.\155\ However, 
this final determination does not affect the ability of generating 
facilities to pursue claims that they have an independent contractual 
right to reactive power compensation within the standard power factor 
range, based on a bilateral agreement with the relevant transmission 
owner.\156\
---------------------------------------------------------------------------

    \155\ See Joint Customers Reply Comments at 14 (``There is no 
validity to the argument that individual rate challenges must be 
pursued by the Commission or complainants, and it is well 
established that a change to the underlying Schedule 2 in a 
transmission provider's tariff, as proposed by the Commission in the 
NOPR, will contemporaneously end compensation to third-party 
generators with no further action required.'').
    \156\ For example, ISO-NE and NEPOOL claim that certain 
agreements exist that do not obligate certain non-generator 
resources to provide reactive power either within or outside of the 
standard power factor range and are still entitled to compensation. 
See supra n.142; ISO-NE Initial Comments at 9; NEPOOL Reply Comments 
at 9. We express no opinion here as to whether any such generating 
facility, such as those situations noted by ISO-NE and NEPOOL, would 
be entitled to such compensation under such agreements.
---------------------------------------------------------------------------

    61. We also find that Generation Developers' and Reactive Service 
Providers' \157\ assertions that the final determination would violate 
Atlantic City by depriving generating facilities of their FPA section 
205 filing rights lack merit. The Commission is not depriving 
generating facilities of their filing rights. The commenters' arguments 
fundamentally misunderstand generating facility compensation under the 
Commission's pro forma OATT and interconnection agreements. The final 
determination is not adjusting, overturning, or reducing to zero any 
generating facility's rate for reactive power within the standard power 
factor range. The final determination addresses only the justness and 
reasonableness of transmission rates chargeable to transmission 
customers under Schedule 2 and by extension, payable to the 
transmission providers' own generating facilities or affiliated 
generating facilities and third-party generating facilities under the 
comparability standard, consistent with their interconnection 
agreements, not any independent right of generating facilities to 
establish a rate under FPA section 205. While this does result in 
generating facilities, affiliated and non-affiliated, no longer being 
entitled to compensation for the provision of reactive power within the 
standard power factor range as a function of comparability, the 
Commission has found that such an outcome does not undermine the 
generating facilities' FPA section 205 filing rights.\158\
---------------------------------------------------------------------------

    \157\ Generation Developers Initial Comments at 31-32 (citing 
Atl. City, 295 F.3d at 9-10); Reactive Service Providers Initial 
Comments at 54.
    \158\ Cf. MISO, 182 FERC ] 61,033 at P 65 (``[W]e find that MISO 
TOs' proposal does not restrict independent power producers' FPA 
section 205 rights to file a rate for reactive power; instead, the 
proposal addresses only the rates chargeable to transmission 
customers under Schedule 2 and by extension, payable to resources 
consistent with their GIAs, not any independent right of generators 
to seek compensation under FPA section 205.''); Opinion No. 583, 184 
FERC ] 61,145 at P 45 (``Applicants' [interconnection agreements] do 
not establish an independent right outside the context of Schedule 2 
to reactive power compensation for merely meeting the technical 
requirements required for interconnection.''); see also Joint 
Customers Initial Comments at 14 (``Without comparability as an 
issue, it is existing Commission policy that it is inappropriate to 
compensate within the standard power factor range. The Order No. 
2003 determination that compensation should not be paid for reactive 
service meeting interconnection requirements remains well 
supported.'' (emphasis in original)). We also note that individual 
generating facility reactive power tariffs themselves do not 
establish a payment obligation, only the rate that a buyer will pay 
if it takes service. A tariff rate is an offer to sell service at 
the stated rate; it does not establish an obligation on any party to 
pay that rate. See 18 CFR 35.2(c)(1) (``The term tariff as used 
herein shall mean a statement of (1) electric service as defined in 
paragraph (a) of this section offered on a generally applicable 
basis) (emphasis added)); Sw. Power Pool, Inc., 149 FERC ] 61,048 at 
P 106 (``The Commission's use of the term `tariff rates' as 
generally applicable rates is justified by the definition of the 
term `tariff' set forth in the Commission's regulations under the 
FPA, which state, in part, that a tariff is `a statement of . . . 
electric service . . . offered on a generally applicable basis.' 
''). In order to constitute an obligation, a party must sign a pro 
forma or other service agreement. See Cal. Indep. Sys. Operator 
Corp., 100 FERC ] 61,234, at 61,834 (2002) (``[T]he Commission moved 
to a paradigm of standard agreements in which terms and conditions 
that are included in a public utility's OATT and bilateral contracts 
are replaced by pro forma service agreements''). Therefore, if 
transmission providers revise their Schedule 2's to eliminate 
compensation for the provision of reactive power within the standard 
power factor range, no party will exist to pay the generating 
facility's filed tariff rate. See, e.g., PNM, 178 FERC ] 61,088 
(finding that the transmission owner is not required to pay for 
reactive power, but not instituting section 206 proceedings to 
cancel reactive power tariffs).
---------------------------------------------------------------------------

B. Cost of Producing Reactive Power

    62. The NOPR preliminarily found that providing compensation for 
the provision of reactive power within the standard power factor range 
is unjust and unreasonable. The Commission relied on three key points 
to support this preliminary finding.
    63. First, the NOPR relied on the Commission's prior findings that, 
for both synchronous and non-synchronous generating facilities, because 
all equipment used to produce reactive power is also necessary to 
produce and deliver real power to the transmission system, there are no 
incremental fixed costs associated with the provision of reactive power 
within the standard power factor range.\159\ The NOPR also explained 
that the Commission has repeatedly found, that ``[v]ariable costs of 
generating reactive power are de minimis'' and ``generally limited to 
changes in losses within the generating facility which are part of the 
overall efficiency of the resource and, as such, are typically captured 
in the resource offers.'' \160\ Thus, by providing reactive power 
within the standard power factor range, both synchronous and 
nonsynchronous facilities incur no additional fixed costs and at most 
de minimis variable costs beyond which they already incur to provide 
real power.\161\
---------------------------------------------------------------------------

    \159\ NOPR, 186 FERC ] 61,203 at PP 29-31 (``[S]ynchronous and 
non-synchronous resources provide real and reactive power as joint 
products, with joint costs.'').
    \160\ Id. P 31.
    \161\ Id. PP 8, 28.
---------------------------------------------------------------------------

    64. Second, the NOPR relied on the fact that all generating 
facilities must provide reactive power within the standard power factor 
range as an obligation of good utility practice and to meet the 
obligations under their interconnection agreements.\162\

[[Page 93424]]

Additionally, the NOPR emphasized that ``reactive support by generating 
facilities operating within the standard power factor range ensures 
that when these facilities inject real power--the product that their 
facilities exist to create and sell--onto the grid under normal 
conditions, they can do their part to maintain adequate voltages and to 
not threaten reliability.'' \163\ In other words, a generating facility 
must produce reactive power within the standard power factor range in 
order to generate and safely inject real power into the transmission 
system and comply with reliability requirements. As such, providing 
reactive power within the standard power factor range can be regarded 
as a joint product with providing real power, with joint costs.
---------------------------------------------------------------------------

    \162\ Id. P 33 (citing MISO, 182 FERC ] 61,033 at P 53 
(``Bearing in mind that the provision of reactive power within the 
standard power factor range is, in the first instance, an obligation 
of the interconnecting generator and good utility practice, MISO 
[transmission owners] do not have an obligation to continue to 
compensate an independent generator for reactive power within the 
standard power factor range when its own or affiliated generators 
are no longer being compensated.'' (citations omitted)); id. P 54 
(``We find unpersuasive protesters' arguments that it is not just 
and reasonable to eliminate compensation for Reactive Service within 
the standard power factor range because generators have come to rely 
on the compensation for Reactive Service in order for the generators 
to remain financially viable. The Commission has previously rejected 
such arguments, finding that all newly interconnecting generators 
are required to provide reactive power within the power factor range 
of 0.95 leading to 0.95 lagging as a condition of interconnection.'' 
(citations omitted)); PNM, 178 FERC ] 61,088 at PP 29, 33 (rejecting 
generating facility's arguments that it is ``just and reasonable for 
it to be compensated for investments made'' to provide reactive 
support consistent with interconnection requirements even though 
transmission provider elected to no longer pay its own or affiliate 
generators for such reactive power); Nev. Power Co., 179 FERC ] 
61,103 at P 22 (finding that the generating facility's argument, 
``that it is not just and reasonable to eliminate their compensation 
for reactive service because they made investments in their 
generating facilities based on the expectation that they would 
receive compensation for reactive service,'' unpersuasive because 
all newly interconnecting generators are required to provide 
reactive power within the standard power factor range as a condition 
of interconnection); Order No. 2003, 104 FERC ] 61,103 at P 546.
    \163\ NOPR, 186 FERC ] 61,203 at P 13 (citing MISO Rehearing 
Order, 184 FERC ] 61,022 at P 23).
---------------------------------------------------------------------------

    65. Third, the NOPR noted that in regions where generating 
facilities recover their costs by participating in organized 
competitive wholesale markets, providing separate compensation for the 
provision of reactive power within the standard power factor range 
risks overcompensation and market distortions in ways that did not 
exist prior to the existence of organized markets.\164\ The NOPR 
explained that the AEP Methodology was created in an era of vertically 
integrated utilities, when most utilities filed FERC Form No. 1s, used 
the Uniform System of Accounts (USofA) to classify their costs, and 
recovered those costs through cost-based rates.\165\ Today, however, 
most generating facilities recover their costs through competitive 
markets in both RTO/ISO and non-RTO/ISO regions, so the imprecision of 
the AEP Methodology, the NOPR explained, becomes more significant 
because it can lead to arbitrary increases in the utility's total 
recovery when cost-based reactive power payments are added to any 
market recoveries.\166\ The NOPR added that this is especially true 
when markets fail to account for separate, cost-based reactive power 
revenues by using standard rate making techniques.\167\
---------------------------------------------------------------------------

    \164\ Id. at P 39.
    \165\ Id.
    \166\ Id.
    \167\ Id. at 39 & nn.100-02. The Commission noted that, in PJM 
for example, while the capacity market rules currently account for 
reactive power payments to resources by assuming average reactive 
power compensation of $2,546 per MW-year, reactive power revenue 
requirements in PJM range from roughly $1,000 per MW-year to $13,000 
per MW-year. The Commission noted that this wide range of actual 
compensation, which is both above and below the assumed reactive 
power compensation in the capacity market rules, can lead to market 
distortions.
---------------------------------------------------------------------------

1. Comments
    66. Many commenters support the NOPR's finding that transmission 
charges for generating facilities' provision of reactive power within 
the standard power factor range are unjust and unreasonable.\168\ 
Likewise, many commenters support the NOPR's preliminary finding that 
generating facilities already provide reactive power within the 
standard power factor range at no cost or de minimis cost.\169\ Ameren 
and MISO Transmission Owners agree with the NOPR that providing 
reactive power within the standard power factor range requires little 
or no cost to generators because the same equipment used to produce 
real power includes reactive power functions.\170\ In support, MISO 
Transmission Owners point to MISO and the MISO Rehearing Order wherein 
the Commission also concluded that, based on that record, reactive 
power service within the standard power factor range required little or 
no incremental investment. MISO Transmission Owners add that, as the 
Commission found in the MISO Rehearing Order, even newer wind turbines 
use inverters that allow generating facilities to produce and control 
reactive power without costly additional equipment.\171\ MISO 
Transmission Owners also state that generating facility equipment 
typically comes with reactive power capabilities that not only meet the 
standard range requirements (i.e., 0.95 leading and 0.95 lagging) but 
exceed them (e.g., 0.80-0.90).\172\ MISO Transmission Owners argue that 
since generating facilities bear no or at most de minimis incremental 
costs to provide reactive power within the standard power factor range, 
one must consider what the actual purpose is of compensating generating 
facilities for such service.\173\
---------------------------------------------------------------------------

    \168\ AEP; Ameren; Joint Consumer Advocates; Joint Customers; 
MISO Transmission Owners; New England Consumer Advocates; Ohio FEA; 
PGE; PJM; the PJM IMM; the Transmission Access Policy Study Group.
    \169\ See Ameren Initial Comments at 3; Joint Customers Reply 
Comments at 11-13; MISO Transmission Owners Initial Comments at 5-7; 
New England Consumer Advocates Initial Comments at 4-6; PJM IMM 
Initial Comments at 4.
    \170\ Ameren Initial Comments at 3 (citing BPA, 120 FERC ] 
61,211 at P 21 (``Evidence from numerous reactive power rate filings 
demonstrates newly interconnecting resources have the capability to 
provide reactive power, some well in excess of the required 0.95 
leading to 0.95 lagging. It is also well-documented that the same 
equipment used to produce real power includes reactive power 
functions and thus there is little, if any, incremental cost 
associated with providing reactive power.'')); MISO Transmission 
Owners Initial Comments at 5-7 (citing MISO, 182 FERC ] 61,033 at P 
55; MISO Rehearing Order, 184 FERC ] 61,022 at PP 25 n.76, 29-30, 
34, 41-42 (``[T]he record establishes, that Reactive Service 
requires little or no incremental investment.'')); MISO Transmission 
Owners Reply Comments at 9; see also Ohio FEA Initial Comments at 3.
    \171\ MISO Transmission Owners Initial Comments at 7 & n.18 
(citing MISO Rehearing Order, 184 FERC ] 61,022 at P 30 n.98 
(``[O]lder wind generators could not produce and control reactive 
power without the use of costly equipment [ ] `because they did not 
use inverters like other non-synchronous generators' but modern 
turbines now use inverters and newer wind generators now can.'')).
    \172\ Id. at 7.
    \173\ Id. at 9.
---------------------------------------------------------------------------

    67. Joint Customers state that attempts to undermine the NOPR, such 
as challenging the assertion that incremental costs of providing 
reactive service within the standard power factor range are de minimis, 
are meritless.\174\ Joint Customers argue that the costs incurred by 
generators to meet interconnection requirements are necessary for safe 
and reliable grid operations and that arguments against the de minimis 
designation often misrepresent the incremental costs involved in 
meeting interconnection requirements versus providing additional 
reactive capability.\175\ Joint Customers note that claims of excessive 
costs for non-synchronous generators to comply with power factor 
requirements are collateral attacks on prior Commission orders, 
particularly Order No. 827.\176\
---------------------------------------------------------------------------

    \174\ Joint Customers Reply Comments at 11-13.
    \175\ Id.
    \176\ Id. at 13 (citing Order No. 827, 155 FERC ] 61,277 at P 11 
(``Prior to Order No. 827, non-synchronous generators were exempt 
from complying with power factor requirements. The entire point of 
Order No. 827 was to find that technological advancements had 
reduced the cost of compliance such that non-synchronous generators 
no longer needed the exemption. The order also explicitly maintained 
the compensation scheme for reactive power, with all that means for 
the elimination of compensation if not justified by 
comparability.'').
---------------------------------------------------------------------------

    68. The PJM IMM, MISO Transmission Owners, and several other 
commenters assert that providing reactive power within the standard 
power factor range is an obligation of interconnection and consistent 
with good utility practice.\177\ The PJM IMM asserts that the 
Commission has a long

[[Page 93425]]

standing policy that ``treats the provision of reactive power inside 
the [standard power factor range] as an obligation of good utility 
practice rather than as a compensable service and permits compensation 
inside the [standard power factor range] only as a function of 
comparability.'' \178\
---------------------------------------------------------------------------

    \177\ PJM IMM Initial Comments at 6-9 (citing PJM, OATT, 
Attachment O, Sec. Sec.  4.7.1.1.1., 4.7.1.2. (3.0.0)); Joint 
Consumer Advocates Initial Comments at 6-7; MISO Transmission Owners 
Reply Comments at 4; TAPS Initial Comments at 6; Ohio FEA Initial 
Comments at 5; Joint Customers Initial Comments at 14-16; PGE 
Initial Comments at 4 (citing MISO, 182 FERC ] 61,033 at P 53 
(noting that in the acceptance of the MISO Transmission Owners 
application to end compensation within the standard power 
application, the Commission reiterated its policy ``that the 
provision of reactive power within the standard power factor range 
is, in the first instance, an obligation of the interconnecting 
generator and good utility practice.'')).
    \178\ PJM IMM Initial Comments at 6-8 (citing NOPR, 186 FERC ] 
61,203 at P 5 (citing BPA Rehearing Order, 125 FERC ] 61,273 at P 
18)); see also MISO Transmission Owners Initial Comments at 10-12.
---------------------------------------------------------------------------

    69. The PJM IMM states that reactive power is not the only design 
obligation the generation interconnection customers assume.\179\ The 
PJM IMM notes, for example, that generating facilities are required to 
provide primary frequency response capability, but the PJM OATT does 
not provide an out of market payment for such service because it is 
treated as an obligation assumed by generation interconnection 
customers for receiving interconnection service.\180\ MISO Transmission 
Owners also point out that the SEIA, the national trade association for 
the U.S. solar industry, has acknowledged that reactive power 
compensation does not affect a generator's operations and that 
provision of reactive power within the standard power factor range is 
required regardless of compensation.\181\
---------------------------------------------------------------------------

    \179\ PJM IMM Initial Comments at 8.
    \180\ Id. (citing PJM, OATT, Attachment O Sec.  4.7.2. (3.0.0)).
    \181\ MISO Transmission Owners Initial Comments at 9 & n.24 
(citing SEIA, Reactive Power Compensation: How to Unlock New Revenue 
Opportunities for Solar and Storage Projects, Solar Energy 
Industries Association 4 (July 29, 2020), <a href="https://old.seia.org/sites/default/files/2023-01/Speaker%20Q&A%20-%20Reactive%20Power%20Compensation%20Webinar.pdf">https://old.seia.org/sites/default/files/2023-01/Speaker%20Q&A%20-%20Reactive%20Power%20Compensation%20Webinar.pdf</a> (also attached as 
Exhibit I) (``Filing for and receiving reactive revenues has no 
impact on the generator's operating profile. The ISO/RTOs have a 
right to dispatch generators to provide reactive service as needed 
to maintain reliability.'')). The MISO Transmission Owners also add 
that ``[a]t the same time MISO was experiencing a dramatic increase 
in the amounts transmission customers paid for reactive power 
service prior to its elimination of compensation for reactive power 
service within the deadband, SEIA highlighted that MISO was one of 
the two `most lucrative' regions for reactive power compensation, 
where generators received millions of dollars in compensation for 
having the capability to produce reactive power within the deadband, 
a capability that was already a condition of obtaining 
interconnection.'' Id. at 9-11.
---------------------------------------------------------------------------

    70. Additionally, MISO Transmission Owners agree that the 
Commission's line of precedent since Order No. 2003 has required 
interconnecting generators to be able to provide reactive power within 
the standard power factor range without compensation, with few 
exceptions.\182\ MISO Transmission Owners argue that generators are 
incented by their own reliability requirements to install the equipment 
that will help keep their projects on-line and delivering real power, 
and that ``skimping'' on equipment that can provide reactive power 
across a range of operating conditions is not in generators' best 
operational interests or consistent with good utility practice.\183\ 
MISO Transmission Owners state that generating facilities are also 
required by the North American Electric Reliability Corporation (NERC) 
reliability standards to operate in automatic voltage control mode and 
maintain a voltage set point provided by the transmission 
provider.\184\
---------------------------------------------------------------------------

    \182\ Id. at 10-11 (citing Order No. 2003, 104 FERC ] 61,103 at 
P 546; Order No. 2003-A, 106 FERC ] 61,220 at PP 410, 416; Order No. 
827, 155 FERC ] 61,277 at P 59).
    \183\ Id. at 11 & n.29 (citing MISO Rehearing Order, 184 FERC ] 
61,022 at P 35 n.116 (``[G]enerators have incentives to install 
equipment to ensure that their generation remains online and 
delivering real power.'')).
    \184\ Id. at 11-12 (citing Reliability Standard VAR-002-3--
Generator Operation for Maintaining Network Voltage Schedules), at 2 
(Aug. 1, 2014), <a href="http://www.nerc.com/pa/Stand/Reliability%20Standards/VAR-002-3.pdf">http://www.nerc.com/pa/Stand/Reliability%20Standards/VAR-002-3.pdf</a> (``R2 . . . Generator Operator 
shall maintain the generator voltage or Reactive Power schedule 
(within each generating Facility's capabilities).'').
---------------------------------------------------------------------------

    71. MISO Transmission Owners and the PJM IMM agree with the NOPR's 
preliminary finding that the current reactive power compensation 
framework allows for undue compensation and potential market 
distortions, and they argue that the current compensation framework 
leads to ``black-box'' settlements that lack transparency and result in 
vastly disparate rates.\185\ The PJM IMM argues that separately 
compensating resources based on a judgment-based allocation of capital 
costs is not appropriate in the PJM markets.\186\ The PJM IMM argues 
that cost-of-service compensation for reactive power distorts markets 
and undermines competition.\187\ The PJM IMM asserts that the current 
rules create strong incentives for generating facilities to attempt to 
maximize the allocation of capital costs to reactive service in order 
to maximize guaranteed, nonmarket revenues.\188\ The PJM IMM claims 
that there is no reasonable basis for the disparity in the price to 
customers from different types of generators for the same service and 
that reactive power is a homogeneous product which should have the same 
price for all sellers. The PJM IMM notes that the most recent reactive 
power rate cases settled prior to issuance of the NOPR have resulted in 
costs well in excess of the reactive power revenue offset assumed in 
PJM's capacity market.\189\
---------------------------------------------------------------------------

    \185\ Id. at 8; PJM IMM Initial Comments at 4-6; see also Joint 
Customers Initial Comments at 4-6.
    \186\ PJM IMM Initial Comments at 3-4.
    \187\ Id. at 4-6.
    \188\ Id. at 4. The PJM IMM asserts that these revenues provide 
a nonmarket advantage to generating facilities that receive them, 
resulting in an arbitrary and nonmarket-based advantage (i.e., 
distortionary).
    \189\ Id. at 6 (explaining that in PJM's capacity market, ``the 
parameters that define the demand curve . . . are based on the costs 
of new entry of a reference generating unit, less net revenues from 
other PJM markets'' such as reactive power revenues). The PJM IMM 
explains that the level of these net revenues that are subtracted, 
or offset, from the costs of new entry, are based on a calculation 
from the PJM IMM of the average Schedule 2 payment for reactive done 
in 2008 and based on reactive rates from prior years. However, the 
PJM IMM states that ``[m]ost recent cases settled prior to issuance 
of the NOPR have settled for costs well in excess of the average 
cost and well in excess of the [] offset amount'' and that ``[t]he 
issue is growing in significance.'' Id. at 5.
---------------------------------------------------------------------------

    72. Many other commenters, in contrast, challenge the Commission's 
preliminary finding that providing reactive power within the standard 
power factor range has no or de minimis costs.\190\ The Indicated Trade 
Associations and Generation Developers emphasize that the costs of 
equipment and production associated with reactive power, particularly 
for renewable resources, are substantial and involve significant 
capital investments.\191\ Indicated Reactive Power Suppliers, NEPGA, 
and Reactive Service Providers assert that eliminating compensation for 
reactive power within the standard power factor range is unjust and 
unreasonable, given the substantial capital costs incurred by 
generators.\192\ They argue that the NOPR's proposal fails to account 
for these costs as well as for lost opportunities for real power 
generation and renewable energy credits.\193\ They assert that the

[[Page 93426]]

Commission's proposal is inconsistent with the FPA's purpose of 
ensuring just and reasonable returns on investment, particularly for 
inverter-based resources, which incur distinct incremental costs for 
reactive power provision.\194\
---------------------------------------------------------------------------

    \190\ Eagle Creek Initial Comments at 3-4; Indicated Trade 
Associations Initial Comments at 7; ACORE Initial Comments at 2; 
Elevate Renewables Initial Comments at 9-12; Generation Developers 
Initial Comments at 13; Glenvale Initial Comments at 9-10; Indicated 
Reactive Power Suppliers Initial Comments at 2, 9-10; Indicated 
Trade Associations Initial Comments at 2, 6; Middle River Power 
Initial Comments at 2-3; NEI Initial Comments at 4-5, 8-9; NHA 
Initial Comments at 2, 4-5. Indicated Trade Associations also assert 
that prior Commission orders cited by the NOPR to support the 
assertion that no costs or de minimis costs are incurred to provide 
reactive power within the standard power factor range do not provide 
evidence to support the conclusion. Indicated Trade Associations 
Initial Comments at 8 (citing BPA, 120 FERC ] 61,211 at P 21; BPA 
Rehearing Order, 125 FERC ] 61,273 at P 7 n.7; Ariz. Pub. Serv. Co., 
94 FERC ] 61,027, at 61,080 (2001) (APS)); Onward Energy Reply 
Comments at 2.
    \191\ Indicated Trade Associations Initial Comments at 10; 
Generation Developers Initial Comments at 13.
    \192\ Indicated Trade Associations Reply Comments at 6-7; NEPGA 
Reply Comments at 3 (citing Indicated Trade Association Initial 
Comments, Affidavit of Michael Borgatti, Docket No. RM22-2-000 at 9-
10 (filed May 28, 2024)); Reactive Service Providers Initial 
Comments at 37-40.
    \193\ See Indicated Trade Associations Initial Comments at 11-12 
(``[F]or renewable resources, having to back down generation in 
order to produce reactive power would also result in lost renewable 
electricity production tax credits, renewable energy certificates, 
and similar benefits''); Generation Developers Initial Comments at 
13.
    \194\ See Indicated Trade Associations Reply Comments at 7; 
Generation Developers Initial Comments at 13, 20-21.
---------------------------------------------------------------------------

    73. Some commenters argue that there is an insufficient legal 
foundation under section 206 of the FPA to demonstrate that all 
existing reactive power rates are unjust and unreasonable.\195\ 
Generation Developers assert that the fact that many generators are 
required to provide reactive power as a condition of receiving 
interconnection service and consistent with good utility practice does 
not provide a basis for concluding that the compensation received by 
generating facilities is unjust and unreasonable.\196\ Generation 
Developers assert that the Commission's reasoning improperly assumes 
that generating facilities investing in reactive power capability are 
not performing a service that benefits the transmission system, but is 
instead only needed to support their own deliveries.\197\ Generation 
Developers assert that the NOPR's categorical determination that the 
just and reasonable reactive power rate is zero, and thus all reactive 
rates that are not zero are unjust and unreasonable, fails to comply 
with the requirements of section 206 of the FPA.\198\ NEI adds that the 
Commission failed to meet its section 206 burden because the NOPR does 
not offer substantial evidence that reactive power costs are zero or 
minimal, cost allocation is inappropriate, or reducing reactive power 
compensation to zero would allow generators to recover their costs, 
plus a reasonable rate of return.\199\
---------------------------------------------------------------------------

    \195\ Generation Developers Initial Comments at 24-25; Middle 
River Power Initial Comments at 4; NEI Initial Comments at 7; PSEG 
Initial Comments at 2-3, 11-12; Reactive Service Providers Initial 
Comments at 7-54; NYISO Initial Comments at 1.
    \196\ Generation Developers Initial Comments at 25.
    \197\ Id.
    \198\ Id. at 31; PSEG Initial Comments at 12-13.
    \199\ NEI Initial Comments at 8.
---------------------------------------------------------------------------

    74. Generation Developers assert that the Commission ignores well-
documented evidence that certain types of generating facilities, namely 
inverter-based generating facilities, incur distinct, incremental costs 
associated with providing reactive power.\200\ Generation Developers 
assert that, when the Commission first required that generating 
facilities be capable of supplying reactive power within the standard 
power factor range in Order No. 2003, it explicitly exempted wind 
generating facilities from that requirement because most wind 
generators could not maintain the power factor range.\201\ Generation 
Developers state that the Commission also generally exempted wind 
generators from operating within the standard power factor range in 
Order No. 661 because ``for wind plants, reactive power capability is a 
significant added cost.'' \202\ Generation Developers assert that while 
the Commission removed this exemption in Order No. 827 \203\ after 
finding that technological advancements made it so the cost of reactive 
power no longer presented an obstacle to the development of wind 
generation, it ``notably did not find that there were no such costs or 
even de minimis costs associated with the provision of reactive power 
by wind resources.'' \204\ Instead, Generation Developers argue that 
the Commission removed this exemption based on its finding that 
imposing an obligation on non-synchronous generating facilities to 
provide reactive power within the standard power factor range was 
necessary to support transmission service and reliability.\205\ 
Generation Developers add that, even if costs have declined over the 
years, the Commission has not demonstrated that it would be just and 
reasonable to nullify the rate schedules of facilities that came online 
years before the technological advancements referenced in Order No. 827 
and had to make incremental investments to its facility to produce 
reactive power within the standard power factor range.\206\
---------------------------------------------------------------------------

    \200\ Generation Developers Initial Comments at 13-17.
    \201\ Id. at 13 (citing Order No. 2003, 104 FERC ] 61,103 
(noting that the Commission exempted wind generation from the 
requirement because ``wind generators for the most part cannot 
maintain the required power factor, simply because the necessary 
technology does not exist for wind generators'')).
    \202\ Id. at 13-14 (citing Order No. 661, 111 FERC ] 61,353 at P 
46; Order No. 661-A, 113 FERC ] 61,254). Generation Developers add 
that in Order No. 661, the Commission was presented with evidence 
that ``wind turbines cannot meet the proposed power factor standard 
over the full range of real power output, and that dynamic VAR 
control (DVAR) banks or static capacitors would have to be installed 
at an additional expense to meet the proposed power factor over the 
entire range.'' Generation Developers Initial Comments at 13 (citing 
Order No. 661-A, 113 FERC ] 61,254 at P 45 (emphasis added)). 
Generation Developers state that while Order No. 661 was limited to 
wind resources, the Commission extended the exemption to other non-
synchronous resources on a case-by-case basis. Generation Developers 
Initial Comments at 14 (citing Nev. Power Co., 130 FERC ] 61,147, at 
P 27 (2010)).
    \203\ Order No. 827, 155 FERC ] 61,277 at P 21.
    \204\ Generation Developers Initial Comments at 14.
    \205\ Id. (citing Order No. 827, 155 FERC ] 61,277 at P 4) 
(``The Commission instead made its decision to apply reactive power 
requirements to non-synchronous resources based on its `balancing 
the costs to newly-interconnecting non-synchronous generators of 
providing reactive power with the benefits to the transmission 
system of having another source of reactive power.' '').
    \206\ Id. at 17.
---------------------------------------------------------------------------

    75. Generation Developers argue that the 2014 Staff Report is the 
most recent and comprehensive evidence on the costs that non-
synchronous generating facilities incur in providing reactive 
power.\207\ Generation Developers assert that the NOPR does not provide 
any evidence to support that the costs of providing reactive power have 
changed since the Commission's observations in the 2014 Staff Report, 
but instead relies on a rehearing order in a proceeding concerning the 
MISO transmission owners' proposal to eliminate reactive power 
compensation within the standard power factor range for the proposition 
that non-synchronous generating facilities have no or de minimis 
costs.\208\ Generation Developers assert that the Commission's reliance 
on a statement from the MISO Rehearing Order, and the purported failure 
of parties in that proceeding to demonstrate costs of non-synchronous 
facilities, does not satisfy the Commission's burden in this case.\209\ 
Generation Developers add that the Commission's reliance on cases that 
pre-date the emergence of non-synchronous generating facilities for the 
proposition that all generating facilities have no or de minimis costs 
is misplaced.\210\ For example, Generation Developers contend that the 
Commission erred in citing Duke Energy Corporation's comments to the 
NOI in support of its finding that the inverter is the most critical 
equipment for the production of reactive power from non-synchronous 
resources.\211\
---------------------------------------------------------------------------

    \207\ Id. at 14-15 (citing 2014 Staff Report (``[M]ost dynamic 
reactive power, which is crucial to transmission system reliability, 
is provided by generators.''). Specifically, Generation Developers 
state that the 2014 Staff Report made the following findings: ``(1) 
the costs of reactive power equipment for wind generators range from 
3.18% to 4% of their capital costs; and (2) the costs of adding 
reactive power capability to solar photovoltaic generators range 
from 2% to 20% of a project's total costs, depending on project 
size.'' Id. at 15 (citing 2014 Staff Report app. 2 at 2-3).
    \208\ Id. at 15 (citing NOPR, 186 FERC ] 61,203 at P 29 n.70 
(citing MISO Rehearing Order, 184 FERC ] 61,022 at P 30)).
    \209\ Id.
    \210\ Id. at 16 (citing BPA, 120 FERC ] 61,211; METC Rehearing 
Order, 97 FERC at 61,852-53; APS, 94 FERC at 61,080).
    \211\ Id. at 16-17 n.52 (citing Duke Energy Corporation Initial 
Comments to the NOI at 4).
---------------------------------------------------------------------------

    76. PSEG similarly notes that the Commission has long used the AEP 
Methodology to allocate costs associated

[[Page 93427]]

with the provision of reactive power within the standard power factor 
range.\212\ PSEG witness Dr. Dumais observes that the AEP Methodology 
identifies four categories of equipment costs that are involved in the 
production of reactive power from synchronous generating 
facilities.\213\
---------------------------------------------------------------------------

    \212\ PSEG Initial Comments at 9.
    \213\ Id., Prepared Testimony of Dr. Paul A. Dumais at 11, 1:11.
---------------------------------------------------------------------------

    77. Indicated Trade Associations argue that the cases cited to in 
the NOPR to support the finding that there are no or de minimis costs 
associated with producing reactive power do not support the 
Commission's assertion.\214\ For example, Indicated Trade Associations 
assert that in BPA, the Commission summarily stated without evidence 
that ``the incremental cost of reactive power service within the 
deadband is minimal.'' \215\ Indicated Trade Associations assert that, 
on rehearing, however, when a party argued that `` `only the short-run 
marginal cost of producing the next increment of reactive power `can 
logically be described as minimal' because it excludes capability 
costs,' . . . the Commission sidestepped this issue, stating that `the 
issue of whether or not the cost is minimal is not relevant to whether 
the independent power producers are entitled to compensation.' '' \216\ 
Indicated Trade Associations argue that in APS, another order cited in 
the NOPR, ``the Commission simply noted that intervenors `have not 
demonstrated that [the proposed reactive power] requirement will limit 
the real power output of a generating unit and therefore will not 
result in any lost opportunity costs.' '' \217\
---------------------------------------------------------------------------

    \214\ Indicated Trade Association Initial Comments at 7-8.
    \215\ Id. at 8 (citing BPA, 120 FERC ] 61,211 at P 21).
    \216\ Id. (citing BPA Rehearing Order, 125 FERC ] 61,273 at 
n.7).
    \217\ Id. (quoting APS, 94 FERC at 61,080; citing NOPR, 186 FERC 
] 61,203 at P 29 n.70).
---------------------------------------------------------------------------

    78. Elevate and Glenvale further argue that the Commission's 
assumption that all resource classes, including energy storage 
resources, incur no or minimal costs is unsupported by evidence.\218\ 
Elevate asserts that recurring capital investments are required to 
address battery degradation caused by the provision of reactive 
power.\219\ Specifically, Elevate argues that while the level of 
degradation increases as the reactive power to real power ratio moves 
further from unity, even the provision of reactive power within the 
standard power factor range contributes to the degradation of the 
storage resource's capability.\220\ Elevate states that energy storage 
resources must make significant and recurring capital investments to 
address this degradation, which, in Elevate's experience, costs 
approximately one percent of the resource's original capital investment 
annually.\221\ Elevate asserts that the record is devoid of any 
evidence that energy storage resources incur no or de minimis costs to 
provide reactive power.\222\ Glenvale argues that there are marginal, 
operational, and replacement costs associated with providing reactive 
power within the power factor range for solar generating 
facilities.\223\ Specifically, Glenvale asserts that, at the capital 
investment stage, there are different inverter options that allow 
generating facilities to provide reactive service outside of generating 
hours (e.g., allowing solar generating facilities to provide reactive 
power at night) and that this incurs additional costs which would not 
be required if the generating facility were not set up to provide 
reactive power at night.\224\ Glenvale also asserts that inverters use 
electricity to provide reactive power, explaining that when a 
generating facility is synchronized, this presents as reduced 
generation, and when a generating facility is not synchronized, the 
generator must either use an alternate power source or it presents as 
negative generation (both of which Elevate states result in additional 
costs).\225\ Glenvale also states that the provision of reactive power 
can result in a reduced inverter service life.\226\ Glenvale notes that 
it is difficult to allocate these costs among each of the three service 
conditions--within the standard power factor range while synchronized, 
within the standard power factor range at night, and outside the 
standard power factor range at all times--but Glenvale asserts that at 
least some of the costs are attributable to providing reactive power 
within the standard power factor range.\227\ NEI asserts that there are 
real costs for nuclear generating facilities to provide and maintain 
reactive power capability, including: properly sized generators, 
maintenance associated with normal operations to preserve reactive 
power capability, and additional repairs that may be needed to address 
age-related degradation to equipment that might otherwise impair 
reactive power capability.\228\
---------------------------------------------------------------------------

    \218\ Elevate Initial Comments at 9-12; Elevate Reply Comments 
at 7-9; Glenvale Initial Comments at 9-10.
    \219\ Elevate Initial Comments at 9-12; Elevate Reply Comments 
at 7-9.
    \220\ Elevate Reply Comments at 8.
    \221\ Id.
    \222\ Elevate Initial Comments at 12.
    \223\ Glenvale Initial Comments at 9-10.
    \224\ Id. at 9.
    \225\ Id.
    \226\ Id. at 9-10 & n.29 (citing Ramanathan Thiagarajan, Adarsh 
Nagarajan, Peter Hacke, and Ingrid Repins, Effect of Reactive Power 
on Photovoltaic Inverter Reliability and Lifetimes (2019), <a href="https://www.nrel.gov/docs/fy19osti/73648.pdf">https://www.nrel.gov/docs/fy19osti/73648.pdf</a>.) (``One characterization in 
recent research is that providing reactive power within the standard 
power factor range reduces service life by one year, and that 
providing reactive power outside of the standard range reduces 
service life by a second year.'')).
    \227\ Id. at 10.
    \228\ NEI Initial Comments at 5.
---------------------------------------------------------------------------

    79. Relatedly, NEI explains that nuclear generators are most likely 
to be called upon to provide reactive power services and thus are the 
generators most likely to face accelerated degradation and damage to 
reactive power equipment.\229\
---------------------------------------------------------------------------

    \229\ Id. at 14-16.
---------------------------------------------------------------------------

    80. Reactive Service Providers argue that there is no evidence to 
support the claim that providing reactive power within the standard 
power factor range requires no incremental investment, and that even if 
the investment needed were de minimis, that would not be a reason to 
not provide compensation.\230\ Reactive Service Providers further 
contend that there is no evidence that the costs of providing reactive 
service have increased since the advent of RTOs and IPPs \231\ or that 
generating facilities are recovering their costs in regions where 
transmission providers do not provide compensation.\232\
---------------------------------------------------------------------------

    \230\ Reactive Service Providers Initial Comments at 37-40.
    \231\ Id. at 31-34.
    \232\ Id. at 37-41.
---------------------------------------------------------------------------

    81. Eagle Creek criticizes the Commission's determination that 
there are no or de minimis costs associated with the provision of 
reactive power in the standard power factor range as flawed based on 
its own tariff cases under the AEP Methodology and argues that 
eliminating compensation for reactive power would be arbitrary and 
capricious.\233\ ACORE, Indicated Reactive Power Suppliers, and Middle 
River Power similarly argue that their facilities have demonstrated 
just and reasonable compensation covering actual reactive power costs 
during settlement negotiations.\234\
---------------------------------------------------------------------------

    \233\ Eagle Creek Initial Comments at 3-4. Eagle Creek argues 
that, for each of its tariff cases, it submitted evidence 
documentation of the fixed and sunk costs that it invested to 
increase its reactive power generation. Id.
    \234\ ACORE Initial Comments at 2; Indicated Reactive Power 
Suppliers Initial Comments at 9; Middle River Power Initial Comments 
at 2-3 (noting that Middle River Power owns 19 fossil-fired 
generating facilities that recover approximately $4.5 million in 
annual reactive power revenues through their reactive service 
tariffs on file with Commission, which it argues were ``demonstrated 
in rigorous proceedings before the Commission'' to be just and 
reasonable compensation covering actual costs).

---------------------------------------------------------------------------

[[Page 93428]]

    82. Indicated Trade Associations assert that the Commission fails 
to reconcile the NOPR's insistence that there are no segregable costs 
associated with the provision of reactive power with its longstanding 
precedent of the AEP Methodology, where the Commission approved 
isolating costs of providing reactive power.\235\ NEI asserts that, 
rather than point to actual data that demonstrates generating facility 
costs for providing reactive power, the NOPR relies on the misplaced 
theory that ``because both synchronous and non-synchronous resources 
provide real and reactive power as joint products, with joint costs, . 
. . any allocation of joint fixed costs between real and reactive power 
could be viewed as inherently arbitrary.'' \236\ NEI and Generation 
Developers argue that the AEP Methodology compensates generators based 
on their actual costs and reactive capabilities, providing them with a 
just and reasonable opportunity to recover their investments in 
reactive service capability, and asserts that the Commission has 
repeatedly confirmed this cost allocation methodology and its 
underlying factual predicates in numerous proceedings.\237\ Generation 
Developers suggest that the Commission has allocated real and reactive 
power costs using the AEP Methodology for over two decades \238\ and 
has rejected arguments that the AEP Methodology results in an improper 
allocation of costs or is used merely as a matter of administrative 
convenience.\239\ The NHA asserts that the Commission correctly 
identifies real power and reactive power as jointly produced 
commodities, but it incorrectly attributes the cost of all generation 
equipment to be predominantly for the production of real power.\240\
---------------------------------------------------------------------------

    \235\ Indicated Trade Associations Initial Comments at 9; see 
also id. (citing Va. Elec. & Power Co., 114 FERC ] 61,318, at P 3 
(2006)) (``[T]he Commission expressly instructed generators to use 
the AEP Methodology `to compute the portion of plant investment 
attributable to reactive power production . . . Because these 
production plants produce real and reactive power, AEP developed an 
allocation factor to segregate the reactive production function from 
the real power production function. The allocation factor is used to 
determine the amount of investment allocable to reactive power.' '') 
(emphasis added by Indicated Trade Associations)).
    \236\ NEI Initial Comments at 10 (citing NOPR, 186 FERC ] 61,203 
at P 30)
    \237\ Id. at 10-11; Generation Developers Initial Comments at 7-
9.
    \238\ Generation Developers Initial Comments at 8-9 (citing 
Dynegy Midwest Generation, Inc., 125 FERC ] 61,280 at P 11; 
Bluegrass Generation Co., L.L.C., 118 FERC ] 61,214, order on reh'g, 
121 FERC ] 61,018, at P 12 (2007)).
    \239\ Id. (citing Bluegrass Generation Co., 121 FERC ] 61,018 at 
P 12 (``This policy is not a matter of administrative convenience . 
. . but the result of the Commission's deliberate determination that 
the AEP methodology is a just and reasonable manner of calculating a 
reactive power revenue requirement'').
    \240\ NHA Initial Comments at 4-5 (noting that ``[t]here is no 
basis for this assumption, especially if the Commission believes the 
AEP Methodology is incapable of isolating real and reactive 
cost.'').
---------------------------------------------------------------------------

    83. Clean Energy Associations assert that reactive power is not 
always coupled with real power as they believe the Commission states in 
the NOPR.\241\ Middle River Power argues that the Commission's 
statement that generating facilities are being asked to provide 
reactive power in order to offset the impact of the power they inject 
into the system is incorrect.\242\ Similarly, Middle River Power 
asserts that the Commission has previously found that generators are 
being asked to supply reactive power to support load. Clean Energy 
Associations argues that the Commission conflates the cost of equipment 
with the cost of providing an essential transmission service and that 
providing reactive power--even within the standard power factor range--
comes at the expense of providing real power.\243\ Clean Energy 
Associations note that a possible solution to this problem could be 
that the Commission distinguish ``reactive power capability'' from the 
``reactive power service.'' \244\
---------------------------------------------------------------------------

    \241\ Clean Energy Associations Initial Comments at 7.
    \242\ Middle River Power Initial Comments at 3.
    \243\ Clean Energy Associations Initial Comments at 6-7.
    \244\ Id.
---------------------------------------------------------------------------

    84. ACORE asserts that a requirement to provide a service does not 
negate the fact that costs are incurred to provide that service.\245\ 
Similarly, Elevate and Indicated Trade Associations argue that, even if 
it were true that resources do not incur distinct costs associated with 
reactive power, the Commission fails to point to precedent to support 
its conclusion that the lack of distinct costs is an appropriate basis 
on which to deny resources the ability to recover those costs.\246\ The 
Indicated Trade Associations assert that the NOPR's assumption that 
there are no or minimal costs associated with the provision of reactive 
power directly contradicts Order No. 888, which Indicated Trade 
Associations argue found that reactive service from generating 
facilities must be priced at cost, thereby acknowledging that there are 
distinguishable costs associated with the provision of reactive 
power.\247\ Middle River Power argues that the Commission has 
historically required compensation for reactive power as a separate 
ancillary service.\248\
---------------------------------------------------------------------------

    \245\ ACORE Initial Comments at 2.
    \246\ Elevate Initial Comments at 9-10; Indicated Trade 
Associations Initial Comments at 9.
    \247\ Indicated Trade Associations Initial Comments at 9 (citing 
Order No. 888, FERC Stats. & Regs. ] 31,036 at 31,720-21).
    \248\ Middle River Power Initial Comments at 2-3.
---------------------------------------------------------------------------

    85. Reactive Service Providers assert that the Commission has not 
supported its claim that generating facilities (and specifically IPP) 
already have an obligation to provide reactive service within the 
standard power factor range.\249\ Reactive Service Providers argue that 
the NOPR's finding is contrary to decades of Commission precedent,\250\ 
and the Commission ``lost its way as it proceeded to Order No. 2003 and 
beyond, caught up in a myopic view that unbundling and the emergence of 
the IPP industry somehow transferred the `obligation' to provide 
reactive service within the standard range from the Transmission 
Provider to the IPP generator.'' \251\ Reactive Service Providers 
assert that transmission providers alone have the obligation to 
maintain a reliable and stable transmission system, and generating 
facilities are purely a tool that transmission providers use to fulfill 
this obligation.\252\ Reactive Service Providers assert that in Order 
No. 888, the Commission determined that various ancillary services 
support the transmission system so that load can be served, but the 
Commission notably did not find that generating facilities have this 
obligation.\253\ Instead, Reactive Service Providers argue that the 
Commission merely recognized that generating facilities were a critical 
tool that transmission providers can use to maintain the safe and 
reliable operation of the transmission system.\254\ Reactive Service 
Providers assert that, for Reactive Supply and Voltage Control from 
Generation Sources (which

[[Page 93429]]

ultimately became Schedule 2), the Commission noted that:
---------------------------------------------------------------------------

    \249\ Reactive Service Providers Initial Comments at 7 (citing 
NOPR, 186 FERC ] 61,203 at P 5).
    \250\ Id. at 9.
    \251\ Id. at 8.
    \252\ Id. at 8-9 (citing Affidavit of Dennis W. Bethel).
    \253\ Id. at 9 (citing Order No. 888, FERC Stats. & Regs. ] 
31,036 at 31,349 (noting that the Commission adopted the following 
definition of ancillary services: ``Those services that are 
necessary to support the transmission of capacity and energy from 
resources to load while maintaining reliable operation of the 
Transmission Provider's Transmission System in accordance with Good 
Utility Practice'' and that the Commission determined that ``A 
control area is part of an interconnected power system with a common 
generation control system. It may contain one or several utilities. 
The operator of the control area is responsible for balancing 
generation and load and for maintaining reliable system 
operation.'')).
    \254\ Id.

    NERC states that reactive supply is provided from both 
generation resources and transmission facilities (e.g., capacitors), 
and lists its provision as two services, distinguished by the 
facilities that supply them. NERC further distinguishes reactive 
supply service based on the source of the need for the service: (1) 
reactive supply needed to support the voltage of the transmission 
system; and (2) reactive supply needed to correct for the reactive 
portion of the customer's load at the delivery point.\255\
---------------------------------------------------------------------------

    \255\ Id. at 10 (citing Order No. 888, FERC Stats. & Regs. ] 
31,036 at 31,355).

    Reactive Service Providers assert that NERC did not identify the 
impact of generating facilities to the transmission system as a reason 
or need for reactive supply, but instead only identified the 
transmission system and load as needing the reactive service, noting 
that generating facilities would serve those needs at the point of 
interconnection.\256\ Reactive Service Providers assert that, while 
both before and after Order No. 888, transmission providers 
holistically relied on generation- and transmission-based reactive 
assets to fulfill their obligations to maintain the voltage of the 
transmission system, generating facilities never had an independent 
obligation to provide reactive service, as the Commission asserts in 
the NOPR.\257\
---------------------------------------------------------------------------

    \256\ Id.
    \257\ Id. at 11.
---------------------------------------------------------------------------

    86. Reactive Service Providers assert that when the Commission 
issued Order No. 2003, it summarily stated that, as a condition to 
obtain interconnection service, the generating facility must provide 
reactive service within the standard power factor range.\258\ Reactive 
Service Providers argue that the Commission did not amass any evidence 
in the Order No. 2003 proceeding to explain why generating facilities 
have an obligation to provide reactive service within the standard 
power factor range and posit that the Commission may have come to this 
conclusion in Order No. 2003 and the NOPR ``because the Transmission 
Provider has always relied on generators as one of its tools to enable 
the Transmission Provider to fulfill its obligation to maintain the 
Transmission System in a safe and reliable manner.'' \259\ Reactive 
Service Providers assert that none of the transmission system 
operators, NERC, and the Commission, in nearly all precedent, have ever 
concluded that generation has an ``obligation'' to provide reactive 
service within the standard range; the Commission's statement in Order 
No. 2003 is an outlier.\260\
---------------------------------------------------------------------------

    \258\ Id. at 11-12.
    \259\ Id. at 12.
    \260\ Id. at 12-19 (citing Order No. 661, 111 FERC ] 61,353 at 
PP 50-51 (``this Final Rule requires the wind plant to maintain the 
required power factor range only if the Transmission Provider shows 
through the System impact Study, that such capability is required of 
that plant to ensure safety or reliability. . . . ``[B]ecause the 
Transmission Provider is responsible for the safe and reliable 
operation of its transmission system (pursuant to NERC and regional 
reliability council standards), it is in the best position to 
establish if reactive power is needed in individual 
circumstances.''); Order No. 827, 155 FERC ] 61,277 at P 35 
(``balancing the costs to newly-interconnecting non-synchronous 
generators of providing reactive power with the benefits to the 
transmission system of having another source of reactive power'') 
(emphasis added by Reactive Service Providers)); id. at 18 (``[I]n 
Order No. 901, the [Commission] continued the clear distinction 
between a Transmission Provider that has the obligation to plan and 
operate the Transmission System and generation that is a tool that 
Transmission Providers must account for and uses to fulfill its 
obligation to plan and operate the Transmission System.'') (citing 
Reliability Standards to Address Inverter-Based Res., Order No. 901, 
88 FR 74250 (Oct. 30, 2023) 185 FERC ] 61,042, at P 174 (2023)).
---------------------------------------------------------------------------

    87. Similarly, Reactive Service Providers assert that ``good 
utility practice'' does not entail an obligation for generating 
facilities to provide reactive power for free, and the Commission has 
not explained why it believes such obligation exists.\261\ Reactive 
Service Providers argue that the current compensation scheme for 
reactive power is consistent with the Commission's definition of good 
utility practice because it includes practices that ``could have been 
expected to accomplish the desired result at a reasonable cost 
consistent with good business practices, reliability, safety and 
expedition.'' \262\ Reactive Service Providers assert that good utility 
practice does not address what the electric industry (i.e., the 
transmission provider) can achieve for free, but rather a cost that the 
transmission provider must pay as a matter of ``good business 
practices'' in order to fulfill its obligation.\263\ Indicated Trade 
Associations argue that the Commission cannot deprive public utilities 
from just and reasonable compensation for reactive power within the 
standard power factor range by simply classifying it as a condition of 
interconnection, particularly when the Commission established that 
condition.\264\
---------------------------------------------------------------------------

    \261\ Id. at 19.
    \262\ Id. at 19-20 (quoting at Order No. 2003, 104 FERC ] 61,103 
at P 56) (emphasis added by Reactive Service Providers). Reactive 
Service Providers assert that the Commission adopted the same 
definition of ``good utility practice'' in Order No. 2003 as it did 
in Order No. 888. Id. at 19.
    \263\ Id. at 20.
    \264\ Indicated Trade Associations Initial Comments at 23 
(citing Banton v. Belt Line Ry. Corp., 268 U.S. 413, 420 (1925) 
(``[t]he commission under the guise of regulation may not compel the 
use and operation of the company's property for public convenience 
without just compensation.''); Gulf Power Co. v. U.S., 187 F.3d 
1324, 1331 (11th Cir. 1999) (``[c]haracterizing the mandatory access 
provision as a regulatory condition . . . cannot change the fact 
that it effects a taking by requiring a utility to submit to a 
permanent, physical occupation of its property'')).
---------------------------------------------------------------------------

    88. Generation Developers assert that the NOPR errs in concluding 
that separate compensation for reactive power may result in a windfall 
to generators. Generation Developers note that many generators across 
markets are in fact increasingly unable to recover their costs.\265\ 
Indicated Trade Associations similarly refute the NOPR's preliminary 
conclusion that separate compensation for reactive power within the 
standard power factor range may result in market distortions, 
contending that all rates are approved by the Commission and that any 
distortions are a result of PJM's capacity market rules.\266\
---------------------------------------------------------------------------

    \265\ Generation Developers Initial Comments at 27 (citing 
CAISO, 2022 Annual Report on Market Issues & Performance 15 (July 
11, 2023), <a href="http://www.caiso.com/market/Pages/MarketMonitoring/AnnualQuarterlyReports/Default.aspx">http://www.caiso.com/market/Pages/MarketMonitoring/AnnualQuarterlyReports/Default.aspx</a>; PJM, Energy Transition in PJM: 
Resource Retirements, Replacements and Risks 10 (Feb. 24, 2023), 
<a href="https://insidelines.pjm.com/pjm-details-resource-retirements-replacements-and-risks">https://insidelines.pjm.com/pjm-details-resource-retirements-replacements-and-risks</a>.).
    \266\ Indicated Trade Associations Reply Comments at 9.
---------------------------------------------------------------------------

2. Commission Determination
    89. Based on our review of the record, we conclude that 
compensation for the provision of reactive power within the standard 
power factor range is unjust and unreasonable because: (1) the 
provision of such reactive power requires either no or at most a de 
minimis increase in variable costs beyond the cost of providing real 
power; (2) such compensation may result in undue compensation and other 
market distortions; and (3) the provision of reactive power within the 
standard power factor range is an obligation of the generating facility 
as an interconnection customer and consistent good utility 
practice.\267\
---------------------------------------------------------------------------

    \267\ PJM IMM Initial Comments at 6-9; Joint Consumer Advocates 
Initial Comments at 6-7; MISO Transmission Owners Reply Comments at 
4; TAPS Initial Comments at 6; Ohio FEA Initial Comments at 5; Joint 
Customers Initial Comments at 14-16; PGE Initial Comments at 4 
(citing MISO, 182 FERC ] 61,033 at P 53 (noting that in the 
acceptance of the MISO Transmission Owners application to end 
compensation within the standard power application, the Commission 
reiterated its policy ``that the provision of reactive power within 
the standard power factor range is, in the first instance, an 
obligation of the interconnecting generator and good utility 
practice.'')).
---------------------------------------------------------------------------

    90. As explained in the NOPR, because real and reactive power are 
provided as joint products with joint costs produced from the same

[[Page 93430]]

equipment, any allocation of joint fixed costs between real and 
reactive power could be viewed as inherently arbitrary.\268\ And while 
the production of reactive power within the standard power factor range 
can result in certain incremental variable costs such as fuel, 
maintenance, and potentially other costs, we continue to find, based on 
the record and past precedent, that variable costs of generating 
reactive power within the standard power factor range are at most de 
minimis.\269\ With respect to fixed costs, for synchronous generating 
facilities, ``the same equipment is used to provide real and reactive 
power.'' \270\ Non-synchronous generating facilities use a different 
physical process to produce reactive power, but ``the most critical 
element in VAR production, the inverter,'' \271\ is also necessary for 
non-synchronous generating facilities to produce real power that can be 
reliably injected into AC systems.\272\ In other words, for both 
synchronous and non-synchronous generating facilities, ``[t]here are 
few if any identifiable costs incurred by generators in order to 
provide reactive power'' \273\ beyond the investments in equipment 
already necessary to generate and supply real power to the transmission 
system.\274\
---------------------------------------------------------------------------

    \268\ NOPR, 186 FERC ] 61,203 at P 30; (citing PJM IMM Initial 
Comments to the NOI at 2 (``There is no reason to include complex 
rules that arbitrarily segregate a portion of a resource's capital 
costs as related to reactive power and that require recovery of that 
arbitrary portion through guaranteed revenue requirement payments 
based on burdensome cost of service rate proceedings.''); id. at 3, 
5, 21, 24; Permian Basin, 390 U.S. at 804 (``There is ample support 
for the Commission's judgment that the apportionment of actual costs 
between two jointly produced commodities, only one of which is 
regulated by the Commission, is intrinsically unreliable.''); 
Richard A. Posner, Natural Monopoly and Its Regulation, 21 Stan. L. 
Rev. 548, 595 (1969) (``[W]here services involve joint or common 
costs a rational allocation is impossible even in theory. How much 
of the cost of a telephone handset is assignable to local and how 
much to interstate telephone service?''); see also A.A. Poultry 
Farms, Inc. v. Rose Acre Farms, Inc., 1400 (7th Cir. 1989) (``How 
does one allocate the cost of activities that have joint products? 
Agencies engaged in ratemaking struggle with these problems for 
years, even decades, without producing clear answers.'')).
    \269\ NOPR, 186 FERC ] 61,203 at P 31 (citing SPP Initial 
Comments to NOI at 2; PJM IMM Initial Comments to NOI at 4.).
    \270\ Ameren Initial Comments at 3; MISO Transmission Owner 
Reply Comments at 9. See also NOPR, 186 FERC ] 61,203 at P 29 
(citing Edison Electric Institute Initial Comments to the NOI at 6).
    \271\ Duke Energy Corporation Initial Comments to the NOI at 4.
    \272\ See, e.g., MISO Transmission Owners Initial Comments at 7 
(``[E]ven newer wind turbines use inverters that allow for the 
generator to produce and control reactive power without costly 
additional equipment.); see also MISO Rehearing Order, 184 FERC ] 
61,022 at P 30 (``As to non-synchronous resources, the principal 
piece of equipment required for non-synchronous resources to produce 
reactive power is the inverter, which is already necessary to 
convert the direct current produced by non-synchronous resources to 
alternating current--i.e., to supply real power that can be injected 
into alternating current power systems. On rehearing and in earlier 
protests, no party points to any other equipment costs incurred by 
non-synchronous generating facilities that are attributable to 
providing Reactive Service.'' (citations omitted)).
    \273\ PJM IMM Initial Comments to the NOI at 4; see also MISO 
Transmission Owners Reply Comments at 7-8.
    \274\ MISO Transmission Owners Initial Comments at 6 (``The MISO 
Transmission Owners' experience supports the Commission's 
preliminary finding that providing reactive power within the 
standard power factor range requires little or no cost to 
generators. Generators incur little or no costs beyond what is 
already needed to produce real power because the same equipment used 
to produce real power includes reactive power functions.'' 
(citations omitted)); PJM IMM Reply Comments at 3 (``Neither 
[Indicated Trade Associations] nor any other opposing commenter, nor 
any of the precedent relied upon by opposing commenters, identify 
any additional costs or more than de minimis costs incurred by 
generators in order to provide reactive capability.''); MISO 
Transmission Owners Reply Comments at 9-10 & n.29. See also, BPA, 
120 FERC ] 61,211 at P 21 (finding that the incremental cost of 
reactive power service within the deadband is minimal); METC 
Rehearing Order, 97 FERC at 61,852-53 (``[R]eactive power provided, 
not as an ancillary service, but rather as a ``no cost'' service 
within reactive design limitations, may therefore, be provided 
without compensation.''); APS, 94 FERC at 61,080 (rejecting 
generators' arguments for reactive power compensation for operating 
within standard power factor range because the generators failed to 
demonstrate that ``such a requirement will limit the real power 
output of a generating unit and therefore will not result in any 
lost opportunity costs'' or that operating a generating unit within 
the proposed standard power factor range will ``affect the 
generation output of a unit'').
---------------------------------------------------------------------------

    91. While most commenters agree or do not dispute that all 
equipment used to produce reactive power, for both synchronous and non-
synchronous generating facilities, is also necessary in order to 
produce and deliver to the transmission system real power, several 
commenters dispute the NOPR's findings that both synchronous and non-
synchronous facilities incur no or at most a de minimis increase in 
costs beyond the cost of providing real power.\275\ However, these 
commenters do not identify any specific costs beyond those incurred to 
ensure that real power can be reliably injected into the transmission 
system.\276\ For example, Indicated Trade Associations, Generation 
Developers, and Glenvale emphasize that there are costs of equipment 
and production associated with reactive power, but they provide only 
vague references to those specific equipment costs and identify no 
distinct equipment (apart from equipment already needed for real power 
production).\277\ Many of the commenters opposing the rule also 
conflate the cost of providing reactive power capability within and 
outside the standard power factor range.\278\ For example, commenters 
suggest that there are opportunity costs to provide reactive power 
capability, even within the standard power factor range, because doing 
so requires a ge

[…truncated; see source link]
Indexed from Federal Register on November 26, 2024.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.