May 22, 2024

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 89 Issue 100 (Wednesday, May 22, 2024)</title>
</head>
<body><pre>
[Federal Register Volume 89, Number 100 (Wednesday, May 22, 2024)]
[Notices]
[Page 44975]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2024-11248]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP23-129-000]


Corpus Christi Liquefaction, LLC, CCL Midscale 8-9, LLC; Notice 
of Revised Schedule for Environmental Review of the Corpus Christi 
Liquefaction Midscale Trains 8 & 9 Project

    This notice identifies the Federal Energy Regulatory Commission 
staff's revised schedule for the completion of the environmental 
assessment (EA) for Corpus Christi Liquefaction, LLC's and CCL Midscale 
8-9, LLC's (collectively referred to as, CCL) Corpus Christi 
Liquefaction Midscale Trains 8 & 9 Project. The first notice of 
schedule, issued on November 3, 2023, identified March 15, 2024 as the 
EA issuance date. However, staff identified additional information 
needs in response to CCL's full impact air dispersion analysis for 
criteria air pollutants filed on March 5, 2024, which resulted in a 
schedule delay for the issuance of the EA. CCL responded to our 
information requests on March 19, March 27, and April 24, 2024, 
providing the information needed to complete our analysis. As a result, 
staff has revised the schedule for issuance of the EA.

Schedule for Environmental Review

Issuance of the EA--June 21, 2024
90-day Federal Authorization Decision Deadline \1\--September 19, 2024
---------------------------------------------------------------------------

    \1\ The Commission's deadline applies to the decisions of other 
Federal agencies, and State agencies acting under federally 
delegated authority, that are responsible for Federal 
authorizations, permits, and other approvals necessary for proposed 
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the 
Commission's deadline for other agency's decisions applies unless a 
schedule is otherwise established by Federal law.
---------------------------------------------------------------------------

    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#db948b8b9bbdbea9b8f5bcb4ad"><span class="__cf_email__" data-cfemail="155a454555737067763b727a63">[email&#160;protected]</span></a>.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (<a href="http://www.ferc.gov">www.ferc.gov</a>). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP23-129), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at <a href="/cdn-cgi/l/email-protection#fabcbfa8b9b5949693949fa98f8a8a95888eba9c9f8899d49d958c"><span class="__cf_email__" data-cfemail="bff9faedfcf0d1d3d6d1daeccacfcfd0cdcbffd9dacddc91d8d0c9">[email&#160;protected]</span></a>. The eLibrary link on the FERC 
website also provides access to the texts of formal documents issued by 
the Commission, such as orders, notices, and rule makings.

    Dated: May 16, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-11248 Filed 5-21-24; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on May 22, 2024.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.