Full Text

<html>
<head>
<title>Federal Register, Volume 88 Issue 238 (Wednesday, December 13, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 238 (Wednesday, December 13, 2023)]
[Notices]
[Page 86326]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-27337]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 15334-000]


SV Hydro LLC; Notice of Preliminary Permit Application Accepted 
for Filing and Soliciting Comments, Motions To Intervene, and Competing 
Applications

    On November 16, 2023, SV Hydro LLC., filed an application for a 
preliminary permit, pursuant to section 4(f) of the Federal Power Act 
(FPA), proposing to study the feasibility of a hydropower project to be 
located at the U.S. Army Corps of Engineers' (Corps) Coffeeville Lock 
and Dam near the Town of Coffeeville, Choctaw, and Clarke Counties, 
Alabama. The sole purpose of a preliminary permit, if issued, is to 
grant the permit holder priority to file a license application during 
the permit term. A preliminary permit does not authorize the permit 
holder to perform any land-disturbing activities or otherwise enter 
upon lands or waters owned by others without the owners' express 
permission.
    The proposed Coffeeville Hydroelectric Project would consist of the 
following: (1) a 200-foot-long, 100-foot-wide intake channel; (2) a 90-
foot-long, 120-foot-wide, 50-foot-high concrete powerhouse located on 
the northwest bank of the river at the left abutment (looking 
downstream) of the existing Corps' dam containing four Kaplan bulb 
turbine-generator units with a total capacity of 36.0 megawatts; (3) a 
250-foot-long, 100-foot-wide tailrace; (4) a switchyard, adjacent to 
the powerhouse; and (5) a 2.7-mile-long, 69 kilovolt transmission line. 
The proposed project would have an estimated annual generation of 180 
megawatt-hours.
    Applicant Contact: Douglas Spaulding, Nelson Energy, 1030 Tyrol 
Trail, Suite 101, Minneapolis, MN 55416; phone: (612) 599-8493.
    FERC Contact: Michael Spencer; phone: (202) 502-6093, or by email 
at <a href="/cdn-cgi/l/email-protection#5e33373d363f3b32702d2e3b303d3b2c1e383b2c3d70393128"><span class="__cf_email__" data-cfemail="a6cbcfc5cec7c3ca88d5d6c3c8c5c3d4e6c0c3d4c588c1c9d0">[email&#160;protected]</span></a>.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#d49b848494b2b1a6b7fab3bba2"><span class="__cf_email__" data-cfemail="2f607f7f6f494a5d4c01484059">[email&#160;protected]</span></a>.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at <a href="https://ferconline.ferc.gov/eFiling.aspx">https://ferconline.ferc.gov/eFiling.aspx</a>. Commenters can submit brief comments 
up to 6,000 characters, without prior registration, using the eComment 
system at <a href="https://ferconline.ferc.gov/QuickComment.aspx">https://ferconline.ferc.gov/QuickComment.aspx</a>. You must 
include your name and contact information at the end of your comments. 
For assistance, please contact FERC Online Support at 
<a href="/cdn-cgi/l/email-protection#9fd9dacddcd0f1f3f6f1facceaefeff0edebdff9faedfcb1f8f0e9"><span class="__cf_email__" data-cfemail="571112051418393b3e393204222727382523173132253479303821">[email&#160;protected]</span></a>, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy. 
Submissions sent via the U.S. Postal Service must be addressed to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via 
any other carrier must be addressed to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, 
Maryland 20852. The first page of any filing should include docket 
number P-15334-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of the 
Commission's website at <a href="https://elibrary.ferc.gov/eLibrary/search">https://elibrary.ferc.gov/eLibrary/search</a>. 
Enter the docket number (P-15334) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: December 7, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-27337 Filed 12-12-23; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on December 13, 2023.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.