Notice2023-19219

EONY Generation Limited; Notice of Denial of Water Quality Certification

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
September 7, 2023

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 88 Issue 172 (Thursday, September 7, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 172 (Thursday, September 7, 2023)]
[Notices]
[Page 61588]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-19219]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 4334-017]


EONY Generation Limited; Notice of Denial of Water Quality 
Certification

    On January 28, 2021, EONY Generation Limited (EONY) filed an 
application for a new license for the Philadelphia Hydroelectric 
Project (project) in the above captioned docket. EONY filed with the 
New York State Department of Environmental Conservation (New York DEC) 
a request for water quality certification for the project under section 
401(a)(1) of the Clean Water Act on August 26, 2022. On August 22, 
2023, the New York DEC denied certification for the project. Pursuant 
to 40 CFR 121.8, we are providing notice that New York DEC's denial 
satisfies the requirements of 40 CFR 121.7(e).

    Dated: August 30, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-19219 Filed 9-6-23; 8:45 am]
BILLING CODE 6717-01-P


</pre></body>
</html>
Indexed from Federal Register on September 7, 2023.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.