Rule2023-16628

Improvements to Generator Interconnection Procedures and Agreements

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
September 6, 2023
Effective
November 6, 2023

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Abstract

The Federal Energy Regulatory Commission (Commission or FERC) is adopting reforms to its pro forma Large Generator Interconnection Procedures, pro forma Small Generator Interconnection Procedures, pro forma Large Generator Interconnection Agreement, and pro forma Small Generator Interconnection Agreement to address interconnection queue backlogs, improve certainty, and prevent undue discrimination for new technologies. The reforms are intended to ensure that the generator interconnection process is just, reasonable, and not unduly discriminatory or preferential.

Full Text

<html>
<head>
<title>Federal Register, Volume 88 Issue 171 (Wednesday, September 6, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 171 (Wednesday, September 6, 2023)]
[Rules and Regulations]
[Pages 61014-61349]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-16628]



[[Page 61013]]

Vol. 88

Wednesday,

No. 171

September 6, 2023

Part II





Department of Energy





-----------------------------------------------------------------------





Federal Energy Regulatory Commission





-----------------------------------------------------------------------





18 CFR Part 35





Improvements to Generator Interconnection Procedures and Agreements; 
Final Rule

Federal Register / Vol. 88, No. 171 / Wednesday, September 6, 2023 / 
Rules and Regulations

[[Page 61014]]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

18 CFR Part 35

[Docket No. RM22-14-000; Order No. 2023]


Improvements to Generator Interconnection Procedures and 
Agreements

AGENCY: Federal Energy Regulatory Commission, Department of Energy.

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: The Federal Energy Regulatory Commission (Commission or FERC) 
is adopting reforms to its pro forma Large Generator Interconnection 
Procedures, pro forma Small Generator Interconnection Procedures, pro 
forma Large Generator Interconnection Agreement, and pro forma Small 
Generator Interconnection Agreement to address interconnection queue 
backlogs, improve certainty, and prevent undue discrimination for new 
technologies. The reforms are intended to ensure that the generator 
interconnection process is just, reasonable, and not unduly 
discriminatory or preferential.

DATES: This final rule is effective November 6, 2023.

FOR FURTHER INFORMATION CONTACT: Tristan Kessler (Technical 
Information), Office of Energy Policy and Innovation, 888 First Street 
NE, Washington, DC 20426, (202) 502-6608, <a href="/cdn-cgi/l/email-protection#c1b5b3a8b2b5a0afefaaa4b2b2ada4b381a7a4b3a2efa6aeb7"><span class="__cf_email__" data-cfemail="eb9f9982989f8a85c5808e9898878e99ab8d8e9988c58c849d">[email&#160;protected]</span></a>.
    Franklin Jackson (Technical Information), Office of Energy Market 
Regulation, 888 First Street NE, Washington, DC 20426, (202) 502-6464, 
<a href="/cdn-cgi/l/email-protection#e48296858a8f888d8aca8e85878f978b8aa482819687ca838b92"><span class="__cf_email__" data-cfemail="99ffebf8f7f2f5f0f7b7f3f8faf2eaf6f7d9fffcebfab7fef6ef">[email&#160;protected]</span></a>.
    Sarah Greenberg (Legal Information), Office of the General Counsel, 
888 First Street NE, Washington, DC 20426, (202) 502-6230, 
<a href="/cdn-cgi/l/email-protection#16657764777e38716473737874736471567073647538717960"><span class="__cf_email__" data-cfemail="ef9c8e9d8e87c1889d8a8a818d8a9d88af898a9d8cc1888099">[email&#160;protected]</span></a>.

SUPPLEMENTARY INFORMATION: 

Table of Contents

Paragraph Numbers

I. Introduction 1
    A. Historical Framework: Order Nos. 2003, 2006, and 845 11.
    B. Regional Transmission Planning and Cost Allocation and 
Generator Interconnection Advance Notice of Proposed Rulemaking 18
    C. Notice of Proposed Rulemaking 20
    D. Joint Federal-State Task Force on Electric Transmission 25
II. Overall Need for Reform 27
    A. NOPR 27
    B. Comments 30
    C. Commission Determination 37
III. Reforms 61
    A. Reforms To Implement a First-Ready, First-Served Cluster 
Study Process 61
    1. Interconnection Information Access 61
    2. Cluster Study Process 165
    3. Allocation of Cluster Study Costs 405
    4. Allocation of Cluster Network Upgrade Costs 422
    5. Shared Network Upgrades 468
    6. Increased Financial Commitments and Readiness Requirements 
490
    7. Transition Process 814
    B. Reforms To Increase the Speed of Interconnection Queue 
Processing 872
    1. Elimination of the Reasonable Efforts Standard 872
    2. Affected Systems 1026
    3. Optional Resource Solicitation Study 1294
    C. Reforms To Incorporate Technological Advancements Into the 
Interconnection Process 1324
    1. Increasing Flexibility in the Generator Interconnection 
Process 1324
    2. Incorporating the Enumerated Alternative Transmission 
Technologies Into the Generator Interconnection Process 1534
    3. Modeling and Ride-Through Requirements for Non-Synchronous 
Generating Facilities 1621
    D. Issues Beyond the Scope of this Rulemaking 1736
    1. Comments 1736
    2. Commission Determination 1743
IV. Compliance Procedures 1744
    A. NOPR Proposal 1744
    B. Comments 1747
    1. Compliance Filing Deadline 1747
    2. Regional Flexibility 1750
    3. Reciprocity Tariffs 1759
    4. Effective Date 1760
    5. Miscellaneous 1761
    C. Commission Determination 1762
V. Information Collection Statement 1772
VI. Environmental Analysis 1779
VII. Regulatory Flexibility Act 1780
VIII. Document Availability 1783
IX. Effective Date and Congressional Notification 1785

I. Introduction

    1. This final rule requires all public utility transmission 
providers to adopt revised pro forma Large Generator Interconnection 
Procedures (LGIP), pro forma Small Generator Interconnection Procedures 
(SGIP), pro forma Large Generator Interconnection Agreements (LGIA), 
and pro forma Small Generator Interconnection Agreements (SGIA).\1\ 
These revisions will ensure that interconnection customers are able to 
interconnect to the transmission system in a reliable, efficient, 
transparent, and timely manner, and will prevent undue discrimination.
---------------------------------------------------------------------------

    \1\ Section 201(e) of the Federal Power Act (FPA) defines 
``public utility'' to mean ``any person who owns or operates 
facilities subject to the jurisdiction of the Commission under this 
subchapter.'' 16 U.S.C. 824(e). A non-public utility that seeks 
voluntary compliance with the reciprocity condition of a tariff may 
satisfy that condition by filing a tariff, which includes the pro 
forma LGIP, the pro forma SGIP, the pro forma LGIA, and the pro 
forma SGIA. See Standardization of Generator Interconnection 
Agreements & Procs., Order No. 2003, 68 FR 49846 (Aug. 19, 2003), 
104 FERC ] 61,103, at PP 1, 616 (2003), order on reh'g, Order No. 
2003-A, 69 FR 15932 (Mar. 5, 2004), 106 FERC ] 61,220, order on 
reh'g, Order No. 2003-B, 70 FR 265 (Jan. 19, 2005), 109 FERC ] 
61,287 (2004), order on reh'g, Order No. 2003-C, 70 FR 37661 (July 
18, 2005), 111 FERC ] 61,401 (2005), aff'd sub nom. Nat'l Ass'n of 
Regul. Util. Comm'rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007) (NARUC 
v. FERC). As stated in the pro forma LGIP, pro forma LGIA, pro forma 
SGIP, and pro forma SGIA, transmission provider ``shall mean the 
public utility (or its designated agent) that owns, controls, or 
operates transmission or distribution facilities used for the 
transmission of electric energy in interstate commerce and provides 
transmission service under the [Transmission Provider's Tariff]. The 
term . . . should be read to include the Transmission Owner when the 
Transmission Owner is separate from the Transmission Provider.'' Pro 
forma LGIP section 1; pro forma LGIA art. 1; pro forma SGIP attach. 
1; pro forma SGIA attach. 1.
---------------------------------------------------------------------------

    2. Twenty years ago the Commission issued Order No. 2003, in which 
the Commission required all public utilities that own, control, or 
operate facilities used for transmitting electric energy in interstate 
commerce to have on file standard procedures and a standard agreement 
for interconnecting generating facilities larger than 20 megawatts (MW) 
(called the pro forma LGIP and the pro forma LGIA).\2\ The Commission 
stated its expectation that the changes would prevent undue 
discrimination, preserve reliability, increase energy supply, and lower 
wholesale prices for customers by increasing the amount and variety of 
new generation that would compete in the wholesale electricity 
market.\3\ The Commission further stated that the standard procedures 
would facilitate market entry for generation competitors by reducing 
interconnection costs and time.\4\ In Order No. 2006, the Commission 
adopted standard procedures and a standard agreement for 
interconnecting generating facilities no larger than 20 MW (called the 
pro forma SGIP and the pro forma SGIA), citing the same purposes 
outlined in Order No. 2003.\5\
---------------------------------------------------------------------------

    \2\ Order No. 2003, 104 FERC ] 61,103 at P 2.
    \3\ Id. P 1.
    \4\ Id. P 12.
    \5\ Standardization of Small Generator Interconnection 
Agreements & Procs., Order No. 2006, 111 FERC ] 61,220, at PP 15, 
35-36, order on reh'g, Order No. 2006-A, 70 FR 71760 (Dec. 30, 
2005), 113 FERC ] 61,195 (2005), order granting clarification, Order 
No. 2006-B, 71 FR 42587 (July 27, 2006), 116 FERC ] 61,046 (2006).
---------------------------------------------------------------------------

    3. The electricity sector has transformed significantly since the 
issuance of Order Nos. 2003 and 2006. The growth of new resources 
seeking to interconnect to the transmission system and the differing 
characteristics of those resources have created new challenges for the 
generator interconnection process. These new challenges are creating 
large interconnection queue

[[Page 61015]]

backlogs and uncertainty regarding the cost and timing of 
interconnecting to the transmission system, increasing costs for 
consumers. Backlogs in the generator interconnection process, in turn, 
can create reliability issues as needed new generating facilities are 
unable to come online in an efficient and timely manner. While the 
Commission recognized these issues and sought to address them in Order 
No. 845,\6\ it is clear that further action is needed. Therefore, we 
believe that it is necessary to reform the Commission's standard 
interconnection procedures and agreements to ensure that 
interconnection customers are able to interconnect to the transmission 
system in a reliable, efficient, transparent, and timely manner, 
thereby ensuring that rates, terms, and conditions for Commission-
jurisdictional services are just, reasonable, and not unduly 
discriminatory or preferential.
---------------------------------------------------------------------------

    \6\ See Reform of Generator Interconnection Procs. & Agreements, 
Order No. 845, 83 FR 21342 (May 9, 2018), 163 FERC ] 61,043, at P 24 
(2018), order on reh'g, Order No. 845-A, 84 FR 8156 (Mar. 6, 2019) 
166 FERC ] 61,137, order on reh'g, Order No. 845-B, 168 FERC ] 
61,092 (2019).
---------------------------------------------------------------------------

    4. Accordingly, we adopt reforms to the Commission's pro forma LGIP 
and pro forma LGIA. Specifically, as explained in detail in this final 
rule, we adopt reforms to: (1) implement a first-ready, first-served 
cluster study process; \7\ (2) increase the speed of interconnection 
queue processing; and (3) incorporate technological advancements into 
the interconnection process.
---------------------------------------------------------------------------

    \7\ A first-ready, first-served cluster study process improves 
efficiency in the interconnection study process by including the 
following elements: increased access to information prior to 
entering the queue; a mechanism to study interconnection requests in 
groups where all interconnection requests in the group are equally 
queued and of equal study priority; and increased financial 
commitments and readiness requirements to enter and proceed through 
the queue. In contrast, the existing first-come, first-served serial 
study process in the pro forma LGIA and LGIP provides limited 
information to interconnection customers prior to entering the 
queue, assigns interconnection requests an individual queue position 
based solely on the date of entry into the queue, and contains 
limited financial and readiness requirements.
---------------------------------------------------------------------------

    5. First, in order to implement a first-ready, first-served cluster 
study process, this final rule requires: (1) transmission providers to 
publicly post available information pertaining to generator 
interconnection; (2) transmission providers to use cluster studies as 
the interconnection study method; (3) transmission providers to 
allocate cluster study costs on a pro rata and per capita basis; (4) 
transmission providers to allocate network upgrade costs based on a 
proportional impact method; (5) interconnection customers to pay study 
and commercial readiness deposits as part of the cluster study process; 
(6) interconnection customers to demonstrate site control at the time 
of submission of the interconnection request; and (7) transmission 
providers to impose withdrawal penalties on interconnection customers 
for withdrawing from the interconnection queue, with certain 
exceptions. We also require transmission providers to adopt a 
transition process to move from the existing serial interconnection 
process to the new cluster study process.
    6. Second, in order to increase the speed of interconnection queue 
processing, this final rule: (1) eliminates the reasonable efforts 
standard for conducting interconnection studies and imposes a financial 
penalty on transmission providers that fail to meet interconnection 
study deadlines; and (2) establishes an affected system study process 
and associated pro forma affected system agreements.
    7. Third, in order to incorporate technological advancements into 
the interconnection process, this final rule requires transmission 
providers to: (1) allow more than one generating facility to co-locate 
on a shared site behind a single point of interconnection and share a 
single interconnection request; (2) evaluate the proposed addition of a 
generating facility at the same point of interconnection prior to 
deeming such an addition a material modification if the addition does 
not change the originally requested interconnection service level; (3) 
allow interconnection customers to access the surplus interconnection 
service process once the original interconnection customer has an 
executed LGIA or requests the filing of an unexecuted LGIA; (4) use 
operating assumptions in interconnection studies that reflect the 
proposed charging behavior of an electric storage resource; and (5) 
evaluate the list of alternative transmission technologies enumerated 
in this final rule during the generator interconnection study process. 
This final rule also requires interconnection customers requesting to 
interconnect a non-synchronous generating facility to: (1) provide the 
transmission provider with the models needed for accurate 
interconnection studies; and (2) have the ability to maintain power 
production at pre-disturbance levels and provide dynamic reactive power 
to maintain system voltage during transmission system disturbances and 
within physical limits. Finally, this final rule requires that all 
newly interconnecting large generating facilities provide ride through 
capability consistent with any standards and guidelines that are 
applied to other generating facilities in the balancing authority area 
on a comparable basis.
    8. We also adopt reforms to the pro forma SGIP and pro forma SGIA. 
Specifically, as explained in detail in this final rule, for small 
generating facilities we propose reforms to incorporate the enumerated 
alternative transmission technologies into the interconnection process, 
and to provide modeling and ride through requirements for non-
synchronous generating facilities.
    9. Many of the reforms adopted in this final rule track the notice 
of proposed rulemaking's \8\ (NOPR) proposed reforms closely. However, 
as discussed more fully below, we have revised aspects of the reforms 
pertaining to the cluster study process, allocation of cluster study 
and network upgrade costs, increased financial commitments and 
readiness requirements, financial penalties for delayed interconnection 
studies, the affected system study process, pro forma affected system 
agreements, the material modification process, operating assumptions 
for interconnection studies, incorporating the enumerated alternative 
transmission technologies, and ride through requirements. Additionally, 
as discussed more fully below, we decline to adopt the NOPR proposals 
pertaining to informational interconnection studies, shared network 
upgrades, the optional resource solicitation study, and the alternative 
transmission technologies annual report.
---------------------------------------------------------------------------

    \8\ Improvements to Generator Interconnection Procs. & 
Agreements, 87 FR 39934 (July 5, 2022), 179 FERC ] 61,194 (2022) 
(NOPR).
---------------------------------------------------------------------------

    10. We recognize that transmission providers have undertaken 
efforts to address interconnection queue management issues. This final 
rule is not intended to divert or slow the potential progress 
represented by those efforts, and we encourage transmission providers 
to continue to innovate to remedy their identified interconnection 
queue management issues. We note that the compliance obligations that 
result from this final rule will be evaluated in light of the 
independent entity variation standard for regional transmission 
organizations (RTO) and independent system operators (ISO) and the 
consistent with or superior to standard for non-RTO/ISO transmission 
providers.\9\
---------------------------------------------------------------------------

    \9\ Order No. 2003, 104 FERC ] 61,103 at P 26; see infra section 
IV.
---------------------------------------------------------------------------

A. Historical Framework: Order Nos. 2003, 2006, and 845

    11. In Order No. 2003, the Commission recognized a need for a

[[Page 61016]]

standard set of interconnection procedures for transmission providers 
and a single, uniformly applicable interconnection agreement for large 
generating facilities.\10\ The Commission noted that generator 
interconnection is a ``critical component of open access transmission 
service and thus is subject to the requirement that utilities offer 
comparable service under the [pro forma open access transmission tariff 
(tariff)].'' \11\ The Commission found that it was appropriate to 
establish a standard set of generator interconnection procedures to 
``minimize opportunities for undue discrimination and expedite the 
development of new generation, while protecting reliability and 
ensuring that rates are just and reasonable.'' \12\ To this end, the 
Commission adopted the pro forma LGIP and pro forma LGIA and amended 
its regulations to require all transmission providers to incorporate 
these standard procedures and agreement into their tariffs.\13\
---------------------------------------------------------------------------

    \10\ Order No. 2003, 104 FERC ] 61,103 at P 11. Large generating 
facilities are defined to mean ``a Generating Facility having a 
Generating Facility Capacity of more than 20 MW.'' Pro forma LGIP 
section 1.
    \11\ Order No. 2003, 104 FERC ] 61,103 at P 9 (citing Tenn. 
Power Co., 90 FERC ] 61,238 (2000)).
    \12\ Id. P 11.
    \13\ 18 CFR 35.28(f)(1) (2022).
---------------------------------------------------------------------------

    12. To initiate the generator interconnection process set forth in 
the Commission's pro forma LGIP,\14\ the interconnection customer 
submits an interconnection request for its proposed generating facility 
that includes preliminary documentation of the site of the proposed 
generating facility, certain technical information about the proposed 
generating facility, and the expected commercial operation date of the 
proposed generating facility, along with a refundable deposit of 
$10,000.\15\ After the transmission provider determines that the 
interconnection request is complete, the interconnection request enters 
the transmission provider's interconnection queue with other pending 
interconnection requests and is assigned a queue position based on the 
time and date of its receipt.\16\ The queue position determines the 
order in which the transmission provider studies the interconnection 
requests in its interconnection queue.\17\
---------------------------------------------------------------------------

    \14\ While we provide a broad description of the process in the 
Commission's pro forma LGIP as background here, we recognize that 
many transmission providers have adopted (and the Commission has 
accepted) variations to many of the terms in the Commission's pro 
forma LGIP and pro forma LGIA. Consequently, some or many of the 
details of a particular transmission provider's generator 
interconnection procedures may vary considerably from the broad 
description provided here.
    \15\ Order No. 2003, 104 FERC ] 61,103 at P 35; pro forma LGIP 
sections 3.1, 3.4.
    \16\ Pro forma LGIP section 4.1.
    \17\ Id.
---------------------------------------------------------------------------

    13. Transmission providers must schedule a scoping meeting with the 
interconnection customer to discuss possible points of interconnection 
for the proposed generating facility and exchange technical 
information, which is followed by a series of interconnection studies 
to evaluate the proposed interconnection in detail.\18\ Transmission 
providers study interconnection requests in three phases: (1) the 
interconnection feasibility study (feasibility study); \19\ (2) the 
interconnection system impact study (system impact study); \20\ and (3) 
the interconnection facilities study (facilities study).\21\ These 
studies contain the power flow, short circuit, and stability analyses 
necessary to: (1) identify any adverse impacts on the transmission 
providers' transmission system or any affected systems; \22\ (2) 
determine the interconnection facilities and network upgrades \23\ 
needed to reliably interconnect the generating facility; and (3) 
estimate the interconnection customer's cost responsibility for these 
facilities.\24\ The pro forma LGIP requires that transmission providers 
use reasonable efforts to complete: (1) feasibility studies within 45 
calendar days; (2) system impact studies within 90 calendar days; and 
(3) facilities studies within 90 or 180 calendar days, depending on the 
interconnection customer's requested accuracy margin.\25\
---------------------------------------------------------------------------

    \18\ Order No. 2003, 104 FERC ] 61,103 at P 36; pro forma LGIP 
sections 3.4.4, 6-8.
    \19\ The pro forma LGIP defines a feasibility study as ``a 
preliminary evaluation of the system impact and cost of 
interconnecting the Generating Facility to the Transmission 
Provider's Transmission System.'' The scope of a feasibility study 
is described in section 6 of the pro forma LGIP. Pro forma LGIP 
sections 1, 6.
    \20\ The pro forma LGIP defines a system impact study as ``an 
engineering study that evaluates the impact of the proposed 
interconnection on the safety and reliability of Transmission 
Provider's Transmission System and, if applicable, an Affected 
System.'' In particular, a system impact study identifies and 
details ``the system impacts that would result if the Generating 
Facility were interconnected without project modifications or system 
modifications, focusing on the Adverse System Impacts identified in 
the [feasibility study], or to study potential impacts, including 
but not limited to those identified in the Scoping Meeting.'' Id. 
section 1.
    \21\ The pro forma LGIP defines a facilities study as ``a study 
conducted by the Transmission Provider or a third-party consultant 
for the Interconnection Customer to determine a list of facilities 
(including Transmission Provider's Interconnection Facilities and 
Network Upgrades as identified in the [system impact study]), the 
cost of those facilities, and the time required to interconnect the 
Generating Facility with the Transmission Provider's Transmission 
System.'' The scope of a facilities study is described in section 8 
of the pro forma LGIP. Id. sections 1, 8.
    \22\ The pro forma LGIP defines an affected system as an 
electric system other than the transmission provider's transmission 
system that may be affected by the proposed interconnection. Id. 
section 1; pro forma LGIA art. 1.
    \23\ For purposes of this final rule, unless otherwise noted, 
``network upgrades'' refer to interconnection-related network 
upgrades. More specifically, the pro forma LGIP and pro forma LGIA 
provide that, ``Network Upgrades shall mean the additions, 
modifications, and upgrades to the Transmission Provider's 
Transmission System required at or beyond the point at which the 
Interconnection Facilities connect to the Transmission Provider's 
Transmission System to accommodate the interconnection of the Large 
Generating Facility to the Transmission Provider's Transmission 
System.'' Pro forma LGIP section 1; pro forma LGIA art. 1.
    \24\ Order No. 2003, 104 FERC ] 61,103 at PP 35-37; pro forma 
LGIP sections 6-8. The interconnection customer is responsible for 
the actual costs of interconnection studies and any necessary 
restudies. Pro forma LGIP section 13.3.
    \25\ Pro forma LGIP sections 6.3, 7.4, 8.3.
---------------------------------------------------------------------------

    14. At the completion of the facilities study, the pro forma LGIP 
requires the transmission provider to issue a report on the best 
estimate of the costs to effectuate the requested interconnection and 
provide a draft generator interconnection agreement to the 
interconnection customer.\26\ If the interconnection customer wishes to 
proceed, after negotiations, the interconnection customer enters into a 
generator interconnection agreement with the transmission provider or, 
in specific circumstances, requests that the transmission provider file 
the agreement with the Commission unexecuted.\27\ The transmission 
provider is responsible for the construction of all network upgrades, 
but, as further discussed below, the interconnection customer has the 
option to build these facilities in certain circumstances.\28\
---------------------------------------------------------------------------

    \26\ Order No. 2003, 104 FERC ] 61,103 at P 38. Section 11.1 of 
the pro forma LGIP requires the transmission provider to tender a 
draft LGIA to the interconnection customer ``in the form of 
Transmission Provider's FERC-approved standard form LGIA.''
    \27\ If the transmission provider and interconnection customer 
execute an LGIA that conforms to the transmission provider's 
Commission-approved standard form LGIA, the agreement does not need 
to be filed with the Commission (if the transmission provider has 
such a standard form LGIA on file and submits an Electronic 
Quarterly Report). Alternatively, the transmission provider must 
file an LGIA with the Commission for review and approval if: (1) the 
interconnection customer determines that negotiations with the 
transmission provider over the terms of an LGIA are at an impasse 
and requests submission of the unexecuted LGIA with the Commission; 
or (2) the LGIA does not conform to the transmission provider's 
Commission-approved standard form LGIA. See Order No. 2003-A, 106 
FERC ] 61,220 at P 201; pro forma LGIP sections 11.2-11.3.
    \28\ Order No. 2003, 104 FERC ] 61,103 at PP 351-354; pro forma 
LGIA art. 5.1.3.
---------------------------------------------------------------------------

    15. Similar to Order No. 2003, in Order No. 2006, the Commission 
recognized the need for standardized

[[Page 61017]]

interconnection procedures and agreements for small generating 
facilities with a capacity of 20 MW or less.\29\ In addition to 
establishing a pro forma interconnection study process for small 
generating facilities similar to the process for large generating 
facilities established in Order No. 2003, the Commission included: (1) 
a ``fast track process'' \30\ that uses technical screens to evaluate a 
certified small generating facility no larger than 2 MW; and (2) a ``10 
[kilowatt (kW)] inverter process'' \31\ that uses the same technical 
screens to evaluate a certified inverter-based small generating 
facility no larger than 10 kW.\32\ The Commission later issued Order 
No. 792,\33\ in which the Commission revised the pro forma SGIP and pro 
forma SGIA to provide for interconnection customers to receive point of 
interconnection information in advance of submitting an interconnection 
request, increase the threshold for participation in the fast track 
process to five MW, and to specifically include electric storage 
devices.\34\
---------------------------------------------------------------------------

    \29\ Order No. 2006, 111 FERC ] 61,220 at P 36.
    \30\ Pro forma SGIP section 2.1.
    \31\ Id. attach. 5.
    \32\ Order No. 2006, 111 FERC ] 61,220 at PP 36, 38-39.
    \33\ Small Generator Interconnection Agreements & Procs., Order 
No. 792, 78 FR 73240 (Dec. 5, 2013), 145 FERC ] 61,159 (2013), 
clarifying, Order No. 792-A, 146 FERC ] 61,214 (2014).
    \34\ See Order No. 792, 145 FERC ] 61,159 at P 1.
---------------------------------------------------------------------------

    16. In response to concerns voiced to the Commission about 
interconnection queue management, in 2007, the Commission held a 
technical conference,\35\ and later issued an order \36\ addressing 
interconnection queue issues in RTOs/ISOs. In the order, the Commission 
noted that some transmission providers were not processing their 
interconnection queues within the timelines established in the pro 
forma LGIP, and in certain cases, were greatly exceeding them.\37\ The 
Commission stated that, although it ``may need to [impose solutions] if 
the RTOs and ISOs do not act themselves,'' each RTO/ISO would have an 
opportunity to work with its stakeholders to develop its own 
solutions.\38\ As further discussed below, following the order, 
multiple RTOs/ISOs submitted queue reform proposals to the Commission, 
some of which moved away from a so-called ``first-come, first-served'' 
approach (whereby interconnection requests are processed in the order 
they are received) to a so-called ``first-ready, first-served'' 
approach (whereby interconnection requests are processed based on when 
interconnection customers meet certain project development 
milestones).\39\ The reason for this move was to allow interconnection 
customers with interconnection requests for generating facilities more 
likely to achieve commercial operation to move faster instead of being 
delayed by interconnection requests that were higher in the 
interconnection queue but making limited or no progress towards 
commercial operation and creating unreasonable queue delays.
---------------------------------------------------------------------------

    \35\ Interconnection Queuing Practices, Notice of Technical 
Conference, Docket No. AD08-2-000 (issued Nov. 2, 2007).
    \36\ Interconnection Queuing Pracs., 122 FERC ] 61,252 (2008) 
(2008 Technical Conference Order).
    \37\ Id. P 3.
    \38\ Id. P 8.
    \39\ See, e.g., Sw. Power Pool, Inc., 128 FERC ] 61,114 (2009); 
Midwest Indep. Transmission Sys. Operator, Inc., 124 FERC ] 61,183 
(2008); Cal. Indep. Sys. Operator Corp., 124 FERC ] 61,292 (2008).
---------------------------------------------------------------------------

    17. In 2018, the Commission issued Order No. 845, in which the 
Commission made the most comprehensive revisions to the pro forma LGIP 
and pro forma LGIA since their adoption in Order No. 2003. In Order No. 
845, the Commission concluded that reforms to the pro forma LGIP and 
pro forma LGIA were needed to mitigate concerns regarding systemic 
inefficiencies, remedy discriminatory practices, and address recent 
developments, including changes in the resource mix and emergence of 
new technologies.\40\ The Commission therefore adopted reforms designed 
to improve certainty for interconnection customers, promote more 
informed interconnection decisions, and enhance the generator 
interconnection process.\41\
---------------------------------------------------------------------------

    \40\ Order No. 845, 163 FERC ] 61,043 at P 7.
    \41\ Id. P 2.
---------------------------------------------------------------------------

B. Regional Transmission Planning and Cost Allocation and Generator 
Interconnection Advance Notice of Proposed Rulemaking

    18. On July 15, 2021, the Commission issued an advance notice of 
proposed rulemaking (ANOPR) in Docket No. RM21-17-000, presenting 
potential reforms to the Commission's requirements governing the 
regional transmission planning and cost allocation and generator 
interconnection processes.\42\ Specific to the generator 
interconnection process, the Commission sought comment on whether and 
which reforms may be necessary to ensure a more purposeful integration 
of the generator interconnection process with the regional transmission 
planning and cost allocation processes, establish a faster and more 
efficient interconnection queueing process, and promote a more 
efficient and cost-effective allocation of network upgrade costs.\43\ 
For instance, the Commission noted that the cost of network upgrades 
can depend largely on both the timing of when the interconnection 
customer enters the interconnection queue and where the interconnection 
customer proposes to interconnect its generating facility. Therefore, 
the Commission noted, interconnection customers may submit multiple 
interconnection requests in an effort to determine the most favorable 
point of interconnection \44\ that minimizes their network upgrade 
costs.\45\ The Commission stated that this practice, in turn, may lead 
to late-stage withdrawals of the excess interconnection requests, which 
can then impede the transmission provider's ability to process its 
interconnection queue in an efficient manner. As a result, the 
Commission stated that it may be time to consider reforms to the 
generator interconnection process that would make it more efficient and 
ensure that generating facilities that are more ``ready'' than others 
are not unduly delayed in the interconnection queue.
---------------------------------------------------------------------------

    \42\ Bldg. for the Future Through Elec. Reg'l Transmission 
Planning & Cost Allocation & Generator Interconnection, 86 FR 40266 
(July 15, 2021), 176 FERC ] 61,024 (2021) (ANOPR).
    \43\ Id. P 5.
    \44\ The pro forma LGIP defines point of interconnection as 
``the point, as set forth in Appendix A to the Standard Large 
Generator Interconnection Agreement, where the Interconnection 
Facilities connect to the Transmission Provider's Transmission 
System.'' Pro forma LGIP section 1.
    \45\ ANOPR, 176 FERC ] 61,024 at P 41.
---------------------------------------------------------------------------

    19. On April 21, 2022, the Commission issued a notice of proposed 
rulemaking (Transmission Planning and Cost Allocation NOPR) proposing 
reforms to its existing regional transmission planning and cost 
allocation requirements in the same proceeding as it issued the 
ANOPR.\46\ While the Transmission Planning and Cost Allocation NOPR did 
not address many of the concerns raised by the Commission in the ANOPR 
with respect to the generator interconnection queue process, the 
Commission noted in the Transmission Planning and Cost Allocation NOPR 
that it would continue to review the record and that it expected to 
address possible inadequacies through subsequent proceedings that 
propose reforms, as warranted, related to that topic.\47\ The 
Commission took that next step with the reforms proposed

[[Page 61018]]

in the NOPR in this proceeding, many of which we adopt in this final 
rule.
---------------------------------------------------------------------------

    \46\ Bldg. for the Future Through Elec. Reg'l Transmission Plan. 
& Cost Allocation & Generator Interconnection, 87 FR 26504 (May 4, 
2022), 179 FERC ] 61,028 (2022).
    \47\ Id. P 10.
---------------------------------------------------------------------------

C. Notice of Proposed Rulemaking

    20. On June 16, 2022, the Commission issued the NOPR, proposing 
reforms focused on improving aspects of the pro forma LGIP, pro forma 
LGIA, pro forma SGIP, and pro forma SGIA. The Commission also sought 
comment on, but did not propose, tariff revisions on other issues.
    21. First, the Commission proposed reforms focused on improving 
interconnection processes to ensure interconnection customers can 
proceed in an efficient and timely manner.\48\ Among those, the 
Commission proposed to: (1) require transmission providers to offer an 
optional informational interconnection study to serve as additional 
information for prospective interconnection customers in deciding 
whether to submit an interconnection request and set minimum 
requirements for transmission providers to publicly post available 
information pertaining to generator interconnection; \49\ (2) require 
transmission providers to implement a first-ready, first-served cluster 
study process that allocates costs associated with cluster studies and 
identified network upgrades consistent with the discussion below; \50\ 
and (3) impose more stringent financial commitments and readiness 
requirements on interconnection customers, including increased study 
deposits, more stringent site control requirements, a commercial 
readiness framework, and higher withdrawal penalties.\51\ To implement 
these reforms, the Commission also proposed to require transmission 
providers to establish a transition process.\52\
---------------------------------------------------------------------------

    \48\ NOPR, 179 FERC ] 61,194 at P 4.
    \49\ Id. PP 42-52.
    \50\ Id. PP 56-101.
    \51\ Id. PP 104-148.
    \52\ Id. PP 150-160.
---------------------------------------------------------------------------

    22. Second, the Commission proposed three reforms to increase the 
speed of interconnection queue processing, including: (1) revisions to 
eliminate the reasonable efforts standard for interconnection study 
processing; \53\ (2) revisions to establish an affected system study 
process, along with necessary pro forma affected system agreements; 
\54\ and (3) revisions to establish an optional resource solicitation 
study.\55\
---------------------------------------------------------------------------

    \53\ Id. PP 168-173.
    \54\ Id. PP 182-215.
    \55\ Id. PP 223-237.
---------------------------------------------------------------------------

    23. Finally, the Commission proposed three reforms to incorporate 
technological advancements into the interconnection study process. With 
these reforms, the Commission proposed to require transmission 
providers to: (1) increase flexibility in the generator interconnection 
process by allowing generating facilities to co-locate, allow the 
interconnection customer to request the addition of a generating 
facility to an existing interconnection request, increase the 
availability of surplus interconnection service, and allow 
interconnection customers to propose operating assumptions for their 
generating facilities; \56\ (2) incorporate the enumerated alternative 
transmission technologies into the interconnection study process at the 
request of the interconnection customer; \57\ and (3) list required 
modeling standards for inclusion in all interconnection requests that 
include inverter-based resources (IBRs), as well as require certain 
performance standards from IBRs during system disturbances.\58\
---------------------------------------------------------------------------

    \56\ Id. PP 242-288.
    \57\ Id. PP 297-302.
    \58\ Id. PP 328-341.
---------------------------------------------------------------------------

    24. In response to the NOPR, 189 comments were filed.\59\ These 
comments have informed our determinations in this final rule.
---------------------------------------------------------------------------

    \59\ Appendix A lists the entities that submitted comments on 
the NOPR and the shortened names used through this final rule to 
describe those entities.
---------------------------------------------------------------------------

D. Joint Federal-State Task Force on Electric Transmission

    25. On June 17, 2021, the Commission established a Joint Federal-
State Task Force on Electric Transmission (Task Force) to formally 
explore broad categories of transmission-related topics.\60\ The 
Commission explained that the development of new transmission 
infrastructure implicated a host of different issues, including 
generator interconnection. The Task Force is comprised of all FERC 
Commissioners as well as representatives from 10 state commissions 
nominated by the National Association of Regulatory Utility 
Commissioners (NARUC), with two originating from each NARUC region.\61\ 
The Task Force convenes for multiple formal meetings annually, which 
are open to the public. Since its creation and as of the date of 
issuance of this final rule, the Task Force has met seven times.
---------------------------------------------------------------------------

    \60\ Joint Fed.-State Task Force on Elec. Transmission, 175 FERC 
] 61,224, at PP 1, 6 (2021).
    \61\ An up-to-date list of Task Force members, as well as 
additional information on the Task Force, is available on the 
Commission's website at: <a href="https://www.ferc.gov/TFSOET">https://www.ferc.gov/TFSOET</a>. Public 
materials related to the Task Force, including transcripts from 
public meetings, are available in the Commission's eLibrary in 
Docket No. AD21-15-000.
---------------------------------------------------------------------------

    26. The discussion at the May 2022 meeting focused on 
interconnection issues, including generator interconnection queue 
processes and backlogs. The Task Force members discussed: the primary 
challenges preventing more efficient processing of interconnection 
queues; specific improvements to interconnection processes (such as 
tighter applicant requirements to enter and remain in the queue, 
clustering, fast tracking, tighter deadlines on transmission providers 
completing studies, and minimizing reiterative studies); and how to 
balance near-term improvements to the interconnection procedures with 
longer-term regional transmission planning and development.\62\
---------------------------------------------------------------------------

    \62\ Joint Fed.-State Task Force on Elec. Transmission, Notice 
of Meeting, Docket No. AD21-15-000 (issued Apr. 22, 2022).
---------------------------------------------------------------------------

II. Overall Need for Reform

A. NOPR

    27. In the NOPR, the Commission noted that the serial first-come, 
first-served study process was adopted at a time when most 
interconnection requests were for large traditional generating 
facilities that would use readily available transmission capacity.\63\ 
The Commission stated that the continued use of this process in the 
face of dramatic changes to the electric power industry, principally 
the surge in interconnection requests, the rapidly changing resource 
mix, evolving market forces, and the emergence of new technologies, has 
led to a growing backlog of interconnection requests and study delays 
for many transmission providers.\64\ The Commission also stated that 
these interconnection queue backlogs and study delays create 
uncertainty and inhibit project developers' ability to interconnect 
generating facilities to the transmission system.\65\ The Commission 
preliminarily found that the existing pro forma LGIP, pro forma LGIA, 
pro forma SGIP, and pro forma SGIA may be insufficient to ensure that 
new generating facilities are able to interconnect to the transmission 
system in a reliable, efficient, transparent, and timely manner and to 
thereby ensure that rates, terms, and conditions for Commission-
jurisdictional services are just, reasonable, and not unduly

[[Page 61019]]

discriminatory or preferential.\66\ Further, because the 
interconnection queue backlogs and study delays afflicting generator 
interconnection service nationwide hinder the timely development of new 
generation and thereby stifle competition in the wholesale electric 
markets, the Commission also preliminarily found that the Commission's 
pro forma LGIP, pro forma LGIA, pro forma SGIP, and pro forma SGIA 
result in rates, terms, and conditions in the wholesale electric 
markets that are unjust, unreasonable, and unduly discriminatory or 
preferential.
---------------------------------------------------------------------------

    \63\ NOPR, 179 FERC ] 61,194 at P 18.
    \64\ Id. PP 18-20.
    \65\ Id. P 19 (citing Joint Fed.-State Task Force on Elec. 
Transmission, Technical Conference, Docket No. AD21-15-000, Tr. 
15:21-16:1 (Ted Thomas) (May 6, 2022) (May Joint Task Force Tr.) 
(``Houston, we have a problem. As stated in the NARUC ANOPR 
comments, existing methods for interconnecting new resources to the 
transmission grid are inadequate and inefficient because of the time 
necessary to interconnect new resources and the corresponding 
network upgrade costs.'')).
    \66\ Id. P 22 (citing May Joint Task Force Tr. 23:6-11 (Riley 
Allen) (``Ultimately, this system is not working efficiently now and 
those inefficiencies translate into costs. It's not just cost on the 
developers, but I find from my decades of experience that, if there 
are inefficiencies in the system, they ultimately have to be borne 
by the loads and ratepayer interests.'')).
---------------------------------------------------------------------------

    28. The Commission stated that its preliminary findings were based 
on several features of the Commission's existing generator 
interconnection procedures and agreements that are of concern, 
specifically: (1) the information (or lack thereof) available to 
prospective interconnection customers and the commitments required of 
them to enter and progress through the interconnection queue; (2) the 
reliance on a serial first-come, first-served study process and the 
standard to which transmission providers are held for meeting 
interconnection study deadlines; (3) the protocols for affected systems 
studies; (4) the provisions for studying new or hybrid generation 
technologies and considering alternative transmission technologies; and 
(5) the performance requirements for non-synchronous generating 
facilities, including wind, solar, and electric storage facilities.\67\
---------------------------------------------------------------------------

    \67\ Id. PP 23-36 (citing May Joint Task Force Tr. 70:20-71:6 
(Matthew Nelson) (analogizing reiterative studies to going to the 
supermarket to buy ingredients for a recipe without knowing how much 
the ingredients cost, finding out at the register that they cost too 
much for your budget, and having to ``go home, get a new recipe, and 
start it all over again'')).
---------------------------------------------------------------------------

    29. The Commission found that some of the same issues persist in 
the small generating facility context and, therefore, proposed limited 
reforms to the pro forma SGIP and pro forma SGIA to incorporate 
alternative transmission technologies into the interconnection process 
and to provide modeling and performance requirements for non-
synchronous generating facilities.\68\
---------------------------------------------------------------------------

    \68\ Id. P 5.
---------------------------------------------------------------------------

B. Comments

    30. The vast majority of commenters overwhelmingly agree with the 
Commission's preliminary conclusion that there is a need to reform the 
Commission's pro forma interconnection procedures and agreements to 
ensure that interconnection customers are able to interconnect to the 
transmission system in a reliable, efficient, transparent, and timely 
manner, thereby ensuring that rates, terms, and conditions for 
Commission-jurisdictional services are just, reasonable, and not unduly 
discriminatory or preferential.\69\ These commenters generally agree 
that the unprecedented volume of generation in the interconnection 
queue, which is almost equal to the current U.S. generation fleet, has 
resulted in severe backlogs in interconnection processes across the 
country.\70\ For example, the Ohio Commission Consumer Advocate states 
that ``there is an urgent need to clear the current generator 
interconnection queue backlog and to facilitate timely and economic 
interconnection of new resources in a way that responds to current and 
future market conditions.'' \71\ EEI recognizes that, despite many 
efforts underway across the country to fix individual transmission 
provider interconnection queue processes, there is still a need for the 
Commission to address backlogs and improve certainty in the 
interconnection queue process.\72\ Several commenters assert that these 
interconnection backlogs have resulted in commercial uncertainty 
regarding both the magnitude of identified upgrade costs and the 
timeline for completion of interconnection studies, delayed project 
development, increased costs for consumers due to the prevention of new 
supply from reaching the market, and impaired reliability.\73\ Senators 
Hickenlooper and King note that, in the past decade, 23% of proposed 
generating facilities reached commercial operation, while 72% were 
withdrawn.\74\ ELCON and APPA-LPPC both argue that uncertainty, on the 
part of both transmission provider and generator project developer, 
inevitably leads to an increase in costs to consumers.\75\ U.S. DOE 
submits a recent report published by the Lawrence Berkeley National 
Laboratory, which finds that interconnection costs in MISO have 
escalated as the number of interconnection requests has increased.\76\ 
Specifically, the report finds that interconnection costs in MISO 
doubled for projects completed between 2019-2021 compared to projects 
completed prior to 2018, and cost estimates tripled for projects still 
active in the queue between the same time periods. Some commenters 
agree that the existing interconnection rules in the pro forma LGIP and 
pro forma LGIA create an incentive for interconnection customers to 
submit interconnection requests even if they are not prepared to

[[Page 61020]]

move forward with their projects, in order to secure a favorable 
position in the interconnection queue or in an attempt to obtain 
locations with available transmission capacity.\77\ They assert that 
the withdrawal of each speculative interconnection request triggers 
reassessments and possible restudies by the transmission provider that 
can increase the timing and interconnection cost for lower-queued 
interconnection requests. Several commenters point to ambitious climate 
goals (such as the United States' commitment to reducing net greenhouse 
gas emissions by 50-52% by 2030 under the Paris Climate Agreement) and 
argue that: (1) these changes will likely spur greater investment in 
new generation and exacerbate the delays in processing interconnection 
requests; and/or (2) without an efficient and transparent 
interconnection process, none of the clean energy generating facilities 
intended to meet these goals can be effectively deployed.\78\ Consumers 
Energy argues that delays in processing interconnection requests will 
exacerbate resource adequacy challenges.\79\
---------------------------------------------------------------------------

    \69\ ACE-NY Initial Comments at 2; ACE-NY Reply Comments at 5; 
AEE Initial Comments at 3, 5; AEE Reply Comments at 5; AES Initial 
Comments at 2; Affected Interconnection Customers Initial Comments 
at 2; Ameren Initial Comments at 2; APPA-LPPC Reply Comments at 2; 
Avangrid Initial Comments at 6, 8; Bonneville Initial Comments at 3; 
CESA Initial Comments at 3; CESA Reply Comments at 1; Clean Energy 
Associations Initial Comments at 8; Clean Energy Buyers Initial 
Comments at 3; Clean Energy States Initial Comments at 2-3; Colorado 
Commission Initial Comments at 1; Consumers Energy Initial Comments 
at 2; Cypress Creek Initial Comments at 1; Dominion Initial Comments 
at 4; EEI Initial Comments at 2; EEI Reply Comments at 3; EDF 
Renewables Initial Comments at 1-2; Enel Initial Comments at 2; 
Energy Keepers Initial Comments at 2; Evergreen Action Initial 
Comments at 1; Eversource Initial Comments at 2; Fervo Energy 
Initial Comments at 2; Google Initial Comments at 2; Guzman Energy 
Initial Comments at 2; Hannon Armstrong Initial Comments at 1; 
Hydropower Commenters Initial Comments at 5; Illinois Commission 
Initial Comments at 2-3, 5; Interwest Initial Comments at 3; 
Interwest Reply Comments at 2; ISO-NE Initial Comments at 2-3; MISO 
TOs Initial Comments at 2, 6; NARUC Initial Comments at 3; New 
Jersey Commission Initial Comments at 4-9; NY Commission and NYSERDA 
Initial Comments at 3; NV Energy Initial Comments at 3; Ohio 
Commission Consumer Advocate Initial Comments at 3-4; OMS Initial 
Comments at 2; [Oslash]rsted Initial Comments at 5; Pine Gate 
Initial Comments at 8; PJM Initial Comments at 1, 4; PJM Coalition 
Initial Comments at 1; RWE Renewables Initial Comments at 1; 
Senators Hickenlooper and King Initial Comments at 1-2; Shell 
Initial Comments at 5-6; State Agencies Initial Comments at 1-2; 
TAPS Initial Comments at 1; Union of Concerned Scientists Reply 
Comments at 1; UMPA Initial Comments at 1; WATT Coalition Initial 
Comments at 1; Xcel Initial Comments at 8.
    \70\ AEE Initial Comments at 3; Apple Initial Comments at 1; 
Bonneville Initial Comments at 3; Clean Energy Buyers Initial 
Comments at 3; Colorado Commission Initial Comments at 2, 8-11; EDF 
Renewables Initial Comments at 2; Evergreen Action Initial Comments 
at 1; Eversource Initial Comments at 2; Interwest Initial Comments 
at 1-2; NV Energy Initial Comments at 2-3; Ohio Commission Consumer 
Advocate Initial Comments at 3-4; [Oslash]rsted Initial Comments at 
2; Senators Hickenlooper and King Initial Comments at 1-2; U.S. 
Chamber of Commerce Initial Comments at 5; UMPA Initial Comments at 
1.
    \71\ Ohio Commission Consumer Advocate Initial Comments at 3-4.
    \72\ EEI Reply Comments at 3.
    \73\ ACE-NY Initial Comments at 2; AEE Initial Comments at 4; 
EDF Renewables Initial Comments at 2; ELCON Initial Comments at 2; 
Fervo Energy Initial Comments at 2; PJM Coalition Initial Comments 
at 2; Xcel Reply Comments at 1.
    \74\ Senators Hickenlooper and King Initial Comments at 1 
(citing Joseph Rand et al., Lawrence Berkeley Nat'l Lab., Queued Up: 
Characteristics of Power Plants Seeking Transmission Interconnection 
(Apr. 2022) (Queued Up 2022), <a href="https://emp.lbl.gov/sites/default/files/queued_up_2021_04-13-2022.pdf">https://emp.lbl.gov/sites/default/files/queued_up_2021_04-13-2022.pdf</a>)).
    \75\ ELCON Initial Comments at 2; APPA-LPPC Initial Comments at 
2.
    \76\ U.S. DOE Initial Comments at 1 (citing Joachim Seel et al., 
Lawrence Berkeley Nat'l Lab., Interconnection Cost Analysis in the 
MISO Territory at 1 (Oct. 2022)).
    \77\ Clean Energy Buyers Initial Comments at 3; Dominion Initial 
Comments at 4-5; PJM Initial Comments at 12; U.S. Chamber of 
Commerce Initial Comments at 4-5.
    \78\ AEP Initial Comments at 2; Affected Interconnection 
Customers Initial Comments at 2; Allen Meyer Initial Comments at 1; 
Apple Initial Comments at 1; Bretton C Little Initial Comments at 1; 
Colorado Commission Initial Comments at 13-14; EDF Renewables 
Initial Comments at 2-3 (referencing Inflation Reduction Act, Pub. 
L. 117-169 (2022)); ELCON Initial Comments at 2; Evergreen Action 
Initial Comments at 2; GSCE Initial Comments at 5-6; Individual 
Signatories Initial Comments at 1-2; Interwest Comments at 1-2; 
National Grid Initial Comments at 2; Payton Alaama Reply Comments at 
1; Pine Gate Reply Comments at 3-4; Rick K Lathrop Reply Comments at 
1; Shell Initial Comments at 6; State Agencies Initial Comments at 
8-9 (citing Int'l Energy Agency, Net Zero by 2050: A Roadmap for the 
Global Energy Sector (2021) <a href="https://www.iea.org/reports/net-zero-by-2050">https://www.iea.org/reports/net-zero-by-2050</a>; The United States' Nationally Determined Contribution (2021), 
<a href="https://www4.unfccc.int/sites/ndcstaging/PublishedDocuments/United%20States%20of%20America%20First/United%20States%20NDC%20April%2021%202021%20Final.pdf">https://www4.unfccc.int/sites/ndcstaging/PublishedDocuments/United%20States%20of%20America%20First/United%20States%20NDC%20April%2021%202021%20Final.pdf</a>; White House, 
FACT SHEET: Biden Administration Jumpstarts Offshore Wind Energy 
Projects to Create Jobs (Mar. 29, 2021), <a href="https://www.whitehouse.gov/briefing-room/statements-releases/2021/03/29/fact-sheet-biden-administration-jumpstarts-offshore-wind-energy-projects-to-create-jobs/">https://www.whitehouse.gov/briefing-room/statements-releases/2021/03/29/fact-sheet-biden-administration-jumpstarts-offshore-wind-energy-projects-to-create-jobs/</a>); Sue Hilton Initial Comments at 1; Union of Concerned 
Scientists Reply Comments at 6; Vistra Initial Comments at 4.
    \79\ Consumers Energy Initial Comments at 7.
---------------------------------------------------------------------------

    31. A small subset of commenters, while supporting an overall need 
for reform, disagree with some of the Commission's preliminary 
conclusions about the need for reform.\80\ A few other commenters claim 
that there is no basis for the Commission's preliminary conclusion that 
speculative projects that enter the interconnection queue and later 
withdraw, causing cascading restudies, are responsible for 
interconnection queue backlogs.\81\ A few commenters assert that the 
Commission did not take into account pertinent factors affecting 
interconnection queue sizes, such as an increase in the development of 
smaller, more diverse generating facilities.\82\
---------------------------------------------------------------------------

    \80\ For instance, Affected Interconnection Customers disagree 
with the Commission's reference to a nationwide shortage of 
qualified engineers and contend that the Commission fails to support 
this conclusion with any evidence beyond statements made by CAISO 
and MISO. Affected Interconnection Customers Initial Comments at 14 
(citing NOPR, 179 FERC ] 61,194 at P 20 n.67).
    \81\ CREA and NewSun Initial Comments at 35-37 (countering that 
interconnection requests do not reach commercial operation due to 
other reasons such as permitting or financing difficulties); NextEra 
Initial Comments at 4; Public Interest Organizations Initial 
Comments at 1-7 (arguing that the rate of queue withdrawal has been 
consistent over the last decade); SEIA Reply Comments at 1.
    \82\ AEE Initial Comments at 6-7; Pine Gate Reply Comments at 4; 
SEIA Reply Comments at 1.
---------------------------------------------------------------------------

    32. Three comments note that various transmission providers use 
vastly different interconnection procedures from the pro forma 
procedures established in Order No. 2003 and argue that there is an 
insufficient legal foundation under FPA section 206 to demonstrate that 
all of these approved interconnection procedures are unjust, 
unreasonable, and unduly discriminatory or preferential.\83\ Southern 
disagrees entirely with the Commission's preliminary conclusion that 
there is a need for reform.\84\ Southern argues that the Commission 
based its proposed actions in the NOPR on conjecture and thus failed to 
provide substantial evidence or engage in reasoned decision-making to 
demonstrate that the current interconnection processes are unjust and 
unreasonable.\85\ In addition, Southern contends that the Commission's 
proposals are arbitrary and capricious because they impose a broadly 
applicable remedy to a problem that does not exist uniformly.\86\
---------------------------------------------------------------------------

    \83\ Early Adopters Coalition Initial Comments at 1-2; 
PacifiCorp Initial Comments at 9; Southern Initial Comments at 10-
11.
    \84\ Southern Initial Comments at 10-12; Southern Reply Comments 
at 1, 4.
    \85\ Southern Initial Comments at 10 (citing Emera Me. v. FERC, 
854 F.3d 9, 24 (D.C. Cir. 2017)); Southern Reply Comments at 1, 4.
    \86\ Southern Initial Comments at 11-12.
---------------------------------------------------------------------------

    33. Southern further asserts that the Commission failed to provide 
any actual evidence that its proposals will reduce interconnection 
queue backlogs or increase certainty for interconnection customers.\87\
---------------------------------------------------------------------------

    \87\ Id. at 10; Southern Reply Comments at 5.
---------------------------------------------------------------------------

    34. Some commenters argue that the sum of the NOPR may actually 
slow study processes, increase backlogs, and may unintentionally 
increase costs to ratepayers.\88\ For example, CAISO asserts that 
shortening study timelines results in rushed, unreliable studies which 
would ultimately require more iteration and longer interconnection 
queue processing times.\89\ Additionally, NextEra argues that the NOPR 
provides few, if any, solutions relevant to those regions that have 
already implemented cluster studies yet continue to experience 
significant study delays.\90\ Further, some commenters oppose any 
generic one-size-fits-all reform, arguing that queue reform is best 
left to the regional level.\91\
---------------------------------------------------------------------------

    \88\ CAISO Initial Comments at 3; Dominion Initial Comments at 
7; New York State Department Initial Comments at 2; NextEra Reply 
Comments at 2; NRECA Initial Comments at 7.
    \89\ CAISO Initial Comments at 3.
    \90\ NextEra Reply Comments at 7.
    \91\ Avangrid Initial Comments at 36-37; Southern Initial 
Comments at 14-15.
---------------------------------------------------------------------------

    35. Several commenters generally support the suite of proposed 
reforms in their entirety.\92\ As discussed in detail in each section 
below discussing individual reforms, most commenters either support 
specific proposals or suggest that the Commission prioritize certain 
proposed reforms. For instance, Consumers Energy supports reforms that 
increase the speed of interconnection queue processing because it 
claims that the reforms provide clarity for resource planners and 
interconnection customers as well as improve the reliability of the 
bulk electric system and the clean energy resource transformation.\93\ 
Google urges the Commission to prioritize reforms that provide a level 
playing field for both utility-backed resources and independent power 
producer-developed resources.\94\ Google also expresses concern that 
the layering of increased study deposits, more stringent site control 
requirements, the proposed commercial readiness requirements, and 
withdrawal penalties may place undue burden on interconnection 
customers if the Commission does not also adopt proposals for more 
publicly available interconnection information, firm study deadlines, 
and penalties for missed study deadlines.\95\
---------------------------------------------------------------------------

    \92\ APPA-LPPC Initial Comments at 2-3; APPA-LPPC Reply Comments 
at 2; Apple Initial Comments at 1; ACORE Initial Comments at 2; 
Amazon Initial Comments at 2; Evergreen Action Initial Comments at 
1-4; Individual Signatories Initial Comments at 1; PJM Coalition 
Initial Comments at 2.
    \93\ Consumers Energy Initial Comments at 10-11.
    \94\ Google Initial Comments at 3.
    \95\ Id. at 16.
---------------------------------------------------------------------------

    36. Some commenters support adopting most or all of the limited

[[Page 61021]]

reforms to the pro forma SGIP and pro forma SGIA proposed in the 
NOPR.\96\ For instance, Microgrid Resources asserts that including the 
proposed reforms in the pro forma SGIP is necessary to reflect the 
operating assumptions of, and to provide equitable treatment for, 
microgrids and other behind-the-meter resources.\97\ Microgrid 
Resources asserts that, if the Commission succeeds in expediting 
interconnections for large generating facilities, while small 
generating facility interconnections languish, it will bias the system 
against smaller local generating facilities that are the backbone of 
community resilience.
---------------------------------------------------------------------------

    \96\ Bonneville Initial Comments at 24 (supporting applying some 
of the Commission's proposed reforms to the pro forma SGIP and pro 
forma SGIA (e.g., commercial readiness requirements), but asking 
that transmission providers be granted flexibility to determine 
which reforms should be applicable to small generator procedures and 
agreements); IREC Initial Comments at 3 (stating that the pro forma 
SGIP lacks the necessary provisions to safely and reliably 
interconnect storage to the electric grid while enabling its unique 
operating characteristics); Microgrid Resources Initial Comments at 
8-9; Xcel Initial Comments at 19 (supporting applying reforms to 
small generating facilities requesting energy only interconnection 
service).
    \97\ Microgrid Resources Initial Comments at 8-9.
---------------------------------------------------------------------------

C. Commission Determination

    37. Based on the record, including comments submitted in response 
to the NOPR, as discussed below, we find that there is substantial 
evidence to support the conclusion that the existing pro forma 
generator interconnection procedures and agreements are unjust, 
unreasonable, and unduly discriminatory or preferential.\98\ We 
therefore adopt the preliminary findings in the NOPR concerning the 
need for reform \99\ and, pursuant to FPA section 206, conclude that 
certain revisions to the pro forma open access transmission tariff and 
the Commission's regulations are necessary to ensure rates that are 
just, reasonable, and not unduly discriminatory or preferential. 
Specifically, we find that the existing pro forma generator 
interconnection procedures and agreements are insufficient to ensure 
that interconnection customers are able to interconnect to the 
transmission system in a reliable, efficient, transparent, and timely 
manner, thereby ensuring that rates, terms, and conditions for 
Commission-jurisdictional services are just, reasonable, and not unduly 
discriminatory or preferential. Absent reform, the current 
interconnection process will continue to cause interconnection queue 
backlogs, longer development timelines, and increased uncertainty 
regarding the cost \100\ and timing of interconnecting to the 
transmission system. These backlogs and delays, and the resulting 
timing and cost uncertainty,\101\ hinder the timely development of new 
generation and thereby stifle competition in the wholesale electric 
markets resulting in rates, terms, and conditions that are unjust, 
unreasonable, and unduly discriminatory or preferential.
---------------------------------------------------------------------------

    \98\ 16 U.S.C. 824e(a); 18 CFR 385.206 (2022).
    \99\ NOPR, 179 FERC ] 61,194 at PP 18-36.
    \100\ See May Joint Task Force Tr. 74:9-21 (Andrew French) 
(stating that generator developers complain principally about cost 
certainty and cost sharing and that ``cost certainty is the much 
bigger issue'' given that ``an essential element of being able to 
sell a product is to know what your inputs are so you can market 
it'').
    \101\ See May Joint Task Force Tr. 23:18-25 (Jason Stanek) 
(expressing frustration with the status quo and agreement that it is 
``no longer tenable'' considering the inability of generators to 
interconnect in a timely manner, e.g., there are ``2,500 projects 
under study [in the MACRUC region] and about a half of them have 
been in the queue since at least 2001'').
---------------------------------------------------------------------------

    38. Indeed, recent data support the Commission's preliminary 
findings in the NOPR that the dramatic increase in the number of 
interconnection requests and limited transmission capacity are 
increasing interconnection queue backlogs across all regions of the 
country.\102\ As of the end of 2022, there were over 10,000 active 
interconnection requests in interconnection queues throughout the 
United States, representing over 2,000 gigawatts (GW) of potential 
generation and storage capacity.\103\ This potential generation is the 
largest interconnection queue size on record, more than four times the 
total volume (in GW) of the interconnection queues in 2010, and a 40% 
increase over the interconnection queue size from just the year 
prior.\104\ These trends are not exclusive to any one region of the 
country. Instead, every single region has faced an increase in both 
interconnection queue size and the length of time interconnection 
customers are spending in the interconnection queue prior to commercial 
operation in recent years.\105\ This is true for RTO/ISO and non-RTO/
ISO regions alike. The non-RTO/ISO west and southeast regions both have 
faced queue size increases ranging from tripling to a 12-fold increase 
while also seeing longer timelines between interconnection requests and 
commercial operation dates.\106\ Furthermore, the uncertainty and 
delays in the interconnection queues have resulted in fewer than 25% of 
interconnection requests, by capacity, reaching commercial operation 
between 2000 and 2017 in any region of the country--with some regions 
as low as 8%.\107\
---------------------------------------------------------------------------

    \102\ Joseph Rand et al., Lawrence Berkeley Nat'l Lab., Queued 
Up: Characteristics of Power Plants Seeking Transmission 
Interconnection, at 7-8 (Apr. 2023) (Queued Up 2023), <a href="https://emp.lbl.gov/sites/default/files/queued_up_2022_04-06-2023.pdf">https://emp.lbl.gov/sites/default/files/queued_up_2022_04-06-2023.pdf</a>; see 
also Order No. 845, 163 FERC ] 61,043 at P 305 (requiring 
transmission providers to post interconnection study metrics). See 
appendix B to this final rule, which provides an overview of recent 
data based on reporting by transmission providers in compliance with 
Order No. 845.
    \103\ Queued Up 2023 at 7-8.
    \104\ Id. at 10.
    \105\ Id. at 9, 32.
    \106\ Id. at 9, 32.
    \107\ Id. at 3, 21.
---------------------------------------------------------------------------

    39. Additionally, recent data continue to show that interconnection 
customers are waiting longer in the interconnection queue before 
withdrawing their interconnection requests,\108\ even as overall 
interconnection study timelines are increasing in many regions.\109\ 
For example, AEE states that, as of February 2022, all 2,274 projects 
waiting for an interconnection agreement in the PJM interconnection 
queue had been waiting for a year or more; 33% (758 projects) had been 
waiting more than 500 days, 22% (497 projects) have been stuck for more 
than two years, and 7% (166 projects) have been waiting more than three 
years.\110\ NV Energy explains that several western utilities that are 
not currently part of an RTO/ISO are experiencing an unprecedented high 
volume of requests in excess of the utility's peak load.\111\ AEE notes 
that wait times for generating facilities in interconnection queues 
nationwide have increased from 2.1 years for generating facilities 
built in 2000-2010 to 3.7 years for those built in 2011-2021.\112\ And 
despite efforts to address

[[Page 61022]]

these challenges,\113\ interconnection queue backlogs and delays have 
persisted and worsened. For generating facilities built in 2022, wait 
times in the interconnection queue saw a marked increase to now roughly 
five years.\114\
---------------------------------------------------------------------------

    \108\ Id. at 25 (reporting that, although the median withdrawal 
duration has been relatively consistent over time, the mean 
withdrawal duration and distributions have edged higher in recent 
years).
    \109\ Id. at 27.
    \110\ AEE Initial Comments at 4 (citing Advanced Energy Economy, 
``In PJM, Renewable Energy Projects Are Getting Stuck'' (February 
2022), <a href="https://blog.aee.net/in-pjm-renewable-energy-projects-are-getting-stuck">https://blog.aee.net/in-pjm-renewable-energy-projects-are-getting-stuck</a>).
    \111\ NV Energy Initial Comments at 2-3. NV Energy explains that 
it has a peak load of 9,400 MW with an interconnection queue backlog 
for projects totaling more than 27,000 MW; Idaho Power has a peak 
load of 3,751 MW with an interconnection queue backlog of over 
18,000 MW; PacifiCorp has a peak load of 13,000 MW with an 
interconnection queue backlog of over 45,000 MW; and APS has a peak 
load of 7,600 MW with an interconnection queue backlog of over 
50,000 MW.
    \112\ AEE Initial Comments at 4 (citing Queued Up 2022); see 
also ACE-NY Initial Comments at 2 (arguing that the ability of New 
York to meet its clean energy goals is threatened by an 
interconnection process that is too slow); Affected System 
Interconnection Customers Initial Comments at 2 (stating that 
Affected System Interconnection Customers have navigated the 
generator interconnection queues of various transmission providers 
around the country and experienced firsthand the inefficiencies and 
delays, which represent the greatest obstacle to achieving 
commercial operation of a new energy project); GSCE Initial Comments 
at 5-6 (contending that an average of 6,000 MW of new solar, wind, 
and batteries must be added each year until 2045 to reach 
California's electric sector carbon-neutrality requirement, but that 
over the past decade California has only succeeded with adding an 
average of 1,000 MW of utility-scale solar and 300 MW of wind to the 
transmission system each year).
    \113\ Order No. 845, 163 FERC ] 61,043 at P 24.
    \114\ Queued Up 2023 at 31; see also Shell Initial Comments at 6 
(describing multiple instances of five to six years until execution 
of an interconnection agreement, four years waiting for an initial 
``kick-off'' call, two years waiting for a feasibility study, three 
years waiting for a system impact study, and over two years waiting 
for a facilities study).
---------------------------------------------------------------------------

    40. Delays in the interconnection study process are an important 
contributor to interconnection queue backlogs nationwide. For instance, 
based on the recent interconnection study metrics transmission 
providers posted in compliance with Order No. 845, of the 2,179 
interconnection studies completed in 2022, 68% were issued late.\115\ 
Furthermore, at the end of 2022, an additional 2,544 studies were 
delayed (i.e., ongoing and past their deadline).\116\ All of the RTOs/
ISOs except CAISO and 14 non-RTO/ISO transmission providers reported 
delayed studies at the end of 2022.\117\
---------------------------------------------------------------------------

    \115\ This is based on data provided by transmission providers 
in compliance with Order No. 845. See appendix B to this final rule 
for the underlying data. Note that data from SPP is omitted here and 
in follow-on references to Order No. 845 data in this determination. 
This is because during 2022, SPP was transitioning to a new 
interconnection study process, and thus its data is not comparable 
to the other transmission providers.
    \116\ Id. Note that the vast majority of these studies (2,211) 
were in PJM.
    \117\ Id. CAISO revised the interconnection study deadlines of 
their queue cluster 14 to account for the unprecedented increase in 
interconnection requests. Cal. Indep. Sys. Operator Corp., 176 FERC 
] 61,207 (2021).
---------------------------------------------------------------------------

    41. Consistent with the NOPR, we find that numerous factors have 
contributed to the increasing volume of interconnection requests, 
including a rapidly changing resource mix, market forces, and emerging 
technologies. For example, the interconnection queues in all parts of 
the country are now predominantly made up of comparatively new 
technologies that have operating characteristics and generally shorter 
construction cycles that were not taken into account when the 
Commission issued Order No. 2003, such as solar, battery storage, and 
hybrid resources, as older, larger generating facilities retire.\118\ 
The Colorado Commission notes that solar projects account for roughly 
half of the cumulative requests in the five RTO/ISO queues and likely 
an even greater percentage of the most recent requests.\119\ In 
addition to the drastic increase in the number of interconnection 
requests in all regions of the country, evidence shows that 
interconnection studies have increased in complexity since the 
Commission issued Order No. 2003, potentially straining transmission 
provider resources.\120\ At the same time, we find that available 
transmission capacity has been largely or fully utilized in many 
regions, creating situations where interconnection customers face 
significant network upgrade cost assignments to interconnect their 
proposed generating facilities.\121\ For example, as referenced by the 
U.S. DOE, a recent report finds that interconnection costs in MISO 
doubled for generating facilities for which the interconnection studies 
were completed between 2019 and 2021 as compared to those completed 
prior to 2019, and cost estimates tripled for proposed generating 
facilities still active in the interconnection queue between the same 
time periods.\122\ These cost increases are similar to those being 
faced in NYISO and PJM, where interconnection costs, per kW, have 
doubled (or more) for recently completed generating facilities.\123\ As 
a result, we find that this combination of increased volume of diverse 
interconnection requests and insufficient transmission capacity leading 
to higher costs to interconnect, which can result in interconnection 
request withdrawals, has resulted in longer interconnection queue 
processing times and larger, more delayed interconnection queues.
---------------------------------------------------------------------------

    \118\ Queued Up 2023 at 9; see also Colorado Commission Comments 
at 9 (stating that the growth of solar project interconnection 
requests is a significant cause of the overall supply and demand 
imbalance across all RTOs/ISOs as well as other regions).
    \119\ Colorado Commission Initial Comments at 9.
    \120\ See, e.g., NYISO Initial Comments at 6-7 (stating that 
``[s]tudies are only becoming more complex with the expanding scope 
of ISO/RTOs' interconnection responsibilities''); Xcel Initial 
Comments at 7 (stating that ``in many cases study models with large 
clusters are difficult to solve . . . Ensuring new transmission 
lines are realistic and even validating substation designs and 
locations takes significant work to be done properly'').
    \121\ See, e.g., ACORE Initial Comments at 2 (noting that 
``upgrades based on generation interconnection may be a sub-optimal, 
expensive, and ultimately ineffective way to accomplish transmission 
expansion''); AEE Initial Comments at 3 (asserting that 
``inefficient and impeded interconnection processes lead to 
unacceptable delays and artificially high interconnection costs''); 
EDF Renewables Initial Comments at 3.
    \122\ Joachim Seel et al., Generator Interconnection Cost 
Analysis in the Midcontinent Independent System Operator (MISO) 
Territory, at 1, 4-5 (2022), <a href="https://emp.lbl.gov/interconnection_costs">https://emp.lbl.gov/interconnection_costs</a>.
    \123\ Julia Mulvaney Kemp et al., Interconnection Cost Analysis 
in the NYISO Territory (2023), <a href="https://emp.lbl.gov/publications/interconnection-cost-analysis-nyiso">https://emp.lbl.gov/publications/interconnection-cost-analysis-nyiso</a> (showing that costs have doubled 
for generating facilities studied since 2017, relative to costs for 
generating facilities studied from 2006 to 2016); Joachim Seel et 
al., Interconnection Cost Analysis in the PJM Territory (2023), 
<a href="https://emp.lbl.gov/publications/interconnection-cost-analysis-pjm">https://emp.lbl.gov/publications/interconnection-cost-analysis-pjm</a> 
(showing that costs for recent ``complete'' generating facilities 
have doubled on average relative to costs from 2000-2019).
---------------------------------------------------------------------------

    42. In response to comments asserting that the Commission did not 
take into account other factors affecting interconnection queue sizes, 
such as the development of smaller, more diverse generating facilities, 
in its preliminary findings on the need for reform in the NOPR,\124\ we 
find that the record shows that interconnection queue sizes are 
increasing in both number of interconnection requests and in total MW 
capacity in all regions of the country and such increases are not due 
to an influx of any particular size of proposed generating facility. 
Moreover, data show that the median duration for all generating 
facilities that enter the interconnection queue hovers around 30 
months, independent of the size of the interconnection request.\125\
---------------------------------------------------------------------------

    \124\ See, e.g., Pine Gate Reply Comments at 4 (stating that 
``the days of . . . large, conventional resources are waning as the 
majority of interconnection requests are now comprised of smaller, 
more diverse resource'' and that ``[l]arger interconnection queues 
are, to a certain extent, a natural byproduct of this change''); 
SEIA Reply Comments at 1 (contending that interconnection requests 
have increased in number ``because newer projects are smaller and 
have less capacity'' and ``[m]ore interconnection requests are 
needed to integrate the same amount of generation capacity into the 
grid'').
    \125\ Queued Up 2023 at 29.
---------------------------------------------------------------------------

    43. Interconnection queue backlogs and delays have created 
uncertainty for interconnection customers regarding the timing and cost 
of ultimately interconnecting to the transmission system. We agree with 
commenters that such uncertainty, on the part of both transmission 
provider and interconnection customer, may lead to an increase in costs 
to consumers.\126\ First, delayed interconnection study results or 
unexpected cost increases can disrupt numerous aspects of generating 
facility development.\127\ Cost

[[Page 61023]]

uncertainty poses an especially significant obstacle because 
interconnection customers may not be able to finance substantial 
increases in unexpected interconnection costs. Second, transmission 
providers may face uncertainty regarding the size and makeup of the 
interconnection queue and the commercial viability of the project in 
the interconnection queue, creating inefficiencies in the study 
process, increasing interconnection study costs, and delayed study 
results. Such uncertainty, either on the part of transmission providers 
or interconnection customers, are ultimately passed through to 
consumers through higher transmission or energy rates.\128\ Increases 
in energy rates may result from wholesale customers having limited 
access to new and more competitive supplies of generation. Conversely, 
efficient interconnection queues and well-functioning wholesale markets 
deliver benefits to consumers by driving down wholesale electricity 
costs.
---------------------------------------------------------------------------

    \126\ See, e.g., Ameren Initial Comments at 2; ELCON Initial 
Comments at 2; ELCON Initial Comments at 2; Xcel Initial Comments at 
8.
    \127\ See, e.g., Interwest Initial Comments at 8 (contending 
that ``[t]he harm to interconnection customers associated with 
interconnection study delays can be significant and costly, 
including liquidated damages if compliance with a commercial 
operation deadline is at risk'').
    \128\ Ameren Initial Comments at 2.
---------------------------------------------------------------------------

    44. As the interconnection queue backlogs and study delays continue 
and even increase, we find that the Commission's existing rules 
contained in the pro forma LGIP, pro forma LGIA, pro forma SGIP, and 
pro forma SGIA result in rates, terms, and conditions for Commission-
jurisdictional services that are unjust, unreasonable, and unduly 
discriminatory or preferential. Not only do the problems described 
above lead to an inability of interconnection customers to interconnect 
to the transmission system in a reliable, efficient, transparent, and 
timely manner, they also hinder the timely development of new 
generation, thereby stifling competition in the wholesale electric 
markets. We, therefore, find that reform to the Commission's existing 
pro forma generator interconnection procedures and agreements is 
necessary.
    45. Our findings that the existing pro forma LGIP, pro forma LGIA, 
pro forma SGIP, and pro forma SGIA must be reformed are based on the 
following features of these existing rules: (1) the information (or 
lack thereof) available to prospective interconnection customers and 
the commitments required of them to enter and progress through the 
interconnection queue; (2) the reliance on a serial first-come, first-
served study process and the ``reasonable efforts'' standard that 
transmission providers are held to for meeting interconnection study 
deadlines; (3) the protocols (or lack thereof) for affected system 
studies; (4) the provisions for studying new generating facility 
technologies and evaluating the list of alternative transmission 
technologies enumerated in this final rule; and (5) the modeling or 
performance requirements (or lack thereof) for non-synchronous 
generating facilities, including wind, solar, and electric storage 
facilities. We discuss each of these five features below.
    46. First, we find that existing pro forma generator 
interconnection procedures and agreements fail to contain a process by 
which an interconnection customer can obtain information about 
potential interconnection costs at a specific location or point of 
interconnection prior to submitting an interconnection request. Without 
this information, it is difficult for interconnection customers to 
assess the commercial viability of a specific proposed generating 
facility prior to entering the interconnection queue.\129\ Furthermore, 
we find that for interconnection customers, the pro forma 
interconnection procedures and agreements fail to include meaningful 
financial commitment requirements to enter and stay in the 
interconnection queue and lack of stringent requirements to establish 
the commercial viability of proposed generating facilities.\130\ As a 
result, interconnection customers often submit multiple interconnection 
requests for proposed generating facilities at various points of 
interconnection, knowing that not all of the proposed generating 
facilities will reach commercial operation, as an exploratory mechanism 
to obtain information to allow the interconnection customer to choose 
to proceed with the interconnection request representing the most 
favorable site in terms of potential interconnection-related 
costs.\131\ For instance, recent interconnection study metrics posted 
by transmission providers continue to show that some interconnection 
customers are withdrawing interconnection requests before any studies 
are completed.\132\ While interconnection customers may withdraw at any 
stage of the interconnection process, to do so before any study is 
completed indicates that interconnection customers may lack information 
prior to entering the interconnection queue and are entering to obtain 
valuable information about the commercial viability of their proposed 
projects vis-[agrave]-vis other interconnection customers in the queue 
or cluster.
---------------------------------------------------------------------------

    \129\ See, e.g., Fervo Energy Initial Comments at 2-3 (stating 
that ``the incidence of interconnection applications simply intended 
to solicit information discovery from the transmission provider . . 
. is a significant defect in today's queue process''); Google 
Initial Comments at 4 (asserting that ``there is extreme information 
asymmetry in the interconnection process,'' with transmission owners 
and their affiliates having greater access than independent power 
producers to information on the relative cost of interconnection at 
different points).
    \130\ See, e.g., Dominion Initial Comments at 4 (stating that 
``owners of speculative projects remain in the queue process for as 
long as they possibly can in the hopes that their project somehow 
becomes viable''); U.S. Chamber of Commerce Initial Comments at 5 
(concurring with the NOPR that there is a ``lack of stringent 
financial commitments and readiness requirements on interconnection 
customers'').
    \131\ See, e.g., Clean Energy Associations Initial Comments at 
11 (stating that ``[i]n most cases, customers must actually enter 
the queue to ascertain what upgrade costs they will be responsible 
for''); Clean Energy Buyers Initial Comments at 3 (stating that 
inefficiencies in the serial study queue are ``compounded by 
exploratory interconnection requests that are based on developers' 
attempts to obtain locations with available transmission 
capacity''); NY Commission and NYSERDA Initial Comments at 6-7 
(stating that ``increased access to valuable information . . . could 
deter developers from submitting multiple, speculative 
[interconnection requests]'').
    \132\ Based on data provided by transmission providers in 
compliance with Order No. 845 (showing that 35% of withdrawals in 
2022 took place before any studies had been completed). See appendix 
B to this final rule for the underlying data.
---------------------------------------------------------------------------

    47. Second, the existing serial first-come, first-served study 
process in the pro forma LGIP requires transmission providers to 
process interconnection requests in the order in which the transmission 
provider receives them. This approach creates incentives for 
interconnection customers to submit exploratory or speculative 
interconnection requests pursuant to which interconnection customers 
seek to secure valuable queue positions as early as possible, even if 
they are not prepared to move forward with the proposed generating 
facility. Such generating facilities are often not commercially viable 
and, thus, the interconnection customers ultimately withdraw from the 
interconnection queue. We agree with commenters that the withdrawal of 
speculative interconnection requests that trigger reassessments and 
possible restudies by the transmission provider can delay the timing 
and increase the cost to interconnect for lower-queued interconnection 
requests.
    48. In summary, we find that the lack of (1) access of information 
about a specific location or point of interconnection prior to 
submitting an interconnection request and (2) meaningful financial 
commitments in the pro forma interconnection procedures and agreements 
for interconnection customers to enter and stay in the interconnection 
queue, as well as the existing serial first-come,

[[Page 61024]]

first-served study process, all incentivize interconnection customers 
to submit speculative interconnection requests that contribute to 
interconnection study backlogs, delays, and uncertainty, and, in turn, 
unjust and unreasonable Commission-jurisdictional rates.
    49. We disagree with commenters' assertions that there is no basis 
to find that speculative interconnection requests are responsible for 
interconnection queue backlog and delays. We highlight that more than 
70% of interconnection requests were withdrawn from the interconnection 
queue between 2000 and 2017.\133\ Although we recognize that there are 
various reasons an interconnection customer may withdraw its request 
from the interconnection queue, a withdrawal indicates an inability to 
reach commercial operation. Because a withdrawal can trigger costly 
restudies and create uncertainty in the interconnection process for 
interconnection customers and transmission providers alike, withdrawals 
of commercially non-viable interconnection requests from the 
interconnection queue is a significant contributing factor to 
interconnection queue backlogs and delays.\134\ Late-stage withdrawals 
of interconnection requests are also increasing.\135\ Late-stage 
withdrawals present a significant problem, as they can trigger 
restudies for other interconnection customers that can result in 
significant increases to the interconnection costs attributed to those 
customers and the timeline for completion of interconnection studies, 
which can result in further late-stage withdrawals, thus exacerbating 
the interconnection queue backlogs and delays.\136\
---------------------------------------------------------------------------

    \133\ Queued Up 2023 at 18 (reporting that 72% of all 
interconnection requests submitted from 2000-2017 were withdrawn).
    \134\ See, e.g., Ohio Commission Consumer Advocate Initial 
Comments at 8 (stating that ``[e]ach withdrawn project entails PJM 
restudy on lower-queued projects, which delays the processing of new 
service queues and may have the consequence of a cascade of 
withdrawals'').
    \135\ Queued Up 2023 at 22.
    \136\ See, e.g., AEE Initial Comments at 4-5; Queued Up 2023 at 
22.
---------------------------------------------------------------------------

    50. We also find that interconnection queue backlogs and delays, 
and the accompanying uncertainty, are further compounded because 
transmission providers have limited incentive to perform 
interconnection studies in a timely manner. Under the pro forma LGIP, 
transmission providers are held to a ``reasonable efforts'' standard in 
completing interconnection studies consistent with their tariff-imposed 
deadlines. However, this standard offers significant discretion to the 
transmission providers in extending their own deadlines. The record 
demonstrates that a majority of transmission providers across the 
country regularly fail to meet interconnection study deadlines.\137\ 
Despite pervasive delays in completing interconnection studies by 
transmission providers, we acknowledge that transmission providers have 
faced few, if any, consequences for failing to meet their tariff-
imposed study deadlines under the reasonable efforts standard.\138\ 
This outcome stands in stark contrast to interconnection customers that 
face financial and commercial consequences due to late interconnection 
study results and may be considered withdrawn from the interconnection 
queue for failing to meet their tariff-imposed deadlines.\139\ For 
these reasons, we find that the existing pro forma LGIP requirement for 
transmission providers to make a reasonable effort to meet 
interconnection study deadlines contributes to the interconnection 
study backlogs, delays, and uncertainty that erects barriers to new 
generation.\140\ Therefore, we find that the use of a reasonable 
efforts standard in the existing pro forma LGIP results in Commission-
jurisdictional rates that are unjust and unreasonable.
---------------------------------------------------------------------------

    \137\ For example, based on data submitted by transmission 
providers in compliance with Order No. 845, 80% of transmission 
providers had delayed studies in at least one of the past three 
years (2020-2022) and 57% had delayed studies in at least two.b See 
also NARUC Initial Comments at 13 (stating ``nearly all transmission 
providers across the country, including many transmission providers 
that have implemented queue reforms, regularly fail to meet 
interconnection study deadlines'').
    \138\ See, e.g., Clean Energy Associations Initial Comments at 
43-44 (stating that ``[a]t present, there is no specific incentive 
for delivering on-time and accurate studies, and late or inaccurate 
studies bring few if any consequences'').
    \139\ See, e.g., ACE-NY Initial Comments at 3 (``Project 
developers have strict deadlines they must adhere to in the 
interconnection process, with penalties that include the forced 
withdrawal of the project from the queue.'').
    \140\ See, e.g., NARUC Initial Comments at 13-14 (contending 
that ``the tendency to miss deadlines introduces uncertainty in a 
process that is important to bringing new generation online in a 
timely and cost-effective manner'').
---------------------------------------------------------------------------

    51. Third, the pro forma LGIP includes no requirements regarding 
how or when transmission providers should complete affected system 
studies. Without requirements, affected system studies often lag behind 
those completed by the transmission provider to whose transmission 
system the interconnection customer proposes to interconnect (the so-
called host transmission provider) and are sometimes completed very 
late in the interconnection process, causing an additional round of 
delays and cost uncertainty for interconnection customers.\141\ 
Additionally, for transmission providers that have procedures for how 
to complete affected system studies in their tariffs or other documents 
(e.g., business practice manuals or joint operating agreements), the 
procedures are not consistent, may be hard for interconnection 
customers to locate, and may not represent the actual practices in use 
by the transmission provider, thus still creating uncertainty for 
interconnection customers. As a result, we find that the lack of 
consistent requirements for affected system modeling and procedures 
results in Commission-jurisdictional rates that are unjust, 
unreasonable, and unduly discriminatory or preferential.
---------------------------------------------------------------------------

    \141\ See, e.g., MISO Initial Comments at 72 (stating that ``the 
need to wait for affected systems studies is the cause of the 
majority of delays in the MISO study process''); May Joint Task 
Force Tr. 65:2-8 (Dan Scripps) (citing affected systems studies as 
``a growing source of delay and cost uncertainty for interconnection 
customers, both in terms of just the timelines involved and the 
difficulty in pinning those down'').
---------------------------------------------------------------------------

    52. Fourth, we find that the Commission's pro forma LGIP fails to 
accommodate the operating characteristics and technical capabilities of 
electric storage resources when it comes to specific interconnection 
procedures and modeling. As stated above, the interconnection queues 
predominantly consist of new technologies which have operating 
characteristics that differ from synchronous resources and were not 
anticipated when the Commission established the pro forma generator 
interconnection procedures and agreements in Order Nos. 2003 and 2006. 
Specifically, electric storage resources can be charged and dispatched 
on a flexible, as-available basis, and are less likely than synchronous 
generating facilities to withdraw energy from the transmission system 
during peak load conditions or discharge during light load 
conditions.\142\ However, the existing pro forma generator 
interconnection procedures and agreements do not contemplate these 
operating characteristics or technical capabilities of electric storage 
resources. As a result, we find that electric storage resources

[[Page 61025]]

(whether standalone, co-located generating facilities, or part of a 
hybrid generating facility), may be studied under inappropriate 
operating assumptions (e.g., charging at full capacity during peak load 
conditions) that result in assigning unnecessary network upgrades and 
increased costs to interconnection customers. Therefore, we find that 
the Commission's pro forma LGIP's lack of ability to modify operating 
assumptions for electric storage resources results in Commission-
jurisdictional rates that are unjust, unreasonable, and unduly 
discriminatory or preferential.
---------------------------------------------------------------------------

    \142\ See, e.g., Bonneville Initial Comments at 22-23 (stating 
that ``storage resources are less likely to charge during peak load 
conditions or discharge during light load conditions, and . . . 
those considerations can be factored into assumptions used in 
interconnection studies''); NARUC Initial Comments at 37 (stating 
that ``assuming that an energy storage device will withdraw energy 
during peak demand . . . fails to recognize that those resources are 
likely to be highly responsive to price signals from the 
transmission provider and can improve reliability'').
---------------------------------------------------------------------------

    53. Additionally, the record supports a finding that the existing 
pro forma interconnection procedures regarding material modifications 
do not provide for consistent evaluation of technology additions to an 
existing interconnection request.\143\ We find that the record 
demonstrates that automatically deeming a request to add a generating 
facility to an existing interconnection request to be a material 
modification creates a significant barrier to access to the 
transmission system.\144\ As a result, we find the existing pro forma 
LGIP and pro forma LGIA results in Commission-jurisdictional rates that 
are unjust and unreasonable.
---------------------------------------------------------------------------

    \143\ See, e.g., NARUC Initial Comments at 35 (stating that the 
``loss of queue position as a result of adding a generating facility 
that does not increase the requested service level or cause 
reliability issues . . . is an inefficient and discriminatory 
outcome'').
    \144\ See, e.g., AEE Initial Comments at 40-41; Public Interest 
Organizations Initial Comments at 45-47; SEIA Initial Comments at 
38-39.
---------------------------------------------------------------------------

    54. Finally, the record supports a finding that the Commission's 
pro forma LGIP and pro forma SGIP fail to require the consideration of 
alternative transmission technologies that can be deployed more quickly 
to be used as network upgrades in place of, and at a lower cost than, 
traditional network upgrades.\145\ In addition, commenters contend that 
some alternative transmission technologies could provide substantial 
benefits by resolving thermal overloads and avoiding voltage collapse, 
allowing for better use of the existing transmission system, improving 
reliability, and reducing interconnection request withdrawals, 
restudies, and overall interconnection delays.\146\ We find that 
failing to require transmission providers to evaluate the list of 
alternative transmission technologies enumerated in this final rule 
results in interconnection customers paying more than is just and 
reasonable to reliably interconnect new generating facilities, 
resulting in Commission-jurisdictional rates that are unjust, 
unreasonable, and unduly discriminatory or preferential. Because the 
benefits of the enumerated alternative transmission technologies 
identified above are present across all interconnection processes, 
regardless of the size of the interconnection request, we find that the 
failure to evaluate the enumerated alternative transmission 
technologies results in both the pro forma LGIP and pro forma SGIP 
being unjust, unreasonable, and unduly discriminatory or preferential.
---------------------------------------------------------------------------

    \145\ See, e.g., NARUC Initial Comments at 38 (stating that 
``failing to consider alternative transmission technologies that can 
be deployed both more quickly and at lower costs than network 
upgrades may render Commission-jurisdictional rates unjust and 
unreasonable''); OMS Initial Comments at 19 (agreeing that ``failing 
to consider these alternative transmission technologies runs the 
risk of implementing longer lead-time network upgrades at a higher 
cost'').
    \146\ See, e.g., AEE Initial Comments at 42 (stating that 
alternative transmission technologies ``provide benefits beyond 
potential costs savings, including maximizing limited rights-of-way 
and potentially avooiding or minimizing environmental and property 
impacts taht can bog down siting and permitting proceedings''); Ohio 
Commission Consumer Advocate Initial Comments at 15 (stating that 
``[t]hese grid-enhancing technologies (`GETs') can improve 
opertations, enhance system reliability, contribute to capacity, and 
more'' and ``[s]ome [grid-enhancing technologies] could provide 
substantial benefits by resolving thermal overloads and avoiding 
voltage collapse, among other things''); WATT Coalition Initial 
Comments at 2 (referring to the report Unlocking the Queue with Grid 
Enhancing Technologies that showed that application of the three 
grid-enhancing technologies in the Kansas and Oklahoma transmission 
systems would enable twice as much renewable energy to interconnect 
out of the queues without any traditional transmission upgrades.).
---------------------------------------------------------------------------

    55. Fifth, we find that the Commission's existing pro forma LGIP 
and pro forma SGIP do not include a modeling requirement for non-
synchronous generating facilities, which is necessary to enable the 
transmission provider to assess and model the facility's ability to 
respond appropriately to transmission system disturbances. These 
modeling requirements include: (1) a validated, user-defined root mean 
square (RMS) positive sequence dynamic model; (2) an appropriately 
parameterized, generic library RMS positive sequence dynamic model; and 
(3) a validated electromagnetic transient (EMT) model, if the 
transmission provider performs an EMT study as part of the 
interconnection study process. Additionally, we find that accurate and 
validated models are necessary to address study delays and to ensure 
that transmission providers identify the necessary interconnection 
facilities and network upgrades to accommodate the interconnection 
request and appropriate assignment of interconnection costs. As a 
result, we find that the lack of a modeling requirement for non-
synchronous generating facilities in the pro forma LGIP and pro forma 
SGIP results in rates that are unjust, unreasonable, and unduly 
discriminatory or preferential.
    56. Furthermore, the physical characteristics of synchronous 
generating facilities allow them to continue to inject electric current 
during transmission system disturbances, as required by the pro forma 
LGIA and pro forma SGIA.\147\ However, non-synchronous generating 
facilities do not face a comparable requirement and many cease 
injecting current through ``momentary cessation,'' which creates 
reliability issues on the transmission system.\148\ Moreover, without 
requirements for non-synchronous generating facilities to remain 
connected to and synchronized with the transmission system, 
interconnection studies may not accurately model expected behavior and 
identify the appropriate interconnection facilities and network 
upgrades to accommodate the interconnection request, skewing the 
assignment of interconnection costs. As a result, we find that the lack 
of comparable requirements for non-synchronous generating facilities to 
remain ``connected to and synchronized with the [t]ransmission 
[s]ystem'' in the pro forma LGIA and pro forma SGIA results in rates 
that are unjust, unreasonable, and unduly discriminatory or 
preferential.
---------------------------------------------------------------------------

    \147\ Pro forma LGIA art. 9.7.3 and pro forma SGIA art. 1.5.7 
require synchronous generating facilities to remain ``connected to 
and synchronized with'' the transmission system during system 
disturbances.
    \148\ See, e.g., NERC Initial Comments at 9 (stating that 
``improper planning and operation of [non-synchronous resources] can 
pose a significant risk to . . . reliability'' and adding that 
``risk mitigation measures . . . have been inconsistently adopted by 
industry''); MISO TOs Initial Comments at 32-33 (concurring with the 
Commission that ``with more and more non-synchronous generation 
facilities entering the interconnection queue, the lack of a 
requirement for such resources to respond to system disturbances 
becomes `more consequential' '').
---------------------------------------------------------------------------

    57. In response to commenters that express broad opposition to the 
need for reform, we disagree with assertions that the existence of 
regional variation in interconnection procedures across the country 
creates an insufficient legal foundation under FPA section 206 to 
demonstrate that rates are unjust, unreasonable, and unduly 
discriminatory or preferential. Similarly, we disagree with assertions 
that reforms to the pro forma generator interconnection procedures and 
agreements are arbitrary and capricious because the problems identified 
herein do not exist uniformly. As an initial matter, the ``Commission 
may rely on `generic' or `general' findings of a systemic problem to 
support imposition

[[Page 61026]]

of an industry-wide solution.'' \149\ That some interconnection 
processes may fare better in the face of industry-wide challenges would 
be ``as unastonishing as it is irrelevant.'' \150\ The Commission may 
reasonably rely on rulemaking to address the systemic drivers leading 
to widespread interconnection queue backlogs and delays, 
notwithstanding regional variation among interconnection procedures.
---------------------------------------------------------------------------

    \149\ S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 67 (D.C. Cir. 
2014) (quoting Interstate Nat. Gas Ass'n of Am. v. FERC, 285 F.3d 
18, 37 (2002)).
    \150\ Id. (quoting Wis. Gas v. FERC, 770 F.2d 1144, 1157 (D.C. 
Cir. 1985)).
---------------------------------------------------------------------------

    58. Moreover, as noted above, every region of the country is seeing 
an increase in both interconnection queue size and the length of time 
interconnection customers are spending in the interconnection queue 
prior to commercial operation in recent years.\151\ Furthermore, the 
uncertainty and delays in the interconnection queues have resulted in 
fewer than 25% of interconnection requests, by capacity, reaching 
commercial operation between 2000 and 2017 in any region of the 
country--with some regions as low as 8%.\152\ For example, only 10% of 
interconnection requests, by capacity, have reached commercial 
operation in the non-RTO/ISO southeast region between 2000 and 
2017.\153\ Additionally, the challenges being faced across the country 
will be further compounded in the future given the recent spikes in 
interconnection queue sizes. In the non-RTO/ISO southeast region, the 
interconnection queue size has more than tripled between 2014 and 2022, 
with the increase predominantly made up of solar, storage, and hybrid 
generating facilities, adding potential complexity to future 
interconnection queue study processes.\154\ To the extent existing pro 
forma interconnection procedures, such as first-come, first-served 
study processes, have worked in the past for smaller or less complex 
queues, such experience is not indicative of what will be necessary in 
the future to ensure that a growing number of interconnection requests 
are processed in a reliable, efficient, transparent, and timely 
manner.\155\ Finally, as recognized in Order No. 2003, interconnection 
queue delays may ``provide[] an unfair advantage to utilities that own 
both transmission and generation facilities,'' \156\ making it 
exceedingly necessary that interconnection delays are addressed in all 
regions of the country, especially those where transmission providers 
continue to own both transmission and generation.\157\ As discussed 
above, because interconnection queue backlogs and delays afflict 
generator interconnection service nationwide, which hinders the timely 
development of new generation and thereby stifles competition in the 
wholesale electric markets, reforms are necessary to ensure Commission-
jurisdictional rates are just, reasonable, and not unduly 
discriminatory or preferential.
---------------------------------------------------------------------------

    \151\ Queued Up 2023 at 9, 32.
    \152\ Id. at 3, 21.
    \153\ Id. at 21.
    \154\ Id. at 9.
    \155\ See, e.g., Public Interest Organization Initial Comments 
at 17; R Street Initial Comments at 3.
    \156\ Order No. 2003, 104 FERC ] 61,103 at P 11.
    \157\ See, e.g., Pine Gate Initial Comments at 15; AEE Reply 
Comments at 22.
---------------------------------------------------------------------------

    59. We are not persuaded by commenters' concerns that the reforms 
proposed in the NOPR, many of which we adopt in this final rule, will 
be counterproductive in addressing the need for reform. As discussed in 
more detail throughout this final rule, we believe that the reforms 
adopted herein, as a whole, will improve the efficiency of study 
processes, reduce interconnection queue backlogs, and thereby ensure 
just, reasonable, and not unduly discriminatory or preferential rates. 
We believe that, on balance, the reforms will produce efficiencies by, 
for example, reducing speculative interconnection requests and 
interconnection request withdrawals, which in turn will reduce the time 
and resources spent in interconnection studies and restudies thereby 
decreasing interconnection queue backlogs and delays. Additionally, the 
majority of the individual reforms that the Commission proposed in the 
NOPR and we adopt in this final rule have already been implemented in 
one or more regions in order to improve the interconnection process, 
demonstrating incremental improvements. This final rule uses some of 
these individual and incremental improvements as a basis for a broad 
suite of reforms that, in their entirety, have not yet been adopted by 
any region and we believe will ensure that interconnection customers 
are able to interconnect to the transmission system in a reliable, 
efficient, transparent, and timely manner. In some cases, such as for 
the commercial readiness reforms adopted in this final rule, we have 
significantly modified the NOPR proposal based on comments received.
    60. Having concluded that the existing pro forma generator 
interconnection procedures and agreements are unjust, unreasonable, and 
unduly discriminatory or preferential, we turn, as we are required to 
do under FPA section 206,\158\ to determining the replacement rate, 
described--at some length--below.
---------------------------------------------------------------------------

    \158\ 16 U.S.C. 824e(a); see, e.g., FERC v. Electric Power 
Supply Ass'n, 577 US 260, 277 (2016) (``If FERC sees a violation of 
[the just and reasonable] standard, it must take remedial action.'')
---------------------------------------------------------------------------

III. Reforms

A. Reforms To Implement a First-Ready, First-Served Cluster Study 
Process

1. Interconnection Information Access
a. Need for Reform
i. NOPR
    61. The Commission noted its concern regarding the lack of 
information available to prospective interconnection customers 
regarding potential interconnection costs prior to submitting an 
interconnection request.\159\ The Commission stated that, without this 
information, it is difficult for interconnection customers to assess 
the viability of a specific proposed generating facility. Subsequently, 
interconnection customers submit multiple speculative interconnection 
requests in an attempt to obtain information through the system impact 
study process about the costs associated with various project 
configurations. The Commission preliminarily found that the 
Commission's pro forma LGIP and pro forma LGIA are unjust, 
unreasonable, and unduly discriminatory or preferential and that 
reforms are needed to allow interconnection customers to interconnect 
in a reliable, efficient, transparent, and timely manner, thereby 
ensuring that rates, terms, and conditions for Commission-
jurisdictional services are just, reasonable, and not unduly 
discriminatory or preferential.\160\
---------------------------------------------------------------------------

    \159\ NOPR, 179 FERC ] 61,194 at P 40.
    \160\ Id. P 39.
---------------------------------------------------------------------------

ii. Comments
    62. Several commenters contend that it is a rational response to a 
lack of pre-interconnection queue information for interconnection 
customers to submit multiple interconnection requests to gain 
information on which interconnection sites are favorable and hedge 
risks, which leads to withdrawals that exacerbate unmanageable 
interconnection queue backlogs.\161\ ELCON and Environmental Defense

[[Page 61027]]

Fund argue that the lack of sufficient information and unexpected cost 
escalation are the primary reasons interconnection requests are 
withdrawn, leading to delays and inefficiencies.\162\
---------------------------------------------------------------------------

    \161\ AES Initial Comments at 3; Affected Interconnection 
Customers Initial Comments at 30; Clean Energy Buyers Initial 
Comments at 5-6; CREA and NewSun Initial Comments at 45; 
Environmental Defense Fund Initial Comments at 3; ELCON Initial 
Comments at 3; Northwest and Intermountain Initial Comments at 5; 
Public Interest Organizations Initial Comments at 18.
    \162\ Environmental Defense Fund Initial Comments at 3; ELCON 
Initial Comments at 4.
---------------------------------------------------------------------------

    63. Many commenters agree with the goal of providing additional 
information prior to entering the interconnection queue.\163\ Some 
commenters state that additional information prior to entering the 
interconnection queue is beneficial,\164\ in particular access to 
information on potential network upgrades and the cost and time to 
interconnect.\165\ Many commenters expect that potential 
interconnection customers' access to additional information prior to 
entering the interconnection queue will reduce speculative 
interconnection requests, thus promoting reliability and cost savings 
by encouraging more optimal interconnection requests that can be 
processed more efficiently and at lower overall cost.\166\
---------------------------------------------------------------------------

    \163\ ACORE Reply Comments at 3; AEE Initial Comments at 9; AEP 
Initial Comments at 12; AES Initial Comments at 3; Affected 
Interconnection Customers Initial Comments at 30; APS Initial 
Comments at 4; Bonneville Initial Comments at 5; Clean Energy Buyers 
Initial Comments at 7; CREA and NewSun Initial Comments at 44; ELCON 
Initial Comments at 3-4; Enel Initial Comments at 9; Google Initial 
Comments at 15; MISO Initial Comments at 20-21; NARUC Initial 
Comments at 4; NESCOE Reply Comments at 2-3; NY Commission and 
NYSERDA Initial Comments at 6-8; NYISO Initial Comments at 16; NYTOs 
Initial Comments at 8; Pacific Northwest Utilities Initial Comments 
at 13; PJM Initial Comments at 45; Puget Sound Initial Comments at 
5; WAPA Initial Comments at 5.
    \164\ AEP Initial Comments at 12; APS Initial Comments at 4.
    \165\ EEI Reply Comments at 7-8; New Jersey Commission Initial 
Comments at 23; NV Energy Initial Comments at 13.
    \166\ Affected Interconnection Customers Initial Comments at 30; 
Clean Energy States Initial Comments at 3; Duke Southeast Utilities 
Initial Comments at 6; Environmental Defense Fund Initial Comments 
at 3; ELCON Initial Comments at 3-4; Fervo Energy Initial Comments 
at 2-3; Google Initial Comments at 4-5; NARUC Initial Comments at 4-
5; NESCOE Reply Comments at 3; New Jersey Commission Initial 
Comments at 20-22; New York State Department Initial Comments at 8; 
Pacific Northwest Utilities Initial Comments at 13; Public Interest 
Organizations Initial Comments at 18; Puget Sound Initial Comments 
at 5; SDG&E Initial Comments at 3-4.
---------------------------------------------------------------------------

    64. Several commenters note the importance of additional 
interconnection information access in light of the other reforms 
proposed in the NOPR. AES contends that it would be inequitable for the 
Commission to increase security deposits to stay in the interconnection 
queue under the NOPR proposal to increase study and LGIA deposits 
without requiring transmission providers to provide sufficient 
information to interconnection customers.\167\ Vistra asserts that the 
proposals to provide additional information will complement the 
exclusive site control proposals and provide an avenue for prospective 
interconnection customers to select the most viable sites on which to 
obtain rights and develop a location, which is a costly and time-
consuming process, before entering the interconnection queue.\168\ 
Northwest and Intermountain argue that, in order for the other proposed 
reforms in the NOPR to be effective, potential interconnection 
customers must have a solution to the problem of identifying optimal 
interconnection locations and configurations that is timely, cost-
effective, and accurate.\169\
---------------------------------------------------------------------------

    \167\ AES Initial Comments at 13.
    \168\ Vistra Initial Comments at 4.
    \169\ Northwest and Intermountain Initial Comments at 9.
---------------------------------------------------------------------------

    65. Google contends that pre-queue information is necessary because 
there is an extreme information asymmetry between independent power 
producers and transmission owners and their generating affiliates, 
which have greater access to planning information, including load 
growth, relative cost of interconnecting at different points, points of 
chronic congestion where upgrades might be needed, and planned local 
upgrades.\170\ Google asserts that this information asymmetry is 
particularly pronounced in the non-RTO/ISO regions, and allows 
transmission owners and their affiliates to identify the best locations 
for interconnection more quickly than independent power producers.
---------------------------------------------------------------------------

    \170\ Google Initial Comments at 3-4.
---------------------------------------------------------------------------

    66. On the other hand, Dominion argues that there is no evidence in 
the record that a lack of information is slowing down the 
interconnection queue process or that transmission providers are not 
engaged in good faith reviews of interconnection requests.\171\ 
According to Dominion, the Commission should focus on making the 
interconnection process more efficient and speedier, and the best way 
to achieve these goals is through the first-ready, first-served cluster 
study reform. While APPA-LPPC support transparency in the generator 
interconnection process and share the Commission's view that the 
availability of transmission system information should reduce the 
incentive to submit speculative interconnection requests, they argue 
that sufficient information is currently publicly available.\172\
---------------------------------------------------------------------------

    \171\ Dominion Reply Comments at 8-9.
    \172\ APPA-LPPC Initial Comments at 11.
---------------------------------------------------------------------------

iii. Commission Determination
    67. We find that, absent reforms to require transmission providers 
to provide additional interconnection information, which can be used by 
interconnection customers prior to submitting an interconnection 
request, speculative interconnection requests will likely remain at 
current levels and continue to contribute to interconnection study 
delays and add costs to the interconnection process. Although 
submitting multiple interconnection requests to gain information may be 
a rational response to a lack of pre-interconnection queue information, 
this practice increases interconnection study delays.\173\ We also 
agree with commenters that additional access to interconnection 
information is a valuable goal \174\ as it can increase the likelihood 
that an interconnection request is viable when submitted. We disagree 
with commenters that current information requirements are 
sufficient.\175\ While certain information is currently available 
through the feasibility study process, as part of our reforms discussed 
below, we eliminate the feasibility study. Therefore, we find it 
necessary to provide a means for interconnection customers to obtain 
additional information prior to entering the interconnection queue. We 
concur with comments that additional access to interconnection 
information prior to entering the interconnection queue is important 
for interconnection customers to make informed decisions, particularly 
given the increased requirements for interconnection customers adopted 
in this final rule, such as increased study deposits and site control, 
as discussed

[[Page 61028]]

below.\176\ We also agree that commenters raise a valid concern that an 
information asymmetry exists between independent power producers and 
transmission owner affiliates, in particular in non-RTO/ISO 
regions.\177\
---------------------------------------------------------------------------

    \173\ See AES Initial Comments at 3; Affected Interconnection 
Customers Initial Comments at 30; Clean Energy Buyers Initial 
Comments at 5-6; CREA and NewSun Initial Comments at 45; 
Enviornmental Defense Fund Initial Comments at 3; ELCON Initial 
Comments at 3; Northwest and Intermountain Initial Comments at 5; 
Public Interest Organizations Initial Comments at 18.
    \174\ ACORE Reply Comments at 3; AEE Initial Comments at 9; AEP 
Initial Comments at 12; AES Initial Comments at 3; Affected 
Interconnection Customers Initial Comments at 30; APS Initial 
Comments at 4; Bonneville Initial Comments at 5; Clean Energy Buyers 
Initial Comments at 7; CREA and NewSun Initial Comments at 44; ELCON 
Initial Comments at 3-4; Enel Initial Comments at 9; Google Initial 
Comments at 15; MISO Initial Comments at 20-21; NARUC Initial 
Comments at 4; NESCOE Reply Comments at 2-3; NY Commission and 
NYSERDA Initial Comments at 6-8; NYISO Initial Comments at 16; NYTOs 
Initial Comments at 8; Pacific Northwest Utilities Initial
    Comments at 13; PJM Initial Comments at 45; Puget Sound Initial 
Comments at 5; WAPA Initial Comments at 5.
    \175\ APPA-LPPC Initial Comments at 9.
    \176\ AES Initial Comments at 13; Northwest and Intermountain 
Initial Comments at 9; Vistra Initial Comments at 4.
    \177\ Google Initial Comments at 3-5.
---------------------------------------------------------------------------

b. Informational Interconnection Study
i. NOPR Proposal
    68. In the NOPR, the Commission proposed to revise the Commission's 
pro forma LGIP to require transmission providers to offer an 
informational interconnection study for prospective interconnection 
customers.\178\ The Commission proposed that the informational 
interconnection study would provide cost estimates for the transmission 
provider's interconnection facilities and network upgrade costs 
specific to the interconnection scenario detailed in the study 
agreement. The Commission also proposed to include new definitions for 
an informational interconnection study and informational 
interconnection study agreement.
---------------------------------------------------------------------------

    \178\ NOPR, 179 FERC ] 61,194 at P 42.
---------------------------------------------------------------------------

    69. Under the Commission's proposal, prospective interconnection 
customers could request up to five separate informational 
interconnection studies at a time.\179\ The Commission explained that 
each configuration of an interconnection request would require a 
separate informational interconnection study. The Commission proposed 
that the informational interconnection study would be at the 
interconnection customer's expense, and each study would require a 
$10,000 deposit, subject to a true-up based on actual study costs.
---------------------------------------------------------------------------

    \179\ Id. P 43.
---------------------------------------------------------------------------

    70. The Commission proposed that, within seven business days of the 
receipt of a prospective interconnection customer's request for an 
informational interconnection study, the transmission provider would 
have to provide the prospective interconnection customer with an 
informational interconnection study agreement.\180\ The Commission 
explained that the informational interconnection study agreement would 
specify the technical data that the prospective interconnection 
customer must provide and an estimate of the expected costs of the 
study, including, to the extent known by the transmission provider, an 
estimate of the study costs expected to be incurred by any relevant 
affected systems. Under the proposal, the prospective interconnection 
customer would have 10 business days to execute the agreement and 
deliver it to the transmission provider, along with the relevant 
technical data and study deposit, after which the transmission provider 
would have 45 calendar days to complete the study.
---------------------------------------------------------------------------

    \180\ Id. P 44.
---------------------------------------------------------------------------

    71. The Commission proposed that the informational interconnection 
study would consist of a sensitivity analysis based on the assumptions 
specified in the informational interconnection study agreement.\181\ 
Under the proposal, the informational interconnection study would 
identify potential interconnection facilities and network upgrades that 
may be required to interconnect the prospective interconnection 
customer's proposed generating facility, including an approximation of 
the costs of such interconnection facilities and network upgrades. The 
Commission noted that the transmission provider would also coordinate 
with affected systems that may be impacted by the prospective 
interconnection customer's request to provide information on affected 
systems-related issues.
---------------------------------------------------------------------------

    \181\ Id. P 45.
---------------------------------------------------------------------------

    72. The Commission proposed an informational interconnection study 
agreement form, which explains that the informational interconnection 
study is performed solely for informational purposes and is not binding 
on either party.\182\ The proposed agreement also requires the study 
report to provide specific information, including, at a minimum: (1) 
preliminary identification of any circuit breaker short circuit 
capability limits exceeded; (2) preliminary identification of any 
thermal overload or voltage limit violations; and (3) estimated network 
upgrade costs related to the identified overloads and violations.
---------------------------------------------------------------------------

    \182\ Id. P 46.
---------------------------------------------------------------------------

    73. The Commission sought comment on: (1) whether the informational 
interconnection study, as proposed, would provide prospective 
interconnection customers with sufficient and timely information to 
inform decision-making prior to submitting an interconnection request; 
(2) whether transmission providers should be required to establish a 
request window of a limited number of days each year in which potential 
interconnection customers can request an optional informational 
interconnection study; and (3) the burdens on transmission providers of 
conducting informational studies and whether other options, such as the 
proposal discussed below for public interconnection information, might 
strike a better balance of providing interconnection customers with 
useful information while making efficient use of transmission provider 
resources.\183\
---------------------------------------------------------------------------

    \183\ Id. PP 47-48.
---------------------------------------------------------------------------

    74. Additionally, the Commission proposed to add new section 3.1.2 
to the pro forma LGIP, which provides that interconnection customers 
evaluating different options (such as different sizes, sites, or 
voltages) are encouraged but not required to use the new informational 
interconnection study proposed in the NOPR before entering the cluster 
study.\184\
---------------------------------------------------------------------------

    \184\ Id. P 66.
---------------------------------------------------------------------------

ii. Comments
(a) Comments in Support
    75. Several commenters support the NOPR proposal to require 
transmission providers to offer an informational interconnection study 
to prospective interconnection customers.\185\ Several commenters agree 
that the informational interconnection study proposal could reduce the 
number of speculative or other interconnection requests \186\ and 
improve the efficiency of siting decisions.\187\ Some commenters expect 
that these changes will have other benefits for the interconnection 
process, including cost savings from fewer and more viable 
interconnection requests,\188\ a reduced need for project withdrawals 
and queue restudies,\189\ and reduced burden on transmission providers, 
which will result in fewer interconnection study delays.\190\
---------------------------------------------------------------------------

    \185\ Affected Interconnection Customers Initial Comments at 30; 
Clean Energy States Initial Comments at 4; Consumers Energy Initial 
Comments at 3; Duke Southeast Utilities Initial Comments at 6; 
Evergreen Action Initial Comments at 3; Fervo Energy Initial 
Comments at 2; Illinois Commission Initial Comments at 6; Interwest 
Initial Comments at 4, 7; NESCOE Reply Comments at 2; Public 
Interest Organizations Initial Comments at 18; Southern Initial 
Comments at 28; Tesla Initial Comments at 4; Tri-State Initial 
Comments at 5.
    \186\ Fervo Energy Initial Comments at 2-3; Google Initial 
Comments at 4; NRECA Initial Comments at 13; NY Commission and 
NYSERDA Initial Comments at 6-8.
    \187\ Duke Southeast Utilities Initial Comments at 6-7; ISO-NE 
Initial Comments at 18; NARUC Initial Comments at 5; NRECA Initial 
Comments at 13; Pine Gate Initial Comments at 13-14; Tesla Initial 
Comments at 4.
    \188\ Evergreen Action Initial Comments at 3; NARUC Initial 
Comments at 5.
    \189\ Evergreen Action Initial Comments at 3; NRECA Initial 
Comments at 13.
    \190\ Google Initial Comments at 4.
---------------------------------------------------------------------------

    76. MISO and Fervo Energy state that it is helpful for a 
prospective interconnection customer to compare how various MW sizes, 
points of interconnection, or other scenarios could affect costs, 
especially for prospective interconnection customers that cannot 
perform such analysis in house, and that the NOPR's

[[Page 61029]]

informational interconnection study proposal would assist in these 
goals.\191\ Pacific Northwest Organizations argue that, without upfront 
interconnection cost information, independent power producers may be 
discouraged from entering the interconnection queue if they are 
subjected to higher withdrawal fees, which may result in preventing 
them from being considered in request for proposals (RFPs) in the 
Pacific Northwest.\192\
---------------------------------------------------------------------------

    \191\ Fervo Energy Initial Comments at 2; MISO Initial Comments 
at 22.
    \192\ Pacific Northwest Organizations Initial Comments at 3-4.
---------------------------------------------------------------------------

    77. Some commenters stress the importance of the informational 
interconnection study in light of the other reforms proposed in the 
NOPR. For instance, Northwest and Intermountain aver that the 
informational study will be the primary resource for interconnection 
customers to demonstrate the feasibility and cost effectiveness of 
their interconnection plan and will serve as the foundation for 
subsequent negotiations for the documents that will establish 
commercial readiness of their project for the cluster study 
process.\193\ Pacific Northwest Organizations assert that the NOPR's 
proposed commercial readiness framework would be problematic in the 
region without something like the informational interconnection study 
to discover costs before entering the queue.\194\
---------------------------------------------------------------------------

    \193\ Northwest and Intermountain Initial Comments at 6-7.
    \194\ Pacific Northwest Organizations Initial Comments at 3.
---------------------------------------------------------------------------

    78. Several commenters are generally supportive of the NOPR 
proposal but either (1) offer qualifications to that support \195\ or 
(2) request specific changes to the proposal.\196\
---------------------------------------------------------------------------

    \195\ Idaho Power Initial Comments at 3 (stating that it only 
supports the proposal if the informational interconnection study 
requirements are less prescriptive and allow for more flexibility); 
NRECA Initial Comments at 8 (stating that it does not oppose the 
proposal as long as the final rule includes a larger package of 
reforms to reduce speculative interconnection requests and speed up 
interconnection queues as well as affords reasonable flexibility on 
compliance); Ohio Commission Consumer Advocate Initial Comments at 6 
(stating that informational studies should not interfere with other 
interconnection studies).
    \196\ ACE-NY Initial Comments at 10; Avangrid Initial Comments 
at 21; Clean Energy Buyers Initial Comments at 7; ELCON Initial 
Comments at 4-5; NY Commission and NYSERDA Initial Comments at 6-7; 
Pattern Energy Initial Comments at 20; Pine Gate Initial Comments at 
11-13; Southern Initial Comments at 28.
---------------------------------------------------------------------------

(b) Comments in Opposition
    79. Many commenters oppose the NOPR proposal to require 
transmission providers to offer an informational interconnection study 
to prospective interconnection customers.\197\ Many commenters argue 
that the informational interconnection study proposal could be a burden 
or divert resources,\198\ which they contend would increase delays for 
the interconnection queue and other studies.\199\ Dominion insists that 
the decision as to whether to offer informational interconnection 
studies should be the transmission provider's and must have 
limits.\200\ Longroad Energy states that transmission-interconnected 
generating facilities are typically complex facilities with unique 
operating characteristics which would be poorly approximated in 
simplified studies.\201\ Environmental Defense Fund states that, while 
it supported the informational interconnection studies proposal in its 
initial comments, after review of the other comments submitted, it 
recommends that the Commission reconsider the proposal and ensure that 
any informational interconnection study reform not delay other 
interconnection processes.\202\
---------------------------------------------------------------------------

    \197\ AECI Initial Comments at 3; AEP Initial Comments at 7; AEP 
Reply Comments at 2; APPA-LPPC Initial Comments at 3; Avangrid 
Initial Comments at 21; Bonneville Initial Comments at 3; CAISO 
Initial Comments at 5; Clean Energy Associations Initial Comments at 
13; Dominion Reply Comments at 5; EEI Initial Comments at 11; EEI 
Reply Comments at 7-8; Enel Initial Comments at 9; ENGIE Initial 
Comments at 2; Eversource Initial Comments at 5; Indicated PJM TOs 
Initial Comments at 12; Indicated PJM TOs Reply Comments at 14; 
Longroad Energy Reply Comments at 3; NextEra Initial Comments at 5; 
NextEra Reply Comments at 8; North Dakota Commission Initial 
Comments at 3-4; NV Energy Initial Comments at 14; OMS Initial 
Comments at 5; [Oslash]rstead Initial Comments at 7; PG&E Initial 
Comments at 9; PJM Initial Comments at 45; PPL Initial Comments at 
4; SEIA Initial Comments at 3; SPP Initial Comments at 2, 3-4; 
Vermont Electric and Vermont Transco Initial Comments at 3; WIRES 
Initial Comments at 8.
    \198\ AECI Initial Comments at 3; AEE Reply Comments at 5-6; AEP 
Initial Comments at 7-8; AEP Reply Comments at 2; AES Initial 
Comments at 4; Alliant Energy Initial Comments at 4; APPA-LPPC 
Initial Comments at 9; APS Initial Comments at 5; Bonneville Initial 
Comments at 3; CAISO Initial Comments at 6; Clean Energy Buyers 
Initial Comments at 6; Clean Energy States Initial Comments at 4; 
Dominion Reply Comments at 5-6; Environmental Defense Fund Reply 
Comments at 5; EEI Initial Comments at 11-12; EEI Reply Comments at 
8-9; ELCON Initial Comments at 4-5; Enel Initial Comments at 9; 
ENGIE Initial Comments at 2; Eversource Initial Comments at 5; 
Google Initial Comments at 5; Idaho Power Initial Comments at 3; 
Indicated PJM TOs Initial Comments at 12; Indicated PJM TOs Reply 
Comments at 14; Longroad Energy Reply Comments at 4-5; MISO Reply 
Comments at 17; National Grid Initial Comments at 9; NESCOE Reply 
Comments at 2; NextEra Reply Comments at 8-9, 11-12; New Jersey 
Commission Initial Comments at 21; North Dakota Commission Initial 
Comments at 3-4; NRECA Initial Comments at 14; NV Energy Initial 
Comments at 14; NYISO Initial Comments at 16; OMS Initial Comments 
at 5; Pine Gate Initial Comments at 12; PPL Initial Comments at 4-6; 
SDG&E Initial Comments at 3-4; SEIA Initial Comments at 3; SEIA 
Reply Comments at 4; SoCal Edison Initial Comments at 12; Tesla 
Initial Comments at 4; Vermont Electric and Vermont Transco Initial 
Comments at 3; WIRES Initial Comments at 8.
    \199\ AECI Initial Comments at 3; AEP Initial Comments at 7-8; 
AEP Reply Comments at 2-3; AES Initial Comments at 4; Alliant Energy 
Initial Comments at 4; APS Initial Comments at 4; Bonneville Initial 
Comments at 3; CAISO Initial Comments at 6; Dominion Initial 
Comments at 9; Duke Southeast Utilities Initial Comments at 7-8; 
Environmental Defense Fund Reply Comments at 5; EEI Initial Comments 
at 11; ELCON Initial Comments at 4-5; Eversource Initial Comments at 
5-6; Google Initial Comments at 5; Idaho Power Initial Comments at 
3; Indicated PJM TOs Initial Comments at 13; MISO Reply Comments at 
17; National Grid Initial Comments at 7, 10-11; NESCOE Reply 
Comments at 2; NextEra Reply Comments at 8; New Jersey Commission 
Initial Comments at 21; North Dakota Commission Initial Comments at 
3-4; NRECA Initial Comments at 14; NYISO Initial Comments at 16-19; 
OMS Initial Comments at 5; Pennsylvania Commission Initial Comments 
at 11; PG&E Initial Comments at 9; PG&E Reply Comments at 5; Pine 
Gate Initial Comments at 12; PJM Initial Comments at 45; PPL Initial 
Comments at 4; SEIA Initial Comments at 4; SoCal Edison Initial 
Comments at 12; Tesla Initial Comments at 4.
    \200\ Dominion Reply Comments at 5.
    \201\ Longroad Energy Reply Comments at 7.
    \202\ Environmental Defense Fund Reply Comments at 5.
---------------------------------------------------------------------------

    80. Several commenters contend that the informational 
interconnection study proposal would not likely be valuable.\203\ Clean 
Energy Associations assert that the proposed informational 
interconnection study would provide no information related to 
stability-driven network upgrades, rendering it near-useless in areas 
where stability limits are most typically the driver of network 
upgrades.\204\ APPA-LPPC warn that informational interconnection 
studies could engender controversy because prospective interconnection 
customers would, notwithstanding the informational nature of the 
studies, likely rely upon the study results in

[[Page 61030]]

making investment decisions, even though the informational study 
results would inevitably diverge from the actual interconnection study 
results.\205\
---------------------------------------------------------------------------

    \203\ AEE Initial Comments at 9-10; AEE Reply Comments at 5-6; 
AEP Initial Comments at 7; AEP Reply Comments at 2; Alliant Energy 
Initial Comments at 4; CAISO Initial Comments at 5-6; Clean Energy 
Associations Initial Comments at 14; CREA and NewSun Initial 
Comments at 42; Dominion Reply Comments at 5; EEI Initial Comments 
at 12; EEI Reply Comments at 8; Enel Initial Comments at 9; ENGIE 
Initial Comments at 2; Eversource Initial Comments at 5-6; Indicated 
PJM TOs Initial Comments at 12; Indicated PJM TOs Reply Comments at 
14; ISO-NE Initial Comments at 19; Longroad Energy Reply Comments at 
3; MISO Initial Comments at 20-21; MISO Reply Comments at 17-18; 
NextEra Initial Comments at 5, 10-11; NextEra Reply Comments at 9; 
North Dakota Commission Initial Comments at 4; NRECA Initial 
Comments at 14; NV Energy Initial Comments at 14; NYISO Initial 
Comments at 17; OMS Initial Comments at 5; Pacific Northwest 
Utilities Initial Comments at 8 n.13; PG&E Initial Comments at 9; 
PG&E Reply Comments at 4; PJM Initial Comments at 45; SDG&E Initial 
Comments at 3-4; SEIA Initial Comments at 3; SEIA Reply Comments at 
3; SoCal Edison Initial Comments at 11-12; WIRES Initial Comments at 
8.
    \204\ Clean Energy Associations Initial Comments at 14.
    \205\ APPA-LPPC Initial Comments at 12.
---------------------------------------------------------------------------

    81. Several commenters argue that the proposal is not an 
improvement over the status quo.\206\ National Grid and NextEra assert 
that it is unclear how the proposal would save any time compared to the 
status quo, and that the best way for an interconnection customer to 
obtain the necessary information is by entering and proceeding through 
the interconnection queue with transmission providers focusing on 
actual studies.\207\ NextEra adds that the proposed informational 
interconnection study is only informative in extreme cases, such as 
very limited capacity available on a transmission line, which the 
interconnection customer should be able to identify themselves.\208\
---------------------------------------------------------------------------

    \206\ National Grid Initial Comments at 9; New Jersey Commission 
Initial Comments at 21; Vermont Electric and Vermont Transco Initial 
Comments at 3.
    \207\ National Grid Initial Comments at 9; NextEra Initial 
Comments at 12.
    \208\ NextEra Initial Comments at 12.
---------------------------------------------------------------------------

    82. CREA and NewSun express concern that the NOPR proposal places 
too much reliance on the usefulness of the informational 
interconnection study in order to justify the financial readiness and 
commitment NOPR proposals.\209\ They assert that the informational 
interconnection study is not a useful replacement for the feasibility 
study, which takes into account the impact of other interconnection 
customers in the interconnection queue cluster. Therefore, CREA and 
NewSun ask the Commission to instead retain the feasibility study as 
part of the cluster study process to allow interconnection customers to 
obtain cluster-level information on likely costs and network upgrades 
before proceeding further with major deposits and irretrievable 
commitments.
---------------------------------------------------------------------------

    \209\ CREA and NewSun Initial Comments at 46-47.
---------------------------------------------------------------------------

    83. Several commenters point to the experience with similar studies 
in SPP and MISO as evidence that the optional informational 
interconnection study proposal will be little-used in practice.\210\ 
SPP reports that its interconnection customers explained that their 
time could be more effectively spent working on the more definitive 
system impact studies, that the feasibility and preliminary impact 
studies did not provide results that could be relied on in making 
business decisions, and that this same outcome would be true of the 
proposed informational interconnection study.\211\
---------------------------------------------------------------------------

    \210\ AEE Initial Comments at 10; AEP Initial Comments at 8,12; 
Clean Energy Associations Initial Comments at 14; Enel Initial 
Comments at 9-10; Longroad Energy Reply Comments at 3-4; MISO 
Initial Comments at 21; NextEra Reply Comments at 8; Omaha Public 
Power Initial Comments at 3; SEIA Reply Comments at 3; SPP Initial 
Comments at 3. NextEra argues that transmission providers with large 
numbers of interconnection requests have tried optional 
interconnection studies and have not found them to be useful. 
NextEra Reply Comments at 10.
    \211\ SPP Initial Comments at 3.
---------------------------------------------------------------------------

    84. Several commenters point to the inability of the informational 
interconnection studies to provide reliable cost estimates \212\ and 
believe that the information provided in these studies will be quickly 
outdated.\213\ The New Jersey Commission is concerned that this 
approach may not materially reduce the uncertainty interconnection 
customers currently face.\214\ In particular, many commenters contend 
that the informational interconnection study is not meaningful in the 
context of a cluster interconnection
---------------------------------------------------------------------------

    \212\ AEP Initial Comments at 8; Ameren Initial Comments at 5; 
CAISO Initial Comments at 5; Clean Energy Associations Initial 
Comments at 14; CREA and NewSun Initial Comments at 43; Cyprus Creek 
Initial Comments at 13; Enel Initial Comments at 9; Interwest 
Initial Comments at 7-8; NextEra Initial Comments at 5; NRECA 
Initial Comments at 14; PJM Initial Comments at 45; SoCal Edison 
Initial Comments at 11-12.
    \213\ AEP Initial Comments at 8; Alliant Energy Initial Comments 
at 4; Dominion Initial Comments at 10; Enel Initial Comments at 9; 
Eversource Initial Comments at 9; Interwest Initial Comments at 7-8; 
PJM Initial Comments at 45; PJM TOs Initial Comments at 13; SEIA 
Reply Comments at 4.
    \214\ New Jersey Commission Initial Comments at 21.
---------------------------------------------------------------------------

    process.\215\ Commenters argue that, because the informational 
interconnection study does not provide information on other 
interconnection customers that would enter the interconnection queue at 
the same time, there is no guarantee that the study results will even 
approximate the actual network upgrade costs determined by the cluster 
results.\216\
---------------------------------------------------------------------------

    \215\ Id.; AEE Initial Comments at 9-10; Avangrid Initial 
Comments at 23-24; Clean Energy Associations Initial Comments at 14; 
CREA and NewSun Initial Comments at 43; Dominion Reply Comments at 
6; EEI Initial Comments at 12; EEI Reply Comments at 8; Enel Initial 
Comments at 9; Eversource Initial Comments at 9-10; ISO-NE Initial 
Comments at 18-19; MISO Initial Comments at 21; NRECA Initial 
Comments at 14; NV Energy Initial Comments at 14; PJM Initial 
Comments at 45; PPL Initial Comments at 5; SEIA Initial Comments at 
4-5; SEIA Reply Comments at 3-4; SoCal Edison Initial Comments at 
12; SPP Initial Comments at 2-3.
    \216\ AEE Initial Comments at 9-10; CAISO Initial Comments at 5-
6; CREA and NewSun Initial Comments at 44; Dominion Initial Comments 
at 10; Duke Southeast Utilities Initial Comments at 7; EEI Reply 
Comments at 8; Indicated PJM TOs Initial Comments at 13; ISO-NE 
Initial Comments at 18-19; MISO Initial Comments at 22; NextEra 
Initial Comments at 11-12; New Jersey Commission Initial Comments at 
21; PG&E Reply Comments at 5; PPL Initial Comments at 5; SEIA Reply 
Comments at 3-4; SoCal Edison Initial Comments at 12.
---------------------------------------------------------------------------

    85. Some commenters expect the proposal will work against the 
Commission's goal of faster interconnection queue processing.\217\ Some 
commenters state that any reduction in speculative interconnection 
requests will be offset by an increase in speculative informational 
interconnection requests, which would require transmission providers to 
shift their focus from the actual interconnection queue to this more 
burdensome informational interconnection process, which is outside of 
their interconnection study process.\218\ NRECA states that, if the 
proposal is included in the final rule, the Commission should ensure 
that it is limited and is not expanded into an elaborate serial study 
process prior to the cluster study process.\219\ Avangrid notes that 
some transmission providers have recently eliminated interconnection 
studies to reduce interconnection queue processing time.\220\ 
Pennsylvania Commission asserts that the Commission should assess the 
results of the NOPR's proposed reforms before requiring any new study 
processes that may further slow the interconnection queue process.\221\
---------------------------------------------------------------------------

    \217\ AEE Reply Comments at 6; AEP Initial Comments at 11; 
Avangrid Initial Comments at 22-23; CAISO Initial Comments at 6; 
Dominion Reply Comments at 6-7; National Grid Initial Comments at 7; 
NESCOE Reply Comments at 2; NV Energy Initial Comments at 14; 
Pennsylvania Commission Initial Comments at 11-12.
    \218\ AECI Initial Comments at 4; AEP Initial Comments at 11; 
APPA-LPPC Initial Comments at 11-12; Bonneville Initial Comments at 
3 (citing NOPR, 179 FERC ] 61,194 at PP 20, 22, 166); Clean Energy 
Buyers Initial Comments at 6; Dominion Reply Comments at 6; NextEra 
Initial Comments at 12; NYISO Initial Comments at 17; Pennsylvania 
Commission Initial Comments at 11 (explaining that because the 
informational study is not binding on any party, the study does not 
move projects through the interconnection queue).
    \219\ NRECA Initial Comments at 14.
    \220\ Avangrid Initial Comments at 23 (citing NOPR, 179 FERC ] 
61,194 at P 56 n.111).
    \221\ Pennsylvania Commission Initial Comments at 11-12.
---------------------------------------------------------------------------

    86. Several commenters note the challenge of staffing to fulfill 
the informational interconnection study requirements given the limited 
number of qualified planners and engineers.\222\
---------------------------------------------------------------------------

    \222\ Id. at 11; AEP Initial Comments at 10-11; APPA-LPPC 
Initial Comments at 12; Avangrid Initial Comments at 22-23; 
Bonneville Initial Comments at 5; Eversource Initial Comments at 5-
6; Indicated PJM TOs Initial Comments at 12; Indicated PJM TOs Reply 
Comments at 14; LADWP Initial Comments at 2; OMS Initial Comments at 
5.
---------------------------------------------------------------------------

    87. Several commenters urge the Commission to weigh the benefits 
against the burdens to determine whether to adopt the informational 
interconnection study proposal.\223\

[[Page 61031]]

WAPA states that, while it agrees that it is important to provide 
prospective interconnection customers with additional information, it 
has concerns about the proposed timelines and penalties, the potential 
amount of informational interconnection study requests it could 
receive, and its ability to process up to five simultaneous 
informational interconnection study requests per interconnection 
customer.\224\ According to Vermont Electric and Vermont Transco, even 
if the informational interconnection studies envisioned by the NOPR 
provide interconnection customer benefits, the burdens of providing 
informational interconnection studies with cost estimates under the 
NOPR's short proposed time frames and low deposit amounts would be 
considerable especially for smaller companies such as Vermont Electric 
and Vermont Transco.\225\ Other commenters contend that the 
informational interconnection study proposal has insufficient 
benefits.\226\
---------------------------------------------------------------------------

    \223\ Ameren Initial Comments at 5; R Street Initial Comments at 
9; Xcel Initial Comments at 20.
    \224\ WAPA Initial Comments at 4-5.
    \225\ Vermont Electric and Vermont Transco Initial Comments at 
3.
    \226\ Id.; AEP Initial Comments at 7; AES Initial Comments at 4; 
EEI Initial Comments at 11; ENGIE Initial Comments at 2; NextEra 
Initial Comments at 10-11; [Oslash]rstead Initial Comments at 7; PJM 
Initial Comments at 45; SEIA Initial Comments at 3.
---------------------------------------------------------------------------

    88. Given PJM's opposition to the informational interconnect study, 
it recommends modifying the proposed new section 3.1.2 to the pro forma 
LGIP to encourage, but not require, interconnection customers 
evaluating different project characteristics to use a prescreening 
tool, such as the queue scope tool PJM is developing, prior to 
submitting an interconnection request.\227\
---------------------------------------------------------------------------

    \227\ PJM Initial Comments at 19 (explaining that the queue 
scope is an interactive prescreening tool that will allow 
interconnection customers to screen potential points of 
interconnection and assess grid capacity (head room) based on a 
given amount of MW injection or withdrawal at a given point of 
interconnection and that the tool will be available at no charge). 
PJM's proposed section 3.1.2 of the pro forma LGIP would read: 
``Interconnection Customers evaluating different options . . . to 
use the prescreening tool (Section 6.1 of this LGIP) before entering 
the Cluster Study.''
---------------------------------------------------------------------------

iii. Commission Determination
    89. We decline to adopt the NOPR proposal to modify the pro forma 
LGIP to require transmission providers to offer an informational 
interconnection study for prospective interconnection customers. We are 
persuaded by commenters' concerns that requiring an informational 
interconnection study could divert the transmission provider's 
resources away from the cluster studies we require in this final rule 
and undermine the benefits of those reforms that seek to reduce 
interconnection study delays, costs, and burden on constrained 
engineering labor. Moreover, we agree with commenters that highlight 
the various limitations of an informational interconnection study. 
Notably, an informational interconnection study, as proposed in the 
NOPR, would have provided a serial, snapshot-in-time analysis on the 
impact of a single interconnection request, but, in the context of the 
subsequent cluster study, the actual impact of an interconnection 
request within a larger cluster would reflect different assumptions and 
differ from the informational interconnection study, providing minimal 
or no value to interconnection customers. The cost estimates that 
result from such an informational interconnection study would bear 
little correspondence to costs determined during a cluster study 
process and thus provide minimal value to interconnection customers.
    90. We also find persuasive comments that the informational 
interconnection study requirement proposed in the NOPR is not the most 
effective way to provide interconnection customers with the needed pre-
interconnection queue information. At the same time, we continue to 
believe that there is a lack of information available to prospective 
interconnection customers prior to entering the interconnection queue, 
especially given other interconnection customer-related reforms adopted 
in this final rule.\228\ Therefore, as discussed below, we adopt the 
NOPR proposal to set minimum requirements for transmission providers to 
publicly post available information pertaining to generator 
interconnection.\229\ We find that the posting of this information 
provides a better balance between the benefits of additional 
information for prospective interconnection customers and the burdens 
on transmission providers.
---------------------------------------------------------------------------

    \228\ See Northwest and Intermountain Initial Comments at 6-7.
    \229\ See infra section III.A.1.c.iii.
---------------------------------------------------------------------------

    91. In response to commenters that support the informational 
interconnection study NOPR proposal, below we explain how several of 
the NOPR proposals that we adopt in this final rule address their 
specific concerns. To address commenters' concerns with the number of 
speculative interconnection requests,\230\ we adopt more stringent site 
control requirements and increased commercial readiness deposit 
requirements,\231\ which we believe will better address these concerns 
than the informational interconnection study proposal. Additionally, we 
find that the minimum requirements for transmission providers to 
publicly post available information pertaining to generator 
interconnection \232\ and the existing requirements in section 2.3 of 
the pro forma LGIP for transmission providers to post up-to-date base 
case study models on their Open Access Same-time Information System 
(OASIS) or other password-protected websites will improve the 
efficiency of siting decisions \233\ and will provide interconnection 
customers with information about the feasibility of their 
interconnection plans.\234\
---------------------------------------------------------------------------

    \230\ Fervo Energy Initial Comments at 2-3; Google Initial 
Comments at 4; NRECA Initial Comments at 13; NY Commission and 
NYSERDA Initial Comments at 6-8.
    \231\ See infra sections III.A.6.b.iii, III.A.6.c.iii.
    \232\ See infra section III.A.1.c.iii.
    \233\ Duke Southeast Utilities Initial Comments at 6-7; ISO-NE 
Initial Comments at 18; NARUC Initial Comments at 5; NRECA Initial 
Comments at 13; Pine Gate Initial Comments at 13-14; Tesla Initial 
Comments at 4.
    \234\ Northwest and Intermountain Initial Comments at 6-7; 
Pacific Northwest Organizations Initial Comments at 3.
---------------------------------------------------------------------------

    92. We are not persuaded that the informational interconnection 
study proposal would benefit the interconnection process through: (1) 
cost savings from fewer, more feasible interconnection requests; \235\ 
(2) a reduced need for interconnection request withdrawals and 
restudies; \236\ and (3) accurate upfront interconnection cost 
information.\237\ On the contrary, the Commission's adoption of the 
cluster study reforms in this final rule \238\ means that the serial 
nature of the informational interconnection study would fail to reflect 
the outcome of the cluster study, and thus would provide minimal, if 
any, benefits to interconnection customers.\239\ We also no longer 
believe that adopting the informational interconnection study

[[Page 61032]]

proposal would reduce burdens on transmission providers.\240\ This is 
because the record overwhelmingly demonstrates that the proposal would 
result in additional burdens on transmission providers and would likely 
cause transmission providers to divert resources from their cluster 
study process to conduct informational interconnection studies,\241\ 
thus increasing study delays and costs. Similarly, we decline CREA and 
NewSun's request that the Commission retain the feasibility study 
instead of the informational interconnection study. As we discuss 
below, the feasibility study was required for the serial study process 
but is no longer relevant for the cluster study process.\242\ We 
believe that our requirement for transmission providers to publicly 
post certain interconnection information will provide interconnection 
customers with the information they need prior to entering the 
interconnection queue, and therefore decline to adopt CREA and NewSun's 
request to maintain the feasibility study.
---------------------------------------------------------------------------

    \235\ Evergreen Action Initial Comments at 3; NARUC Initial 
Comments at 5.
    \236\ Evergreen Action Initial Comments at 3; NRECA Initial 
Comments at 13.
    \237\ Fervo Energy Initial Comments at 2; MISO Initial Comments 
at 22; Pacific Northwest Organizations Initial Comments at 3-4.
    \238\ See infra section III.A.2.
    \239\ See AEE Initial Comments at 9-10; Avangrid Initial 
Comments at 23-24; Clean Energy Associations Initial Comments at 14; 
CREA and NewSun Initial Comments at 43; Dominion Reply Comments at 
6; EEI Initial Comments at 12; EEI Reply Comments at 8; Enel Initial 
Comments at 9; Eversource Initial Comments at 9-10; ISO-NE Initial 
Comments at 18-19; MISO Initial Comments at 21; New Jersey 
Commission Initial Comments at 21; NRECA Initial Comments at 14; NV 
Energy Initial Comments at 14; PJM Initial Comments at 45; PPL 
Initial Comments at 5; SEIA Initial Comments at 4-5; SEIA Reply 
Comments at 3-4; SoCal Edison Initial Comments at 12; SPP Initial 
Comments at 2-3.
    \240\ See Google Initial Comments at 5 (arguing that the 
informational interconnection study requirement alone would likely 
increase the burden on transmission providers in a way that would 
lengthen delays).
    \241\ Id.; AECI Initial Comments at 3; AEE Reply Comments at 5-
6; AEP Initial Comments at 7-8; AEP Reply Comments at 2; AES Initial 
Comments at 4; Alliant Energy Initial Comments at 4; APPA-LPPC 
Initial Comments at 9; APS Initial Comments at 5; Bonneville Initial 
Comments at 3; CAISO Initial Comments at 6; Clean Energy Buyers 
Initial Comments at 6; Clean Energy States Initial Comments at 4; 
Dominion Reply Comments at 5-6; Environmental Defense Fund Reply 
Comments at 5; EEI Initial Comments at 11-12; EEI Reply Comments at 
8-9; ELCON Initial Comments at 4-5; Enel Initial Comments at 9; 
ENGIE Initial Comments at 2; Eversource Initial Comments at 5; Idaho 
Power Initial Comments at 3; Indicated PJM TOs Initial Comments at 
12; Indicated PJM TOs Reply Comments at 14; Longroad Energy Reply 
Comments at 4-5; MISO Reply Comments at 17; National Grid Initial 
Comments at 9; NESCOE Reply Comments at 2; New Jersey Commission 
Initial Comments at 21; NextEra Reply Comments at 8-9, 11-12; North 
Dakota Commission Initial Comments at 3-4; NRECA Initial Comments at 
14; NV Energy Initial Comments at 14; NYISO Initial Comments at 16; 
OMS Initial Comments at 5; Pine Gate Initial Comments at 12; PPL 
Initial Comments at 4-6; SDG&E Initial Comments at 3-4; SEIA Initial 
Comments at 3; SEIA Reply Comments at 4; SoCal Edison Initial 
Comments at 12; Tesla Initial Comments at 4; Vermont Electric and 
Vermont Transco Initial Comments at 3; WIRES Initial Comments at 8.
    \242\ See infra section III.A.2.f.iii.
---------------------------------------------------------------------------

    93. Because we do not adopt the NOPR proposal to require 
transmission providers to offer an informational interconnection study, 
we decline to adopt the proposal to add new section 3.1.2 to the pro 
forma LGIP to encourage interconnection customers to use the 
informational interconnection study.
c. Public Interconnection Information
i. NOPR Proposal
    94. In the NOPR, the Commission proposed to require transmission 
providers to maintain and make publicly available an interactive visual 
representation of available interconnection capacity (commonly known as 
a ``heatmap'') as well as a table of relevant interconnection metrics 
that allow prospective interconnection customers to see certain 
estimates of a potential generating facility's effect on the 
transmission provider's transmission system.\243\ Specifically, the 
Commission proposed to revise section 6.4 of the pro forma LGIP to 
require transmission providers to post on their public website a 
heatmap of estimated incremental injection capacity (in MW) available 
at each bus in the transmission provider's footprint under N-1 
conditions, as well as provide a table of results showing the estimated 
impact of the addition of a proposed project (based on the user-
specified MW amount, voltage level, and point of interconnection) for 
each monitored facility impacted by the proposed project on: (1) the 
distribution factor; (2) the MW impact (based on the proposed project 
size and the distribution factor); (3) the percentage impact on the 
monitored facility (based on the MW values of the proposed project and 
the monitored facility rating); (4) the percentage of power flow on the 
monitored facility before the proposed project; and (5) the percentage 
power flow on the monitored facility after the injection of the 
proposed project. The Commission explained that these metrics would be 
calculated based on the power flow model of the cluster study or 
restudy with the transfer simulated from each bus to the whole 
transmission provider's footprint (to approximate Network Resource 
Interconnection Service (NRIS)), and with the incremental capacity at 
each bus decremented by the existing and queued generation in the 
cluster (based on the existing or requested interconnection service 
limit of the generation). The Commission proposed to require 
transmission providers to update this information within 30 days after 
the completion of each cluster study and restudy.
---------------------------------------------------------------------------

    \243\ NOPR, 179 FERC ] 61,194 at P 51.
---------------------------------------------------------------------------

    95. The Commission sought comment on whether: (1) there are any 
security concerns with this proposed requirement; and (2) the 
assumptions specified for the analysis are the right set of 
assumptions.\244\
---------------------------------------------------------------------------

    \244\ Id. P 52.
---------------------------------------------------------------------------

ii. Comments
(a) Comments in Support
    96. Many commenters express support for the NOPR's proposal to 
require transmission providers to provide public interconnection 
information.\245\ Several commenters agree that the NOPR proposal will 
provide valuable information to interconnection customers before they 
enter the interconnection queue.\246\ Several commenters aver that the 
proposal could reduce the number of interconnection requests withdrawn 
\247\ and therefore could reduce costs for all parties.\248\ Alliant 
Energy and Clean Energy Associations also see value in the standardized 
format of the proposed

[[Page 61033]]

public interconnection information.\249\ R Street states that a 
properly done visual representation of interconnection capacity can be 
a ``powerful decentralized self-screening tool.'' \250\ R Street states 
that better information and simpler deliverability requirements shift 
congestion performance risk to generating facilities while reducing 
barriers to entry.\251\ The Ohio Commission Consumer Advocate states 
that the visual map of available interconnection capacity would be 
useful both to transmission providers and interconnection customers and 
would encourage information sharing on transmission system congestion 
during the interconnection process.\252\ Google argues that making 
these data publicly available to consumers would allow buyers to make 
informed choices regarding power procurement.\253\ Additionally, Google 
asserts that there needs to be a standard of reasonable care applied to 
ensure that the publicly available information is reasonably current 
and useful to avoid exploratory interconnection requests.\254\ SEIA 
argues that greater transparency will increase competition between 
merchant and utility developed generating facilities, benefiting 
consumers.\255\ Illinois Commission contends that, if properly 
implemented, the NOPR proposal will increase the pace at which new 
generating facilities can connect to the transmission system, 
furthering state policy objectives.\256\
---------------------------------------------------------------------------

    \245\ ACE-NY Initial Comments at 11; AES Initial Comments at 3; 
Affected Interconnection Customers Initial Comments at 30; APPA-LPPC 
Initial Comments at 13; CAISO Initial Comments at 7; CESA Initial 
Comments at 7; Clean Energy Associations Initial Comments at 12; 
Clean Energy Buyers Initial Comments at 6-7; Colorado Commission 
Initial Comments at 8; Consumers Energy Initial Comments at 3; CREA 
and NewSun Initial Comments at 44-45; Duke Southeast Utilities 
Initial Comments at 6; Environmental Defense Fund Initial Comments 
at 3; Environmental Defense Fund Reply Comments at 2-3; ELCON 
Initial Comments at 4; ENGIE Initial Comments at 2; Evergreen Action 
Initial Comments at 3; Fervo Energy Initial Comments at 2; Google 
Initial Comments at 14; Google Reply Comments at 6; Illinois 
Commission Initial Comments at 6; Interwest Initial Comments at 7; 
New Jersey Commission Initial Comments at 11-12; Northwest and 
Intermountain Initial Comments at 9-10; NY Commission and NYSERDA 
Initial Comments at 8; [Oslash]rsted Initial Comments at 7; Pattern 
Energy Initial Comments at 23; Pine Gate Initial Comments at 13; 
Public Interest Organizations Initial Comments at 18-19; R Street 
Initial Comments at 8, 10; Southern Initial Comments at 28; Tesla 
Initial Comments at 6-7; Vistra Initial Comments at 1, 4.
    \246\ Alliant Energy Initial Comments at 5; Clean Energy 
Associations Initial Comments at 12; CREA and NewSun Initial 
Comments at 44-45; Duke Southeast Utilities Initial Comments at 6; 
EEI Initial Comments at 12-13; ELCON Initial Comments at 6; ENGIE 
Initial Comments at 2; Evergreen Action Initial Comments at 3; Fervo 
Energy Initial Comments at 2-3; Illinois Commission Initial Comments 
at 6; Indicated PJM TOs Initial Comments at 14; Indicated PJM TOs 
Reply Comments 6; ISO-NE Initial Comments at 26-27; New Jersey 
Commission Initial Comments at 12; NY Commission and NYSERDA Initial 
Comments at 8; Ohio Commission Consumer Advocate Initial Comments at 
7; Pacific Northwest Utilities Initial Comments at 13; SEIA Initial 
Comments at 5.
    \247\ CESA Initial Comments at 9; CESA Reply Comments at 3; 
Consumers Energy Initial Comments at 3; CREA and NewSun Initial 
Comments at 44-45; Duke Southeast Utilities Initial Comments at 6; 
Environmental Defense Fund Initial Comments at 3; EEI Initial 
Comments at 12-13; ELCON Initial Comments at 6; Evergreen Action 
Initial Comments at 3; Google Initial Comments at 14; Illinois 
Commission Initial Comments at 6-7; New Jersey Commission Initial 
Comments at 12; NY Commission and NYSERDA Initial Comments at 8; 
Pacific Northwest Utilities Initial Comments at 13; SEIA Initial 
Comments at 5.
    \248\ Evergreen Action Initial Comments at 3; New Jersey 
Commission Initial Comments at 12.
    \249\ Alliant Energy Initial Comments at 5; Clean Energy 
Associations Initial Comments at 12.
    \250\ R Street Initial Comments at 10.
    \251\ R Street Reply Comments at 2.
    \252\ Ohio Commission Consumer Advocate Initial Comments at 7.
    \253\ Google Initial Comments at 4.
    \254\ Google Reply Comments at 7.
    \255\ SEIA Reply Comments at 5.
    \256\ Illinois Commission Initial Comments at 6.
---------------------------------------------------------------------------

    97. Some commenters contend that the proposal to provide public 
interconnection information is not overly burdensome.\257\ APPA-LPPC 
members report that the information posting and interactive capability 
described in the NOPR could be feasibly implemented with available 
industry system simulation tools.\258\ Clean Energy Associations state 
that heatmaps should be as automated as possible, without significant 
commitments of staff or resources.\259\
---------------------------------------------------------------------------

    \257\ APPA-LPPC Initial Comments at 16; Clean Energy 
Associations Initial Comments at 12-13; Google Initial Comments at 
14; New York State Department Initial Comments at 8; Pennsylvania 
Commission Initial Comments at 13; SEIA Initial Comments at 6.
    \258\ APPA-LPPC Initial Comments at 16.
    \259\ Clean Energy Associations Initial Comments at 13.
---------------------------------------------------------------------------

    98. Several commenters point to the fact that some transmission 
providers are already developing such tools as evidence that these 
tools are unlikely to cause further delays to stressed interconnection 
queues or additional burden on transmission providers.\260\ For 
instance, some commenters note that MISO already offers a heatmap that 
represents geographically advantageous siting locations.\261\ Several 
commenters also note that PJM is developing such a tool.\262\ PJM 
states that in 2023 its queue scope tool will provide a congestion map 
with colors or symbols indicating the worst flowgate loading at each 
point of interconnection.\263\ SPP states that it is also developing a 
tool to be implemented by 2025 that would provide much of the 
functionality described in the Commission's public information proposal 
to new interconnections.\264\
---------------------------------------------------------------------------

    \260\ Id. at 12; Environmental Defense Fund Reply Comments at 3; 
ENGIE Initial Comments at 2-3; Pennsylvania Commission Initial 
Comments at 13.
    \261\ CESA Reply Comments at 5; Fervo Energy Reply Comments at 
3; OMS Initial Comments at 3, 6; R Street Initial Comments at 10; 
SEIA Initial Comments at 6.
    \262\ CESA Reply Comments at 4; Fervo Energy Reply Comments at 
3; Indicated PJM TOs Initial Comments at 14; Ohio Commission 
Consumer Advocate Initial Comments at 7; Pennsylvania Commission 
Initial Comments at 13; PJM Initial Comments at 48; PPL Initial 
Comments at 9; R Street Initial Comments at 10; SEIA Initial 
Comments at 6.
    \263\ PJM Initial Comments at 46-47.
    \264\ SPP Initial Comments at 4.
---------------------------------------------------------------------------

    99. Several commenters contend that the public information proposal 
is a more reasonable balance of costs and benefits relative to the 
informational interconnection study proposal.\265\ Pennsylvania 
Commission states that, once a public information tool is established, 
it may require fewer ongoing resources, continuing to inform 
interconnection customers while freeing those resources for additional 
interconnection studies as compared to the proposed informational 
interconnection study.\266\
---------------------------------------------------------------------------

    \265\ Ameren Initial Comments at 5; APPA-LPPC Initial Comments 
at 16; APS Initial Comments at 5; Bonneville Initial Comments at 5; 
Pennsylvania Commission Initial Comments at 13; PJM Initial Comments 
at 45-48; R Street Initial Comments at 10.
    \266\ Pennsylvania Commission Initial Comments at 13.
---------------------------------------------------------------------------

(b) Comments in Opposition
    100. A few commenters oppose the NOPR proposal to require 
transmission providers to provide public interconnection 
information.\267\ A larger number of commenters express reservations 
about the proposal,\268\ in particular regarding its usefulness \269\ 
or the burden it creates.\270\ Other commenters request that the 
Commission make public interconnection information posting 
optional.\271\
---------------------------------------------------------------------------

    \267\ Avangrid Reply Comments at 4; El Paso Electric Initial 
Comments at 8; PG&E Initial Comments at 9.
    \268\ AEP Initial Comments at 13; Idaho Power Initial Comments 
at 3; NextEra Initial Comments at 12-13; Omaha Public Power Initial 
Comments at 4; PacifiCorp Initial Comments at 13-14; SPP Initial 
Comments at 4; Tri-State Initial Comments at 4; WAPA Initial 
Comments at 7-8.
    \269\ AEP Initial Comments at 13; Idaho Power Initial Comments 
at 3; ISO-NE Initial Comments at 17; Longroad Energy Reply Comments 
at 7; Omaha Public Power Initial Comments at 4; PacifiCorp Initial 
Comments at 13-14; SPP Initial Comments at 4; WAPA Initial Comments 
at 7-8.
    \270\ AECI Initial Comments at 5; Dominion Initial Comments at 
12; National Grid Initial Comments at 7; NextEra Initial Comments at 
12-13; Omaha Public Power Initial Comments at 4; PacifiCorp Initial 
Comments at 13-14; SPP Initial Comments at 4.
    \271\ AEP Initial Comments at 13; Avangrid Initial Comments at 
21-22; SPP Initial Comments at 4.
---------------------------------------------------------------------------

    101. Several commenters argue that the proposal to require 
transmission providers to provide public interconnection information is 
not useful,\272\ particularly because it might not provide sufficient 
detail \273\ or commercially actionable information for interconnection 
customers.\274\ Commenters explain that heatmaps are specific to a 
moment in time and thus not representative of actual available 
injection across the transmission system, which is ever-changing.\275\ 
NextEra observes that heatmaps do not contain actionable information 
for interconnection and instead focus on energy prices and 
congestion.\276\ ISO-NE, MISO, and Omaha Public Power note that a 
visual representation of interconnection capacity cannot account for 
all of the conditions identified in a system impact study, including 
different system stresses, operability issues (e.g., N-1-1), stability 
and voltage issues, and weak transmission system issues.\277\

[[Page 61034]]

Longroad Energy asserts that generator interconnection heatmaps or 
hosting capacity maps can be of some use for interconnections to the 
distribution system but are unlikely to be beneficial for projects 
interconnecting at transmission voltages.\278\
---------------------------------------------------------------------------

    \272\ Dominion Initial Comments at 13; Idaho Power Initial 
Comments at 3; ISO-NE Initial Comments at 17; NextEra Initial 
Comments at 12; New York State Department Initial Comments at 8; 
NYISO Initial Comments at 17; Omaha Public Power Initial Comments at 
4; PacifiCorp Initial Comments at 14.
    \273\ AECI Initial Comments at 5; Dominion Initial Comments at 
13; Longroad Energy Reply Comments at 7; National Grid Initial 
Comments at 8; New York State Department Initial Comments at 8; 
Omaha Public Power Initial Comments at 4.
    \274\ AEE Initial Comments at 9; Cypress Creek Initial Comments 
at 13; NextEra Initial Comments at 12.
    \275\ AECI Initial Comments at 5; AEP Initial Comments at 13; 
New York State Department Initial Comments at 8; NYISO Initial 
Comments at 17.
    \276\ NextEra Initial Comments at 12.
    \277\ ISO-NE Initial Comments at 17; MISO Initial Comments at 26 
(citing NOPR, 179 FERC ] 61,194 at P 50 & n.105); Omaha Public Power 
Initial Comments at 4.
    \278\ Longroad Energy Reply Comments at 7.
---------------------------------------------------------------------------

    102. Some commenters do not believe that the heatmap proposal will 
appreciably reduce speculative interconnection requests.\279\ MISO 
explains that, in its experience, few interconnection customers use its 
interconnection heatmap tool and instead tend to use their own 
tools.\280\ Puget Sound states that, even with a heatmap, if an 
interconnection customer has a request that would require energy 
transfer across balancing authorities, it would have to submit an 
interconnection request to get information on the scope of necessary 
network upgrades.\281\ NV Energy asserts that a heatmap of its 
transmission system would be of little value, appearing as though there 
is no available transfer capacity, because the generation in its 
interconnection queue is more than five times the level of NV Energy 
load.\282\ Meanwhile, Puget Sound states that a heatmap of its 
territory would only account for generation and interconnection 
capacity in its balancing authority footprint even though its 
transmission goes beyond this footprint.\283\
---------------------------------------------------------------------------

    \279\ Idaho Power Initial Comments at 3; PPL Initial Comments at 
9.
    \280\ MISO Initial Comments at 25-26.
    \281\ Puget Sound Initial Comments at 6.
    \282\ NV Energy Initial Comments at 10.
    \283\ Puget Sound Initial Comments at 6.
---------------------------------------------------------------------------

    103. Several commenters contend that a heatmap tool as proposed 
would be less useful in a cluster study than it is in a serial process 
because it cannot include similarly queued generation.\284\ Ohio 
Commission Consumer Advocate questions whether it will capture the 
``dynamic elements'' of cluster studies and restudies.\285\ PacifiCorp 
and AEP state that the mere fact that an area is not shown as congested 
on a heatmap does not mean that it will be a suitable interconnection 
location, particularly if multiple interconnection customers seek to 
interconnect there.\286\
---------------------------------------------------------------------------

    \284\ CAISO Initial Comments at 8; CREA and NewSun Initial 
Comments at 48; Duke Southeast Utilities Initial Comments at 6-7; 
MISO Initial Comments at 26; Ohio Commission Consumer Advocate 
Initial Comments at 7; PacifiCorp Initial Comments at 15.
    \285\ Ohio Commission Consumer Advocate Initial Comments at 7.
    \286\ AEP Initial Comments at 13; PacifiCorp Initial Comments at 
15.
---------------------------------------------------------------------------

    104. Longroad Energy and PacifiCorp express concern that the 
heatmap tools would not be restricted to prospective interconnection 
customers and could instead be used by third-party consultants for 
their own business interests; for instance, real estate speculators 
could use the information to secure exclusive site control for 
locations that show significant generator interconnection 
capacity.\287\ According to Longroad Energy, such risk is particularly 
harmful to wind and solar generation interconnection customers' needs 
for large tracts of land to accommodate their generation 
equipment.\288\
---------------------------------------------------------------------------

    \287\ Longroad Energy Reply Comments at 7; PacifiCorp Initial 
Comments at 15.
    \288\ Longroad Energy Reply Comments at 7.
---------------------------------------------------------------------------

    105. Some commenters assert that maintaining the heatmap and 
posting required information on available interconnection capacity 
would be burdensome for transmission providers, especially in non-RTO/
ISO regions.\289\ Similarly, NV Energy states that it participates in 
the CAISO energy imbalance market and its energy management system does 
not currently have the technical functionality to build an interactive 
map that shows information like the available interconnection 
capacity.\290\ Some commenters argue that the heatmaps may provide 
insufficient benefit to justify cost, resources, and time it would take 
to produce them.\291\ Omaha Public Power further asserts that 
interconnection customers will likely find it more valuable for a 
transmission provider invest in more reliable and consequential 
studies.\292\ Pacific Northwest Utilities assert that the Commission 
should present additional data regarding the benefits of requiring a 
heatmap before mandating their use.\293\ Clean Energy Associations 
recommend that the Commission consider other means of increasing 
information to prospective interconnection customers, such as public 
scoping meetings prior to the prospective interconnection customers 
entering the interconnection queue.\294\
---------------------------------------------------------------------------

    \289\ National Grid Initial Comments at 7-8; PacifiCorp Initial 
Comments at 13; Tri-State Initial Comments at 7.
    \290\ NV Energy Initial Comments at 10.
    \291\ Dominion Initial Comments at 13; National Grid Initial 
Comments at 8; NextEra Initial Comments at 12; New York State 
Department Initial Comments at 8; Omaha Public Power Initial 
Comments at 4; Pacific Northwest Utilities Initial Comments at 14; 
PPL Initial Comments at 9; Tri-State Initial Comments at 4; WAPA 
Initial Comments at 7.
    \292\ Omaha Public Power Initial Comments at 4.
    \293\ Pacific Northwest Utilities Initial Comments at 14.
    \294\ Clean Energy Associations Initial Comments at 14.
---------------------------------------------------------------------------

    106. Some commenters express concern that the public information 
proposal will impose new costs on ratepayers and market 
participants.\295\ WAPA states that, given its defined appropriations 
and budgets, it is difficult to create new programs, unlike for larger 
investor-owned utilities or RTOs/ISOs.\296\ Dominion estimates that 
implementation would require a large up-front financial commitment, 
potentially for third-party software and personnel hours, and longer-
term financial commitment to maintain such a site.\297\ NV Energy 
contends that creating such a heatmap showing interconnection 
capabilities would require finding an eligible software, an ongoing 
expense.\298\
---------------------------------------------------------------------------

    \295\ New York State Department Initial Comments at 8; SoCal 
Edison Initial Comments at 13.
    \296\ WAPA Initial Comments at 7.
    \297\ Dominion Initial Comments at 12.
    \298\ NV Energy Initial Comments at 10.
---------------------------------------------------------------------------

    107. Several commenters speak to the burden of additional staffing 
needs to provide public interconnection information. National Grid 
states that the interactive visual representation tool, even if 
contracted from a third party, would require significant time 
commitments from numerous personnel with relevant and advanced 
expertise in transmission and interconnection engineering.\299\ Tri-
State notes that the Commission has recognized the lack of available 
engineers and that imposing a heatmap requirement would exacerbate the 
problem.\300\ Dominion and Duke Southeast Utilities state that any 
additional process would require additional financial and personnel 
resources, and also burden the same personnel that are already engaged 
in managing the interconnection queue.\301\ El Paso Electric argues 
that transmission providers should not be required to allocate human 
resources from interconnection studies to monthly transmission line 
capacity estimates because the staff reallocation could cause 
interconnection study backlogs.\302\ PacifiCorp states that this burden 
will be particularly onerous to transmission providers outside RTO/ISO 
regions, which have comparatively few transmission staff 
available.\303\
---------------------------------------------------------------------------

    \299\ National Grid Initial Comments at 7-8.
    \300\ Tri-State Initial Comments at 8.
    \301\ Dominion Initial Comments at 13; Duke Southeast Utilities 
Initial Comments at 7.
    \302\ El Paso Electric Initial Comments at 7.
    \303\ PacifiCorp Initial Comments at 13.
---------------------------------------------------------------------------

    108. Several commenters suggest that interconnection customers, on 
their own or with consultants, can perform studies with the available 
information that would provide estimates on available capacity similar 
to that produced under

[[Page 61035]]

the NOPR proposal.\304\ PPL states that interconnection customers can 
make their own such maps using transmission planning models the 
Commission makes available following a Freedom of Information Act 
request.\305\ APPA-LPPC argue that the Commission fails to establish 
that the information already available to prospective interconnection 
customers under the existing pro forma LGIP, along with the substantial 
supplement implemented with Order No. 845, is inadequate.\306\ SoCal 
Edison states that the information included in the NOPR proposal and 
more is already available if interconnection customers request it from 
the Commission for their own studies or use studies developed by 
transmission providers.\307\ The Ohio Commission Consumer Advocate 
states that the determination of a suitable site depends largely on the 
location and geography of the resources, which is publicly available 
from national labs and the U.S. Energy Information Administration.\308\
---------------------------------------------------------------------------

    \304\ Id. at 15; AEP Initial Comments at 8; APPA-LPPC Initial 
Comments at 9; El Paso Electric Initial Comments at 7; PPL Initial 
Comments at 9; SoCal Edison Initial Comments at 14.
    \305\ PPL Initial Comments at 9.
    \306\ APPA-LPPC Initial Comments at 9.
    \307\ SoCal Edison Initial Comments at 14.
    \308\ Ohio Commission Consumer Advocate Initial Comments at 6-7.
---------------------------------------------------------------------------

    109. Several commenters state that sufficient data are already 
required to be posted on OASIS.\309\ According to Idaho Power, Order 
No. 2003-A required interconnection study reports to be publicly 
available and provide locational and cost information for previously 
studied interconnections, but this has not reduced the amount of 
interconnection requests at congested locations.\310\ SoCal Edison and 
NYISO state that this information is already available in FERC Form 
715, where it is protected with a non-disclosure agreement as critical 
energy infrastructure information (CEII) and has the benefit of being 
available in one centralized location.\311\ On the other hand, ACE-NY 
disagrees with the assertion that FERC Form 715 provides sufficient 
information for interconnection customers to do their own analysis, 
asserting that the FERC Form 715 database base cases do not contain 
sufficient data about the generation interconnection queue and study 
assumptions and are therefore inadequate.\312\ Rather, ACE-NY argues 
that more detailed base cases such as those currently being made 
available by MISO and PJM, should be required.
---------------------------------------------------------------------------

    \309\ Duke Southeast Utilities Initial Comments at 6-7; Idaho 
Power Initial Comments at 3; NV Energy Initial Comments at 10; 
PacifiCorp Initial Comments at 14-15.
    \310\ Idaho Power Initial Comments at 3.
    \311\ NYISO Initial Comments at 17; SoCal Edison Initial 
Comments at 14.
    \312\ ACE-NY Reply Comments at 3-4.
---------------------------------------------------------------------------

    110. Several commenters state that the usefulness of public 
interconnection information proposal will depend on the implementation 
details.\313\ For example, Illinois Commission and CESA recognize that 
the accuracy of the heatmaps is an important part of how useful they 
will be.\314\ Puget Sound states that it has considered creating such a 
heatmap but has concerns about its effectiveness given implementation 
challenges.\315\ SPP states that technology, information, and tools are 
quickly evolving and that a standardization tool might be obsolete 
before it is implemented.\316\ CESA explains that currently CAISO 
provides static, snapshot-in-time transmission capability estimates 
that are helpful but do not capture locational granularity or other 
projects already in the interconnection queue, making it difficult to 
make an informed project siting decision and at times requiring data 
requests of CAISO.\317\ For this reason, CESA stresses that the 
heatmaps and associated data must be made available in a user-friendly 
format. CREA and NewSun argue that the Commission should be careful not 
to overestimate the ability to forecast interconnection costs and 
project viability that will ultimately result from a cluster 
study.\318\ Several commenters stress that any potential increase in 
transparency and interconnection process performance resulting from 
this proposal must outweigh the additional burden imposed on 
transmission providers.\319\
---------------------------------------------------------------------------

    \313\ CESA Initial Comments at 8-9; Illinois Commission Initial 
Comments at 6; Puget Sound Initial Comments at 6; SPP Initial 
Comments at 4.
    \314\ CESA Initial Comments at 9; Illinois Commission Initial 
Comments at 6.
    \315\ Puget Sound Initial Comments at 6.
    \316\ SPP Initial Comments at 4.
    \317\ CESA Initial Comments at 8.
    \318\ CREA and NewSun Initial Comments at 48.
    \319\ Cypress Creek Initial Comments at 14; EEI Initial Comments 
at 12-13; Eversource Initial Comments at 11; New Jersey Commission 
Initial Comments at 22-23; New York State Department Initial 
Comments at 8-9.
---------------------------------------------------------------------------

(c) Comments on Specific Proposal
(1) Metrics
    111. While some commenters agree with the Commission's proposed 
table of metrics,\320\ multiple commenters suggest additional metrics 
that should be posted.\321\ For instance, Public Interest Organizations 
request information on the available interconnection capacity 
(including, at a minimum, a snapshot of existing available 
interconnection capacity and associated tran

[…truncated; see source link]
Indexed from Federal Register on September 6, 2023.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.