Accelerated Decommissioning Partners Crystal River Unit 3, LLC; Crystal River Unit 3 Nuclear Generating Plant; License Amendment Application; Withdrawal by Applicant
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Issuing agencies
Abstract
The U.S. Nuclear Regulatory Commission (NRC) has granted the request of Accelerated Decommissioning Partners Crystal River Unit 3, LLC (ADP CR3, the licensee) to withdraw its application dated December 12, 2022, for a proposed amendment to Facility Operating License No. DPR-72. The proposed amendment would have added a license condition to include the License Termination Plan for the Crystal River Unit 3 Nuclear Generating Plant.
Full Text
<html>
<head>
<title>Federal Register, Volume 89 Issue 171 (Wednesday, September 4, 2024)</title>
</head>
<body><pre>
[Federal Register Volume 89, Number 171 (Wednesday, September 4, 2024)]
[Notices]
[Page 71939]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2024-19800]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-302; NRC-2023-0174]
Accelerated Decommissioning Partners Crystal River Unit 3, LLC;
Crystal River Unit 3 Nuclear Generating Plant; License Amendment
Application; Withdrawal by Applicant
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has granted the
request of Accelerated Decommissioning Partners Crystal River Unit 3,
LLC (ADP CR3, the licensee) to withdraw its application dated December
12, 2022, for a proposed amendment to Facility Operating License No.
DPR-72. The proposed amendment would have added a license condition to
include the License Termination Plan for the Crystal River Unit 3
Nuclear Generating Plant.
DATES: September 4, 2024.
ADDRESSES: Please refer to Docket ID NRC-2023-0174 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly available information related to this document
using any of the following methods:
<bullet> Federal Rulemaking Website: Go to <a href="https://www.regulations.gov">https://www.regulations.gov</a> and search for Docket ID NRC-2023-0174. Address
questions about Docket IDs in <a href="http://Regulations.gov">Regulations.gov</a> to Stacy Schumann;
telephone: 301-415-0624; email: <a href="/cdn-cgi/l/email-protection#0c5f786d6f75225f6f6479616d62624c627e6f226b637a"><span class="__cf_email__" data-cfemail="6f3c1b0e0c16413c0c071a020e01012f011d0c41080019">[email protected]</span></a>. For technical
questions, contact the individual listed in the For Further Information
Contact section of this document.
<bullet> NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at <a href="https://www.nrc.gov/reading-rm/adams.html">https://www.nrc.gov/reading-rm/adams.html</a>. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, please contact the NRC's Public
Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737,
or by email to <a href="/cdn-cgi/l/email-protection#9fcfdbcdb1cdfaecf0eaedfcfadff1edfcb1f8f0e9"><span class="__cf_email__" data-cfemail="1d4d594f334f786e72686f7e785d736f7e337a726b">[email protected]</span></a>. The ADAMS accession number for
each document referenced (if it is available in ADAMS) is provided the
first time that it is mentioned in this document.
FOR FURTHER INFORMATION CONTACT: Chris Allen, Office of Nuclear
Material Safety and Safeguards, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001, telephone: 301-415-6877; email:
<a href="/cdn-cgi/l/email-protection#5c0b353030353d31721d303039321c322e3f723b332a"><span class="__cf_email__" data-cfemail="86d1efeaeaefe7eba8c7eaeae3e8c6e8f4e5a8e1e9f0">[email protected]</span></a>.
SUPPLEMENTARY INFORMATION:
I. Discussion
The NRC has granted the request of ADP CR3 (the licensee) to
withdraw its December 12, 2022 (ADAMS Accession No. ML22355A441),
application for proposed amendment to Facility Operating License No.
DPR-72 for the Crystal River Unit 3 Nuclear Generating Plant, located
in Citrus County, Florida. The proposed amendment would have added a
license condition to include the License Termination Plan. On November
8, 2023, the NRC published in the Federal Register a notice of
application receipt and public meeting notice (88 FR 77111).
By letter dated August 12, 2024 (ADAMS Accession No. ML24225A207),
ADP CR3 withdrew the license amendment request. By letter dated August
27, 2024 (ADAMS Accession No. ML24226B239), the NRC accepted ADP CR3's
request to withdraw the license amendment.
Dated: August 29, 2024.
For the Nuclear Regulatory Commission.
Nicole Warnek,
Acting Chief, Reactor Decommissioning Branch, Division of
Decommissioning, Uranium Recovery, and Waste Programs, Office of
Nuclear Material Safety and Safeguards.
[FR Doc. 2024-19800 Filed 9-3-24; 8:45 am]