Notice2023-19219
EONY Generation Limited; Notice of Denial of Water Quality Certification
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
September 7, 2023
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 88 Issue 172 (Thursday, September 7, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 172 (Thursday, September 7, 2023)]
[Notices]
[Page 61588]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-19219]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 4334-017]
EONY Generation Limited; Notice of Denial of Water Quality
Certification
On January 28, 2021, EONY Generation Limited (EONY) filed an
application for a new license for the Philadelphia Hydroelectric
Project (project) in the above captioned docket. EONY filed with the
New York State Department of Environmental Conservation (New York DEC)
a request for water quality certification for the project under section
401(a)(1) of the Clean Water Act on August 26, 2022. On August 22,
2023, the New York DEC denied certification for the project. Pursuant
to 40 CFR 121.8, we are providing notice that New York DEC's denial
satisfies the requirements of 40 CFR 121.7(e).
Dated: August 30, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-19219 Filed 9-6-23; 8:45 am]
BILLING CODE 6717-01-P