Ketchikan Public Utilities; Notice of Revised Procedural Schedule for Draft and Final Environmental Assessment for the Proposed Project Relicense
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
June 11, 2024
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 89 Issue 113 (Tuesday, June 11, 2024)</title>
</head>
<body><pre>
[Federal Register Volume 89, Number 113 (Tuesday, June 11, 2024)]
[Notices]
[Page 49169]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2024-12677]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 1922-052]
Ketchikan Public Utilities; Notice of Revised Procedural Schedule
for Draft and Final Environmental Assessment for the Proposed Project
Relicense
On October 27, 2022, Ketchikan Public Utilities (KPU) filed an
application for a new major license for the 7.1-megawatt Beaver Falls
Hydroelectric Project (Beaver Falls Project; FERC No. 1922). On January
5, 2024, Commission staff issued a notice of intent to prepare a draft
and final Environmental Assessment (EA) to evaluate the effects of
relicensing the Beaver Falls Project. The notice of intent included an
anticipated schedule for issuing the draft and final EA. By this
notice, Commission staff is updating the procedural schedule for
completing the draft and final EAs. The revised schedule is shown
below. Further revisions to the schedule may be made as appropriate.
---------------------------------------------------------------------------
\1\ The Council on Environmental Quality's (CEQ) regulations
under 40 CFR 1501.10(b)(1) (2022) require that EAs be completed
within 1 year of the Federal action agency's decision to prepare an
EA. See National Environmental Policy Act, 42 U.S.C. 4321 et seq.,
as amended by section 107(g)(1)(B)(iii) of the Fiscal Responsibility
Act of 2023, Public Law 118-5, sec. 4336a, 137 Stat. 42.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Commission issues draft EA................ August 2024.
Comments on draft EA...................... September 2024.
Commission issues final EA................ January 2025.\1\
------------------------------------------------------------------------
Any questions regarding this notice may be directed to Golbahar
Mirhosseini at <a href="/cdn-cgi/l/email-protection#a9eec6c5cbc8c1c8db87e4c0dbc1c6dadaccc0c7c0e9cfccdbca87cec6df"><span class="__cf_email__" data-cfemail="ebac8487898a838a99c5a68299838498988e828582ab8d8e9988c58c849d">[email protected]</span></a>.
Dated: June 4, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-12677 Filed 6-10-24; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on June 11, 2024.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.