Notice2023-11241
Natural Gas Pipeline Company of America, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
May 26, 2023
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 88 Issue 102 (Friday, May 26, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 102 (Friday, May 26, 2023)]
[Notices]
[Pages 34148-34149]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-11241]
[[Page 34148]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP23-477-000]
Natural Gas Pipeline Company of America, LLC; Notice of Request
Under Blanket Authorization and Establishing Intervention and Protest
Deadline
Take notice that on May 10, 2023, Natural Gas Pipeline Company of
America, LLC (NGPL), 3250 Lacey Road, Suite 700, Downers Grove,
Illinois 60515, filed in the above referenced docket, a prior notice
request pursuant to sections 157.205 and 157.216(b) of the Federal
Energy Regulatory Commission's (Commission) regulations under the
Natural Gas Act (NGA) and NGPL's blanket certificate issued in Docket
No. CP82-402-000, seeking authorization to abandon in-place its
Compressor Station 158 (CS 158) located in Dewey County, Oklahoma
(Compressor Station 158 Abandonment Project).
Specifically, NGPL states that the project consists of abandoning
in-place CS 158 facilities including a 2,745 HP compressor unit, fuel
gas heater, dehydrator, control room, auxiliary building, odorizer,
positive meter, waste sump tank, waste oil storage tank, water well,
meter building, and gas reservoir tank. NGPL states that the project
will allow abandonment of CS 158 facilities that are no longer required
due to the changes in receipt and delivery points utilized by shippers
on its system and the current operating conditions of its Mountain View
to Minneola (M&M) Line, coupled with the steady decline since 2011 of
gas produced in the Granite Wash producing area in the Anadarko Basin.
Thus, NGPL asserts that the operation of CS 158 is not needed to meet
its existing firm contractual commitments, and NGPL does not anticipate
CS 158 will be needed to meet future service obligations. NGPL
estimates the total cost of the Project to be $177,000, all as more
fully set forth in the application which is on file with the Commission
and open for public inspection.
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (<a href="http://www.ferc.gov">www.ferc.gov</a>) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room. For assistance, contact the Federal Energy Regulatory
Commission at <a href="/cdn-cgi/l/email-protection#abedced9c8e4c5c7c2c5cef8dedbdbc4d9dfebcdced9c885ccc4dd"><span class="__cf_email__" data-cfemail="3b7d5e495874555752555e684e4b4b54494f7b5d5e4958155c544d">[email protected]</span></a> or call toll-free, (886) 208-
3676 or TTY (202) 502-8659.
Any questions concerning this request should be directed to
Francisco Tarin, Director, Regulatory, for Kinder Morgan Inc., as
Operator of Natural Gas Pipeline Company of America LLC, 2 North Nevada
Avenue, Colorado Springs, Colorado 80903, at (719) 667-7515, or
<a href="/cdn-cgi/l/email-protection#a5c3d7c4cbc6ccd6c6cafad1c4d7cccbe5cecccbc1c0d7c8cad7c2c4cb8bc6cac8"><span class="__cf_email__" data-cfemail="93f5e1f2fdf0fae0f0fccce7f2e1fafdd3f8fafdf7f6e1fefce1f4f2fdbdf0fcfe">[email protected]</span></a>.
Public Participation
There are three ways to become involved in the Commission's review
of this project: you can file a protest to the project, you can file a
motion to intervene in the proceeding, and you can file comments on the
project. There is no fee or cost for filing protests, motions to
intervene, or comments. The deadline for filing protests, motions to
intervene, and comments is 5:00 p.m. Eastern Time on July 18, 2023. How
to file protests, motions to intervene, and comments is explained
below.
Protests
Pursuant to section 157.205 of the Commission's regulations under
the NGA,\1\ any person \2\ or the Commission's staff may file a protest
to the request. If no protest is filed within the time allowed or if a
protest is filed and then withdrawn within 30 days after the allowed
time for filing a protest, the proposed activity shall be deemed to be
authorized effective the day after the time allowed for protest. If a
protest is filed and not withdrawn within 30 days after the time
allowed for filing a protest, the instant request for authorization
will be considered by the Commission.
---------------------------------------------------------------------------
\1\ 18 CFR 157.205.
\2\ Persons include individuals, organizations, businesses,
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------
Protests must comply with the requirements specified in section
157.205(e) of the Commission's regulations,\3\ and must be submitted by
the protest deadline, which is July 18, 2023. A protest may also serve
as a motion to intervene so long as the protestor states it also seeks
to be an intervenor.
---------------------------------------------------------------------------
\3\ 18 CFR 157.205(e).
---------------------------------------------------------------------------
Interventions
Any person has the option to file a motion to intervene in this
proceeding. Only intervenors have the right to request rehearing of
Commission orders issued in this proceeding and to subsequently
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
To intervene, you must submit a motion to intervene to the
Commission in accordance with Rule 214 of the Commission's Rules of
Practice and Procedure \4\ and the regulations under the NGA \5\ by the
intervention deadline for the project, which is July 18, 2023. As
described further in Rule 214, your motion to intervene must state, to
the extent known, your position regarding the proceeding, as well as
your interest in the proceeding. For an individual, this could include
your status as a landowner, ratepayer, resident of an impacted
community, or recreationist. You do not need to have property directly
impacted by the project in order to intervene. For more information
about motions to intervene, refer to the FERC website at <a href="https://www.ferc.gov/resources/guides/how-to/intervene.asp">https://www.ferc.gov/resources/guides/how-to/intervene.asp</a>.
---------------------------------------------------------------------------
\4\ 18 CFR 385.214.
\5\ 18 CFR 157.10.
---------------------------------------------------------------------------
All timely, unopposed motions to intervene are automatically
granted by operation of Rule 214(c)(1). Motions to intervene that are
filed after the intervention deadline are untimely and may be denied.
Any late-filed motion to intervene must show good cause for being late
and must explain why the time limitation should be waived and provide
justification by reference to factors set forth in Rule 214(d) of the
Commission's Rules and Regulations. A person obtaining party status
will be placed on the service list maintained by the Secretary of the
Commission and will receive copies (paper or electronic) of all
documents filed by the applicant and by all other parties.
Comments
Any person wishing to comment on the project may do so. The
Commission considers all comments received about the project in
determining the appropriate action to be taken. To ensure that your
comments are timely and properly recorded, please submit your comments
on or before July 18, 2023. The filing of a comment alone will not
serve to make the filer a party to the proceeding. To become a party,
you must intervene in the proceeding.
How To File Protests, Interventions, and Comments
There are two ways to submit protests, motions to intervene, and
comments. In both instances, please reference the Project docket number
CP23-477-000 in your submission.
(1) You may file your protest, motion to intervene, and comments by
using the
[[Page 34149]]
Commission's eFiling feature, which is located on the Commission's
website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the link to Documents and Filings. New
eFiling users must first create an account by clicking on
``eRegister.'' You will be asked to select the type of filing you are
making; first select General'' and then select ``Protest'',
``Intervention'', or ``Comment on a Filing''; or \6\
---------------------------------------------------------------------------
\6\ Additionally, you may file your comments electronically by
using the eComment feature, which is located on the Commission's
website at <a href="http://www.ferc.gov">www.ferc.gov</a> under the link to Documents and Filings.
Using eComment is an easy method for interested persons to submit
brief, text-only comments on a project.
---------------------------------------------------------------------------
(2) You can file a paper copy of your submission by mailing it to
the address below. Your submission must reference the Project docket
number CP23-477-000.
To file via USPS: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Washington, DC 20426
To file via any other method: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland
20852
The Commission encourages electronic filing of submissions (option
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or <a href="/cdn-cgi/l/email-protection#42042730210d2c2e2b2c27113732322d303602242730216c252d34"><span class="__cf_email__" data-cfemail="6b2d0e190824050702050e381e1b1b04191f2b0d0e1908450c041d">[email protected]</span></a>.
Protests and motions to intervene must be served on the applicant
either by mail or email (with a link to the document) at: Francisco
Tarin, Director, Regulatory, for Kinder Morgan Inc., as Operator of
Natural Gas Pipeline Company of America LLC, 2 North Nevada Avenue,
Colorado Springs, Colorado 80903, or <a href="/cdn-cgi/l/email-protection#244256454a474d57474b7b5045564d4a644f4d4a404156494b5643454a0a474b49"><span class="__cf_email__" data-cfemail="c1a7b3a0afa2a8b2a2ae9eb5a0b3a8af81aaa8afa5a4b3acaeb3a6a0afefa2aeac">[email protected]</span></a>.
Any subsequent submissions by an intervenor must be served on the
applicant and all other parties to the proceeding. Contact information
for parties can be downloaded from the service list at the eService
link on FERC Online.
Tracking the Proceeding
Throughout the proceeding, additional information about the project
will be available from the Commission's Office of External Affairs, at
(866) 208-FERC, or on the FERC website at <a href="http://www.ferc.gov">www.ferc.gov</a> using the
``eLibrary'' link as described above. The eLibrary link also provides
access to the texts of all formal documents issued by the Commission,
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. For more information and to register, go to
<a href="http://www.ferc.gov/docs-filing/esubscription.asp">www.ferc.gov/docs-filing/esubscription.asp</a>.
Dated: May 19, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-11241 Filed 5-25-23; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on May 26, 2023.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.