LinkPast Solutions, Inc.; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
December 20, 2023

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 88 Issue 243 (Wednesday, December 20, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 243 (Wednesday, December 20, 2023)]
[Notices]
[Pages 88073-88074]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-27979]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 15302-001]


LinkPast Solutions, Inc.; Notice of Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

    On June 26, 2023, LinkPast Solutions, Inc., filed an application 
for a preliminary permit, pursuant to section 4(f) of the Federal Power 
Act (FPA), proposing to study the feasibility of hydropower on the 
Black River in Jefferson County, New York. The sole purpose of a 
preliminary permit, if issued, is to grant the permit holder priority 
to file a license application during the permit term. A preliminary 
permit does not authorize the permit holder to perform any land-
disturbing activities or otherwise enter upon lands or waters owned by 
others without the owners' express permission.
    The proposed Sewalls Island Hydro Project would be located on the 
North Channel of the Black River at Sewalls Island in Watertown, New 
York. The proposed project would operate with flows below the minimum 
and above the maximum hydraulic capacities of Erie Boulevard 
Hydropower, L.P.'s Sewalls Development of the Black River Hydroelectric 
Project No. P-2569 (Sewalls Development). The Sewalls

[[Page 88074]]

Development consists of two dams--a 90-foot-long, 18.5-foot-high 
concrete gravity dam on the North Channel of Sewalls Island (North 
Channel dam) and a 243-foot-long, 15.5-foot-high concrete gravity dam 
on the South Channel of Sewalls Island. A 4-acre reservoir with a 
storage capacity of 48-acre-feet at an elevation of 466.45 feet 
National Geodetic Vertical Datum of 1929 was created by the dams.
    The proposed project would consist of the following: (1) two new 
powerhouses--a 70-foot-long by 30-foot-wide reinforced concrete 
powerhouse at the North Channel dam (powerhouse #1) and a 60-foot-long, 
40-foot-wide reinforced concrete powerhouse downstream on the North 
Channel at the lower end of Sewalls Island (powerhouse #2); (2) a new 
70-foot-long, 25-foot-wide integral intake structure at the North 
Channel dam for use by both powerhouses; (3) a new 12.5-foot-diameter, 
1,250-foot-long steel and concrete penstock for conveying water to 
powerhouse #2 that would involve the demolition of the existing 80-
foot-long, 16-foot-high Black Clawson Dam on the western tip of the 
island in the North Channel; (4) an axial flow vertical turbine-
generator unit with an installed capacity of 3,600 kilowatts (kW) and a 
micro turbine-generator unit with an installed capacity of 15.7 kW 
housed in powerhouse #1; (5) one or more axial flow vertical turbine-
generator unit(s) with a total installed capacity of 5,500 kW housed in 
powerhouse #2; (6) a new approximately 120-foot-long access road for 
powerhouse #1 and a new approximately 320-foot-long access road for 
powerhouse #2; (7) a new 1,900-foot-long, 23-kilovolt (kV) transmission 
line connecting the powerhouses to the existing switchyard of the Black 
River Project's Sewalls Development (option 1) or a new 4,270-foot-
long, 23-kV transmission line connecting the powerhouses to a 
switchyard adjacent to the New York Airbrake Manufacturing plant; and 
(8) appurtenant facilities. The proposed project would have an average 
annual generation of approximately 2,245 megawatt-hours.
    Applicant Contact: Brian McArthur, LinkPast Solutions, Inc., P.O. 
Box 5474, Clark, NJ 07066; phone: (848) 628-4414.
    FERC Contact: Monir Chowdhury; phone: (202) 502-6736.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at <a href="https://ferconline.ferc.gov/FERCOnline.aspx">https://ferconline.ferc.gov/FERCOnline.aspx</a>. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at <a href="https://ferconline.ferc.gov/QuickComment.aspx">https://ferconline.ferc.gov/QuickComment.aspx</a>. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
<a href="/cdn-cgi/l/email-protection#fdbbb8afbeb29391949398ae888d8d928f89bd9b988f9ed39a928b"><span class="__cf_email__" data-cfemail="fabcbfa8b9b5949693949fa98f8a8a95888eba9c9f8899d49d958c">[email&#160;protected]</span></a>, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy. 
Submissions sent via the U.S. Postal Service must be addressed to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via 
any other carrier must be addressed to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, 
Maryland 20852.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of the 
Commission's website at <a href="https://elibrary.ferc.gov/eLibrary/search">https://elibrary.ferc.gov/eLibrary/search</a>. 
Enter the docket number (P-15302) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: December 14, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-27979 Filed 12-19-23; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>