Notice2023-12946

Florida Gas Transmission Company, LLC; Notice of Application and Establishing Intervention Deadline

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
June 16, 2023

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 88 Issue 116 (Friday, June 16, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 116 (Friday, June 16, 2023)]
[Notices]
[Pages 39418-39420]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-12946]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP23-492-000]


Florida Gas Transmission Company, LLC; Notice of Application and 
Establishing Intervention Deadline

    Take notice that on June 2, 2023, Florida Gas Transmission Company, 
LLC, (FGT) 1300 Main St., Houston, Texas 77002, filed an application 
under section 7(c) of the Natural Gas Act (NGA), and part 157 and 284 
of the Federal Energy Regulatory Commission's (Commission) requesting 
the authorization to increase the certificated capacity by increasing 
certain compression station from construct, install, modify, operate 
and maintain its Louisiana Project located at St. Landry, East Baton 
Rouge, and Washington Parishes, Louisiana and Perry County, Mississippi 
which will provide an additional 100,000 million cubic feet per day of 
firm transportation service back into FGT's Zone 2 and provide gas to 
downstream customers from power generation and local distribution 
companies.
    Specifically, FGT is requesting approval to (1) uprate two existing 
natural gas-fired compressor turbine units (Units 7501 and 7502), each 
from 6,500 horsepower (HP); to 7,700 HP at its Compressor station (CS) 
7.5 in St. Landry Parish, Louisiana; (2) At CS (8), add process cooling 
units to support the existing gas compressor units at FGT's existing 
Mainline in East Baton Rouge Parish; (3) At CS 9, install one new 7,700 
HP natural gas-fired turbine compressor unit on FGT's Mainline in 
Washington Parish, Louisiana; (4) At CS 10, install one new 15,900 HP 
natural gas-fired turbine compressor unit on FGT's Mainline in Perry 
County, Mississippi; (5) The total estimated cost

[[Page 39419]]

of the project is approximately $74.9 million, all as more fully set 
forth in the request which is on file with the Commission and open to 
public inspection.
    In addition to publishing the full text of this document in the 
Federal Registerthe Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (<a href="http://www.ferc.gov">www.ferc.gov</a>) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room. For assistance, contact the Federal Energy Regulatory 
Commission at <a href="/cdn-cgi/l/email-protection#2b6d4e594864454742454e785e5b5b44595f6b4d4e5948054c445d"><span class="__cf_email__" data-cfemail="fdbb988f9eb29391949398ae888d8d928f89bd9b988f9ed39a928b">[email&#160;protected]</span></a> or call toll-free, (886) 208-
3676 or TTY (202) 502-8659.
    Any questions concerning this request should be directed to Blair 
Lichtenwalter, Senior Director, Certificates, Florida Gas Transmission 
Company, LLC., 4700 1300 Main St. P.O. Box 4967, Houston, Texas 77210-
4967, by phone at (713) 989-2605, or by email at 
<a href="/cdn-cgi/l/email-protection#81c3ede0e8f3afcde8e2e9f5e4eff6e0edf5e4f3c1e4efe4f3e6f8f5f3e0eff2e7e4f3afe2eeec"><span class="__cf_email__" data-cfemail="95d7f9f4fce7bbd9fcf6fde1f0fbe2f4f9e1f0e7d5f0fbf0e7f2ece1e7f4fbe6f3f0e7bbf6faf8">[email&#160;protected]</span></a>.

Public Participation

    There are three ways to become involved in the Commission's review 
of this project: you can file a protest to the project, you can file a 
motion to intervene in the proceeding, and you can file comments on the 
project. There is no fee or cost for filing protests, motions to 
intervene, or comments. The deadline for filing protests, motions to 
intervene, and comments is 5:00 p.m. Eastern Time on July 3, 2023. How 
to file protests, motions to intervene, and comments is explained 
below.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or <a href="/cdn-cgi/l/email-protection#ace3fcfceccac9decf82cbc3da"><span class="__cf_email__" data-cfemail="49061919092f2c3b2a672e263f">[email&#160;protected]</span></a>.

Protests

    Pursuant to section 157.205 of the Commission's regulations under 
the NGA,\1\ any person \2\ or the Commission's staff may file a protest 
to the request. If no protest is filed within the time allowed or if a 
protest is filed and then withdrawn within 30 days after the allowed 
time for filing a protest, the proposed activity shall be deemed to be 
authorized effective the day after the time allowed for protest. If a 
protest is filed and not withdrawn within 30 days after the time 
allowed for filing a protest, the instant request for authorization 
will be considered by the Commission.
---------------------------------------------------------------------------

    \1\ 18 CFR 157.205.
    \2\ Persons include individuals, organizations, businesses, 
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------

    Protests must comply with the requirements specified in section 
157.205(e) of the Commission's regulations,\3\ and must be submitted by 
the protest deadline, which is July 3, 2023. A protest may also serve 
as a motion to intervene so long as the protestor states it also seeks 
to be an intervenor.
---------------------------------------------------------------------------

    \3\ 18 CFR 157.205(e).
---------------------------------------------------------------------------

Interventions

    Any person has the option to file a motion to intervene in this 
proceeding. Only intervenors have the right to request rehearing of 
Commission orders issued in this proceeding and to subsequently 
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \4\ and the regulations under the NGA \5\ by the 
intervention deadline for the project, which is July 3, 2023. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
your interest in the proceeding. For an individual, this could include 
your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene. For more information 
about motions to intervene, refer to the FERC website at <a href="https://www.ferc.gov/resources/guides/how-to/intervene.asp">https://www.ferc.gov/resources/guides/how-to/intervene.asp</a>.
---------------------------------------------------------------------------

    \4\ 18 CFR 385.214.
    \5\ 18 CFR 157.10.
---------------------------------------------------------------------------

    All timely, unopposed motions to intervene are automatically 
granted by operation of Rule 214(c)(1). Motions to intervene that are 
filed after the intervention deadline are untimely and may be denied. 
Any late-filed motion to intervene must show good cause for being late 
and must explain why the time limitation should be waived and provide 
justification by reference to factors set forth in Rule 214(d) of the 
Commission's Rules and Regulations. A person obtaining party status 
will be placed on the service list maintained by the Secretary of the 
Commission and will receive copies (paper or electronic) of all 
documents filed by the applicant and by all other parties.

Comments

    Any person wishing to comment on the project may do so. The 
Commission considers all comments received about the project in 
determining the appropriate action to be taken. To ensure that your 
comments are timely and properly recorded, please submit your comments 
on or before July 3, 2023. The filing of a comment alone will not serve 
to make the filer a party to the proceeding. To become a party, you 
must intervene in the proceeding.

How To File Protests, Interventions, and Comments

    There are two ways to submit protests, motions to intervene, and 
comments. In both instances, please reference the Project docket number 
CP23-492-000 in your submission.
    (1) You may file your protest, motion to intervene, and comments by 
using the Commission's eFiling feature, which is located on the 
Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the link to Documents and 
Filings. New eFiling users must first create an account by clicking on 
``eRegister.'' You will be asked to select the type of filing you are 
making; first select ``General'' and then select ``Protest'', 
``Intervention'', or ``Comment on a Filing''; or \6\
---------------------------------------------------------------------------

    \6\ Additionally, you may file your comments electronically by 
using the eComment feature, which is located on the Commission's 
website at <a href="http://www.ferc.gov">www.ferc.gov</a> under the link to Documents and Filings. 
Using eComment is an easy method for interested persons to submit 
brief, text-only comments on a project.
---------------------------------------------------------------------------

    (2) You can file a paper copy of your submission by mailing it to 
the address below. Your submission must reference the Project docket 
number CP23-483-000.
    To file via USPS: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426.
    To file via any other method: Kimberly D. Bose, Secretary, Federal 
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 
20852.
    The Commission encourages electronic filing of submissions (option 
1 above) and has eFiling staff available

[[Page 39420]]

to assist you at (202) 502-8258 or <a href="/cdn-cgi/l/email-protection#bcfad9cedff3d2d0d5d2d9efc9ccccd3cec8fcdad9cedf92dbd3ca"><span class="__cf_email__" data-cfemail="8ccae9feefc3e2e0e5e2e9dff9fcfce3fef8cceae9feefa2ebe3fa">[email&#160;protected]</span></a>.
    Protests and motions to intervene must be served on the applicant 
either by mail or email (with a link to the document) at: Blair 
Lichtenwalter, Senior Director, Certificates, Florida Gas Transmission 
Company, LLC., 4700 1300 Main St. P.O. Box 4967, Houston, Texas 77210-
4967, or by email at <a href="/cdn-cgi/l/email-protection#f1b39d909883dfbd98929985949f86909d859483b1949f948396888583909f82979483df929e9c"><span class="__cf_email__" data-cfemail="2c6e404d455e0260454f445849425b4d4058495e6c4942495e4b55585e4d425f4a495e024f4341">[email&#160;protected]</span></a>. Any 
subsequent submissions by an intervenor must be served on the applicant 
and all other parties to the proceeding. Contact information for 
parties can be downloaded from the service list at the eService link on 
FERC Online.

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at <a href="http://www.ferc.gov">www.ferc.gov</a> using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. For more information and to register, go to 
<a href="http://www.ferc.gov/docs-filing/esubscription.asp">www.ferc.gov/docs-filing/esubscription.asp</a>.

    Dated: June 12, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-12946 Filed 6-15-23; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on June 16, 2023.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.