McCallum Enterprises I, Limited Partnership and Shelton Canal Company; Notice Rejecting Application, Waiving Regulations, and Soliciting Applications
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
April 2, 2024
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 89 Issue 64 (Tuesday, April 2, 2024)</title>
</head>
<body><pre>
[Federal Register Volume 89, Number 64 (Tuesday, April 2, 2024)]
[Notices]
[Pages 22711-22712]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2024-06871]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 6066-041]
McCallum Enterprises I, Limited Partnership and Shelton Canal
Company; Notice Rejecting Application, Waiving Regulations, and
Soliciting Applications
On March 1, 2024, McCallum Enterprises I, Limited Partnership and
Shelton Canal Company (McCallum and Shelton), co-licensees for the
Derby Dam Hydroelectric Project No. 6066 (project), filed an
application for a new license for the project pursuant to section
15(c)(1) of the Federal Power Act (FPA). The license application was
untimely filed and is hereby rejected.\1\
---------------------------------------------------------------------------
\1\ Eveready Machinery Company, Inc. was issued a major license
for the project on March 25, 1986, for a term of 40 years, effective
the first day of the month in which the order was issued. See
Eveready Machinery Company, Inc., 34 FERC ] 62,578 (1986).
Therefore, the license would expire on February 28, 2026, and the
statutory deadline for filing a new license application was February
29, 2024. See FPA Sec. 15(c)(1), 16 U.S.C. 808(c)(1). The
Commission received the application via the internet at 12:09 a.m.
Eastern Time on March 1, 2024.
---------------------------------------------------------------------------
The project is located on the Housatonic River in Fairfield and New
Haven Counties, Connecticut. The project consists of: (a) a 23.7-foot-
high, 675-foot-long dam made of concrete capped cut stone with
flashboards of varying heights, ranging from 1.8-foot-high to 2.2-foot-
high, and a crest elevation of 25.2 feet National Geodetic Vertical
Datum of 1988 (NGVD 88); (b) a 400-foot-long earth dike with a maximum
height of 10 feet, located at the east abutment and oriented in a
northwest-southwest direction; (c) a reservoir (Lake Housatonic) with a
normal maximum water surface elevation of 25.2 feet NGVD 88 and a
usable storage capacity of 500 acre-feet; (d) a gatehouse (Derby
gatehouse) and 2,135 foot-long, 40-foot-wide canal paralleling the east
bank of the river; (e) a gatehouse (Shelton gatehouse) and 130-foot-
long, 94-foot-wide headrace channel extending downstream from the dam;
(f) a navigation lock located at the west abutment, which constitutes
the first 70 feet of the Shelton canal; (g) a powerhouse (Shelton
powerhouse) at the west abutment, in the existing Shelton canal and
lock structure, and located approximately 130 feet downstream of the
Shelton gatehouse, containing two horizontal A-C tube Kaplan turbines
with two direct drive generators with a total rated capacity of 7.8
megawatts and a rated flow of 4,600 cubic feet per second; (h) a 775-
foot-long, 13.8 kilovolt underwater transmission line tying into the
existing United Illuminating Company system; and (i) appurtenant
facilities.
As a result of the rejection of McCallum and Shelton's application
and pursuant to section 16.25 of the Commission's regulations, the
Commission is soliciting license applications from potential
applicants. This solicitation is necessary because the deadline for
filing an application for a new license and any competing license
applications, pursuant to section 16.9 of the Commission's regulations,
was February 29, 2024, and no other license applications for this
project were filed. With this notice, we are waiving those parts of
section 16.24(a) and 16.25(a) which bar an existing licensee that
missed the two-year application filing deadline from filing another
application. Further, because McCallum and Shelton completed the
consultation requirements pursuant to Part 4 of the Commission's
regulations, we are waiving the consultation requirements in section
16.8 for the existing licensees. Consequently, McCallum and Shelton
will be allowed to refile a license application and compete for the
license, and the incumbent preference established by the FPA section
15(a)(2) will apply.\2\
---------------------------------------------------------------------------
\2\ See Pacific Gas and Electric Co., 98 FERC ] 61,032 (2002),
reh'g denied, 99 FERC ] 61,045 (2002), aff'd, City of Fremont v.
FERC, 336 F.3d 910 (9th Cir. 2003).
---------------------------------------------------------------------------
The licensees are required to make available certain information
described in section 16.7 of the regulations. For
[[Page 22712]]
more information from the licensees, please contact Mr. Joseph W.
Szarmach Jr., Managing Partner, McCallum Enterprises I Limited
Partnership, 2874 Main Street, Stratford, Connecticut 06614, (203) 386-
1745.
Pursuant to section 16.25(b), a potential applicant that files a
notice of intent within 90 days from the date of this notice: (1) may
apply for a license under Part I of the FPA and Part 4 (except section
4.38) of the Commission's regulations within 18 months of the date on
which it files its notice; and (2) must comply with sections 16.8 and
16.10 of the Commission's regulations.
Questions concerning this notice should be directed to Brandi
Welch-Acosta, (202) 502-8964 or <a href="/cdn-cgi/l/email-protection#3775455659535e1960525b545f1a765458444356775152455419505841"><span class="__cf_email__" data-cfemail="cc8ebeada2a8a5e29ba9a0afa4e18dafa3bfb8ad8caaa9beafe2aba3ba">[email protected]</span></a>.
Dated: March 26, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-06871 Filed 4-1-24; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on April 2, 2024.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.