Alabama Power Company; Notice of Revised Procedural Schedule for Environmental Impact Statement for the Proposed Project Relicense

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
September 13, 2024

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 89 Issue 178 (Friday, September 13, 2024)</title>
</head>
<body><pre>
[Federal Register Volume 89, Number 178 (Friday, September 13, 2024)]
[Notices]
[Page 74937]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2024-20833]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2628-066]


Alabama Power Company; Notice of Revised Procedural Schedule for 
Environmental Impact Statement for the Proposed Project Relicense

    On November 23, 2021, as supplemented,\1\ the Alabama Power Company 
filed an application for a new major license for the 135-megawatt R.L. 
Harris Hydroelectric Project No. 2628 (Harris Project or project). On 
March 31, 2023, Commission staff issued a notice of intent to prepare 
an Environmental Impact Statement (EIS) to evaluate the effects of 
relicensing the Harris Project. The notice included an anticipated 
schedule for issuing the draft and final EIS. On April 18, 2024, staff 
issued a notice of revised procedural schedule for preparing a draft 
and final EIS.
---------------------------------------------------------------------------

    \1\ The final license application filed November 23, 2021, was 
supplemented on March 23, 2022, June 15, 2022, and December 27, 
2022.
---------------------------------------------------------------------------

    By this notice, Commission staff is updating the procedural 
schedule for completing the draft EIS. The revised schedule is shown 
below. Further revisions to the schedule may be made as appropriate.

------------------------------------------------------------------------
                 Milestone                           Target date
------------------------------------------------------------------------
Issue draft EIS...........................  November 2024.
------------------------------------------------------------------------

    Any questions regarding this notice may be directed to Sarah 
Salazar at (202) 502-6863 or <a href="/cdn-cgi/l/email-protection#4e3d2f3c2f26603d2f222f342f3c0e282b3c2d60292138"><span class="__cf_email__" data-cfemail="7c0f1d0e1d14520f1d101d061d0e3c1a190e1f521b130a">[email&#160;protected]</span></a>.

    Dated: September 9, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-20833 Filed 9-12-24; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on September 13, 2024.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.