Notice2024-02718
City of Aspen, Colorado; Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
February 9, 2024
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 89 Issue 28 (Friday, February 9, 2024)</title>
</head>
<body><pre>
[Federal Register Volume 89, Number 28 (Friday, February 9, 2024)]
[Notices]
[Page 9142]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2024-02718]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 10441-019]
City of Aspen, Colorado; Notice of Intent To File License
Application, Filing of Pre-Application Document, and Approving Use of
the Traditional Licensing Process
(February 5, 2024.)
a. Type of Filing: Notice of Intent to File License Application and
Request to Use the Traditional Licensing Process.
b. Project No.: 10441-019.
c. Date Filed: June 30, 2023.
d. Submitted By: City of Aspen, Colorado.
e. Name of Project: Maroon Creek Hydroelectric Project.
f. Location: On Maroon Creek in Pitkin County, Colorado.
g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
h. Potential Applicant Contact: Phil Overenyder at City of Aspen at
(970) 920-5111; or email at <a href="/cdn-cgi/l/email-protection#c7b7afaeabe9a8b1a2b5a2bea9a3a2b587a6b4b7a2a9e9a0a8b1"><span class="__cf_email__" data-cfemail="8bfbe3e2e7a5e4fdeef9eef2e5efeef9cbeaf8fbeee5a5ece4fd">[email protected]</span></a>..
i. FERC Contact: Everard Baker at (202) 502-8554; or email at
<a href="/cdn-cgi/l/email-protection#3e5b485b4c5f4c5a105c5f555b4c7e585b4c5d10595148"><span class="__cf_email__" data-cfemail="22475447504350460c404349475062444750410c454d54">[email protected]</span></a>.
j. The City of Aspen filed its request to use the Traditional
Licensing Process on June 30, 2023. The City of Aspen provided public
notice of its request on July 31, 2023. In a letter dated September 28,
2023, the Director of the Division of Hydropower Licensing approved the
City of Aspen's request to use the Traditional Licensing Process.
k. With this notice, we are initiating informal consultation with
the U.S. Fish and Wildlife Service under section 7 of the Endangered
Species Act and the joint agency regulations thereunder at 50 CFR part
402. We are also initiating consultation with the Colorado State
Historic Preservation Officer, as required by section 106, National
Historical Preservation Act, and the implementing regulations of the
Advisory Council on Historic Preservation at 36 CFR 800.2.
l. With this notice, we are designating the City of Aspen as the
Commission's non-Federal representative for carrying out informal
consultation, pursuant to section 7 of the Endangered Species Act and
section 106 of the National Historic Preservation Act.
m. The City of Aspen filed a Pre-Application Document (PAD;
including a proposed process plan and schedule) with the Commission,
pursuant to 18 CFR 5.6 of the Commission's regulations.
n. A copy of the PAD may be viewed and/or printed on the
Commission's website (<a href="http://www.ferc.gov">http://www.ferc.gov</a>), using the ``eLibrary''
link. Enter the docket number, excluding the last three digits in the
docket number field to access the document. At this time, the
Commission has suspended access to the Commission's Public Reference
Room. For assistance, contact FERC at <a href="/cdn-cgi/l/email-protection#87c1c2d5c4c8e9ebeee9e2d4f2f7f7e8f5f3c7e1e2f5e4a9e0e8f1"><span class="__cf_email__" data-cfemail="195f5c4b5a56777570777c4a6c6969766b6d597f7c6b7a377e766f">[email protected]</span></a> or
call toll free, (886) 208-3676 or TTY (202) 502-8659.
o. The licensee states its unequivocal intent to submit an
application for a subsequent license for Project No. 10441. Pursuant to
18 CFR 16.20 each application for a subsequent license and any
competing license applications must be filed with the Commission at
least 24 months prior to the expiration of the existing license. All
applications for license for this project must be filed by June 30,
2026.
p. Register online at <a href="http://www.ferc.gov/docs-filing/esubscription.asp">http://www.ferc.gov/docs-filing/esubscription.asp</a> to be notified via email of new filing and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
q. The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202)502-6595 or <a href="/cdn-cgi/l/email-protection#cf809f9f8fa9aabdace1a8a0b9"><span class="__cf_email__" data-cfemail="753a252535131007165b121a03">[email protected]</span></a>.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-02718 Filed 2-8-24; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on February 9, 2024.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.