Notice2024-16858

City of Tualatin, Oregon; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
July 31, 2024

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 89 Issue 147 (Wednesday, July 31, 2024)</title>
</head>
<body><pre>
[Federal Register Volume 89, Number 147 (Wednesday, July 31, 2024)]
[Notices]
[Pages 61415-61416]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2024-16858]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD24-3-000]


City of Tualatin, Oregon; Notice of Preliminary Determination of 
a Qualifying Conduit Hydropower Facility and Soliciting Comments and 
Motions To Intervene

    On July 23, 2024, the City of Tualatin, Oregon, filed a notice of 
intent to construct a qualifying conduit hydropower facility, pursuant 
to section 30 of the Federal Power Act (FPA). The proposed Tualatin 
Service Center Hydroelectric Energy Recovery Project would have an 
installed capacity of 56 kilowatts (kW), and would be located along the 
applicant's existing water supply system in the City of Tualatin, 
Washington County, Oregon.
    Applicant Contact: Gregg Semler, InPipe Energy, 830 NE Holladay 
St., Portland, OR 97232, 503-341-0004, <a href="/cdn-cgi/l/email-protection#5e392c3b39391e37302e372e3b3b303b2c3927703d3133"><span class="__cf_email__" data-cfemail="1a7d687f7d7d5a73746a736a7f7f747f687d6334797577">[email&#160;protected]</span></a>.
    FERC Contact: Christopher Chaney, 202-502-6778, 
<a href="/cdn-cgi/l/email-protection#14777c667d67607b647c71663a777c757a716d54727166773a737b62"><span class="__cf_email__" data-cfemail="9dfef5eff4eee9f2edf5f8efb3fef5fcf3f8e4ddfbf8effeb3faf2eb">[email&#160;protected]</span></a>.
    Qualifying Conduit Hydropower Facility Description: The project 
would consist of: (1) one 56-kW centrifugal pump as turbine generating 
unit and (2) appurtenant facilities. The proposed project would have an 
estimated annual generation of approximately 278 megawatt-hours.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all the criteria shown in the table below.

                          Table 1--Criteria for Qualifying Conduit Hydropower Facility
----------------------------------------------------------------------------------------------------------------
           Statutory provision                                  Description                      Satisfies (Y/N)
----------------------------------------------------------------------------------------------------------------
FPA 30(a)(3)(A)..........................  The conduit the facility uses is a tunnel, canal,                  Y
                                            pipeline, aqueduct, flume, ditch, or similar
                                            manmade water conveyance that is operated for the
                                            distribution of water for agricultural, municipal,
                                            or industrial consumption and not primarily for the
                                            generation of electricity.
FPA 30(a)(3)(C)(i).......................  The facility is constructed, operated, or maintained               Y
                                            for the generation of electric power and uses for
                                            such generation only the hydroelectric potential of
                                            a non-federally owned conduit.
FPA 30(a)(3)(C)(ii)......................  The facility has an installed capacity that does not               Y
                                            exceed 40 megawatts.
FPA 30(a)(3)(C)(iii).....................  On or before August 9, 2013, the facility is not                   Y
                                            licensed, or exempted from the licensing
                                            requirements of Part I of the FPA.
----------------------------------------------------------------------------------------------------------------

    Preliminary Determination: The proposed Tualatin Service Center 
Hydroelectric Energy Recovery Project will not alter the primary 
purpose of the conduit, which is for municipal water supply. Therefore, 
based upon the above criteria, Commission staff preliminarily 
determines that the operation of the project described above satisfies 
the

[[Page 61416]]

requirements for a qualifying conduit hydropower facility, which is not 
required to be licensed or exempted from licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 30 
days from the issuance date of this notice. Deadline for filing motions 
to intervene is 30 days from the issuance date of this notice. Anyone 
may submit comments or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210 and 
385.214. Any motions to intervene must be received on or before the 
specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the filing responds; (3) 
state the name, address, and telephone number of the person filing; and 
(4) otherwise comply with the requirements of sections 385.2001 through 
385.2005 of the Commission's regulations.\1\ All comments contesting 
Commission staff's preliminary determination that the facility meets 
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2023).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at <a href="http://www.ferc.gov/docs-filing/efiling.asp">http://www.ferc.gov/docs-filing/efiling.asp</a>. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at <a href="http://www.ferc.gov/docs-filing/ecomment.asp">http://www.ferc.gov/docs-filing/ecomment.asp</a>. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at <a href="/cdn-cgi/l/email-protection#55131007161a3b393c3b30062025253a272115333027367b323a23"><span class="__cf_email__" data-cfemail="fdbbb8afbeb29391949398ae888d8d928f89bd9b988f9ed39a928b">[email&#160;protected]</span></a>, (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, you may send a 
paper copy. Submissions sent via the U.S. Postal Service must be 
addressed to: Debbie-Anne A. Reese, Acting Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 
20426. Submissions sent via any other carrier must be addressed to: 
Debbie-Anne A. Reese, Acting Secretary, Federal Energy Regulatory 
Commission, 12225 Wilkins Avenue, Rockville, MD 20852. A copy of all 
other filings in reference to this application must be accompanied by 
proof of service on all persons listed in the service list prepared by 
the Commission in this proceeding, in accordance with 18 CFR 385.2010.
    Locations of Notice of Intent: The Commission provides all 
interested persons an opportunity to view and/or print the contents of 
this document via the internet through the Commission's website at 
<a href="http://www.ferc.gov/docs-filing/elibrary.asp">http://www.ferc.gov/docs-filing/elibrary.asp</a>. Enter the docket number 
(i.e., CD24-3) in the docket number field to access the document. You 
may also register online at <a href="http://www.ferc.gov/docs-filing/esubscription.asp">http://www.ferc.gov/docs-filing/esubscription.asp</a> to be notified via email of new filings and issuances 
related to this or other pending projects. Copies of the notice of 
intent can be obtained directly from the applicant. For assistance, 
call toll-free 1-866-208-3676 or email <a href="/cdn-cgi/l/email-protection#15535047565a7b797c7b70466065657a676155737067763b727a63"><span class="__cf_email__" data-cfemail="2a6c6f786965444643444f795f5a5a45585e6a4c4f5849044d455c">[email&#160;protected]</span></a>. For 
TTY, call (202) 502-8659.

    Dated: July 25, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-16858 Filed 7-30-24; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on July 31, 2024.