Notice2023-25972

Tallassee Shoals, LLC; Notice of Authorization for Continued Project Operation

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
November 24, 2023

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 88 Issue 225 (Friday, November 24, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 225 (Friday, November 24, 2023)]
[Notices]
[Page 82350]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-25972]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 6951-000]


Tallassee Shoals, LLC; Notice of Authorization for Continued 
Project Operation

    The license for the Tallassee Shoals Hydroelectric Project No. 6951 
was issued for a period ending September 30, 2023.
    Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the 
Commission, at the expiration of a license term, to issue from year-to-
year an annual license to the then licensee(s) under the terms and 
conditions of the prior license until a new license is issued, or the 
project is otherwise disposed of as provided in section 15 or any other 
applicable section of the FPA. If the project's prior license waived 
the applicability of section 15 of the FPA, then, based on section 9(b) 
of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth 
at 18 CFR 16.21(a), if the licensee of such project has filed an 
application for a subsequent license, the licensee may continue to 
operate the project in accordance with the terms and conditions of the 
license after the minor or minor part license expires, until the 
Commission acts on its application. If the licensee of such a project 
has not filed an application for a subsequent license, then it may be 
required, pursuant to 18 CFR 16.21(b), to continue project operations 
until the Commission issues someone else a license for the project or 
otherwise orders disposition of the project.
    If the project is subject to section 15 of the FPA, notice is 
hereby given that an annual license for Project No. 6951 is issued to 
Tallassee Shoals, LLC for a period effective October 1, 2023, through 
September 30, 2024, or until the issuance of a new license for the 
project or other disposition under the FPA, whichever comes first. If 
issuance of a new license (or other disposition) does not take place on 
or before September 30, 2024, notice is hereby given that, pursuant to 
18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is 
renewed automatically without further order or notice by the 
Commission, unless the Commission orders otherwise.
    If the project is not subject to section 15 of the FPA, notice is 
hereby given that Tallassee Shoals, LLC is authorized to continue 
operation of the Tallassee Shoals Hydroelectric Project under the terms 
and conditions of the prior license until the issuance of a subsequent 
license for the project or other disposition under the FPA, whichever 
comes first.

    Dated: November 17, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-25972 Filed 11-22-23; 8:45 am]
BILLING CODE 6717-01-P


</pre></body>
</html>
Indexed from Federal Register on November 24, 2023.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.