Notice2023-24037

FFP Project 101, LLC; Notice of Modification of Procedural Schedule

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
November 1, 2023

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 88 Issue 210 (Wednesday, November 1, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 210 (Wednesday, November 1, 2023)]
[Notices]
[Page 74990]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-24037]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14861-002]


FFP Project 101, LLC; Notice of Modification of Procedural 
Schedule

    Take notice that the schedule for processing the following 
hydroelectric application has been modified.
    a. Type of Application: Original Major License.
    b. Project No.: 14861-002.
    c. Date Filed: June 23, 2020.
    d. Applicant: FFP Project 101, LLC.
    e. Name of Project: Goldendale Energy Storage Project.
    f. Location: Off-stream on the north side of the Columbia River at 
River Mile 215.6 in Klickitat County, Washington, with transmission 
facilities extending into Sherman County, Oregon. The project would be 
located approximately 8 miles southeast of the City of Goldendale, 
Washington. The project would occupy 18.1 acres of lands owned by the 
U.S. Army Corps of Engineers and administered by the Bonneville Power 
Administration.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Erik Steimle, Rye Development, 745 Atlantic 
Avenue, Boston, Massachusetts 02111; (503) 998-0230; email_
<a href="/cdn-cgi/l/email-protection" class="__cf_email__" data-cfemail="2d485f44466d5f544849485b4841425d40484359034e4240">[email&#160;protected]</a>.
    i. FERC Contact: Michael Tust at (202) 502-6522; or email at 
<a href="/cdn-cgi/l/email-protection#91fcf8f2f9f0f4fdbfe5e4e2e5d1f7f4e3f2bff6fee7"><span class="__cf_email__" data-cfemail="e38e8a808b82868fcd97969097a385869180cd848c95">[email&#160;protected]</span></a>.
    j. Procedural Schedule: The Commission's February 2, 2023, Notice 
of Modification of Procedural Schedule established October 2023 as the 
target date for issuing the Final Environmental Impact Statement (Final 
EIS). The revised estimate for issuing the Final EIS is December 2023.
    Any questions regarding this notice may be directed to Michael 
Tust.

    Dated: October 25, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-24037 Filed 10-31-23; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on November 1, 2023.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.