Notice2024-00767
Black Canyon Hydro, LLC; Notice of Revised Schedule for the Seminoe Pumped Storage Project
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
January 17, 2024
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 89 Issue 11 (Wednesday, January 17, 2024)</title>
</head>
<body><pre>
[Federal Register Volume 89, Number 11 (Wednesday, January 17, 2024)]
[Notices]
[Page 2937]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2024-00767]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 14787-004]
Black Canyon Hydro, LLC; Notice of Revised Schedule for the
Seminoe Pumped Storage Project
This notice revises the Federal Energy Regulatory Commission's
(Commission) schedule for processing Black Canyon Hydro, LLC's license
application for the Seminoe Pumped Storage Project. A prior notice
issued on July 10, 2023, identified an anticipated schedule for
issuance of draft and final National Environmental Policy Act (NEPA)
documents and a final order for the project. After the issuance of that
notice, Black Canyon Hydro, LLC requested an extension of time to
complete additional studies with a final study report to be filed by
September 30, 2024. Commission staff issued a letter approving the
extension of time on October 31, 2023. To account for the additional
time needed for Black Canyon Hydro, LLC to complete the studies and
file the study reports, the application will be processed according to
the following revised schedule.
Notice of Ready for Environmental Analysis: December 2024
Draft NEPA Document: August 2025
Final NEPA Document: March 13, 2026
In addition, in accordance with title 41 of the Fixing America's
Surface Transportation Act, enacted on December 4, 2015, agencies are
to publish completion dates for all federal environmental reviews and
authorizations. This notice identifies the Commission's anticipated
schedule for issuance of the final order for the project, which is
based on the revised issuance date for the final NEPA document.
Accordingly, we currently anticipate issuing a final order for the
project no later than:
Issuance of Final Order: June 18, 2026
If a schedule change becomes necessary, an additional notice will
be provided so that interested parties and government agencies are kept
informed of the project's progress.
Dated: January 10, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-00767 Filed 1-16-24; 8:45 am]
BILLING CODE 6717-01-P
</pre></body>
</html>Indexed from Federal Register on January 17, 2024.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.