Notice2024-06770
Erie Boulevard Hydropower, L.P.; Notice of Revised Procedural Schedule for Final Environmental Assessment for the Proposed Project Relicense
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
April 1, 2024
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 89 Issue 63 (Monday, April 1, 2024)</title>
</head>
<body><pre>
[Federal Register Volume 89, Number 63 (Monday, April 1, 2024)]
[Notices]
[Page 22399]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2024-06770]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2701-061]
Erie Boulevard Hydropower, L.P.; Notice of Revised Procedural
Schedule for Final Environmental Assessment for the Proposed Project
Relicense
On February 26, 2021, Erie Boulevard Hydropower, L.P. (Erie) filed
an application for a new major license to continue to operate and
maintain the 39.75-megawatt (MW) West Canada Creek Hydroelectric
Project No. 2701 (West Canada Creek Project). On June 27, 2022,
Commission staff issued a notice of intent to prepare a draft and final
Environmental Assessment (EA) to evaluate the effects of relicensing
the West Canada Creek Project. The notice of intent included a schedule
for preparing a draft and final EA. On September 6, 2023, Commission
staff issued the draft EA. By notice issued September 21, 2023, the
schedule for completing a final EA was revised. The revised due date
for the final EA was to be March 2024.
On February 2, 2024 Erie filed a Comprehensive Relicensing
Settlement Agreement (Settlement Agreement) on behalf of itself, the
U.S. Fish and Wildlife Service, the New York State Department of
Environmental Conservation, and the New York State Council of Trout
Unlimited. In order for Commission staff to fully consider the
Settlement Agreement, stakeholder comments on the Settlement Agreement,
and any additional information requested by staff, the procedural
schedule for completing a final EA is being revised as follows. Further
revisions to the schedule may be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Issue Final EA............................ September 2024.
------------------------------------------------------------------------
Any questions regarding this notice may be directed to Laurie Bauer
at (202) 502-6519, or by email at <a href="/cdn-cgi/l/email-protection#24484551564d410a464551415664424156470a434b52"><span class="__cf_email__" data-cfemail="1874796d6a717d367a796d7d6a587e7d6a7b367f776e">[email protected]</span></a>.
Dated: March 25, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-06770 Filed 3-29-24; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on April 1, 2024.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.