Notice2023-10356
LinkPast Solutions, Inc.; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
May 16, 2023
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 88 Issue 94 (Tuesday, May 16, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 94 (Tuesday, May 16, 2023)]
[Notices]
[Page 31260]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-10356]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 15298-000]
LinkPast Solutions, Inc.; Notice of Preliminary Permit
Application Accepted for Filing and Soliciting Comments, Motions To
Intervene, and Competing Applications
On January 25, 2023, LinkPast Solutions, Inc., filed an application
for a preliminary permit, pursuant to section 4(f) of the Federal Power
Act (FPA), proposing to study the feasibility of hydropower on the
Black River in Jefferson County, New York. The sole purpose of a
preliminary permit, if issued, is to grant the permit holder priority
to file a license application during the permit term. A preliminary
permit does not authorize the permit holder to perform any land-
disturbing activities or otherwise enter upon lands or waters owned by
others without the owners' express permission.
The proposed Great Mills Hydro Project (Plant #1) would consist of
the following: (1) a new 330-foot-long concrete gravity dam at the site
of an existing breached dam; (2) an impoundment with an approximate
surface area of 220 acres and a storage capacity of 1,100 acre-feet at
a normal pool elevation of 609.05 feet National Geodetic Vertical Datum
of 1929; (4) a new 85-foot-long by 65-foot-wide reinforced concrete
powerhouse housing two or more axial flow vertical turbine-generator
units with a total installed capacity of 5 megawatts; (5) additional
new DIVE-turbine-generator (generator directly connected to the turbine
shaft that can be completely submerged) units to utilize flows below
the minimum or above the maximum hydraulic capacities of the main
powerhouse; (6) a new 50-foot-long by 50-foot-wide switchyard; (7) two
new access roads, one on the north and the other on the south shores of
the river; (8) a new 2.23-mile-long, 115-kilovolt transmission line;
and (9) appurtenant facilities. The proposed project would have an
average annual generation of 24,500 megawatt-hours.
Applicant Contact: Brian McArthur, LinkPast Solutions, Inc., P.O.
Box 5474, Clark, New Jersey 07066; phone: (848) 628-4414.
FERC Contact: Monir Chowdhury; phone: (202) 502-6736.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, notices of intent, and competing
applications using the Commission's eFiling system at <a href="https://ferconline.ferc.gov/FERCOnline.aspx">https://ferconline.ferc.gov/FERCOnline.aspx</a>. Commenters can submit brief
comments up to 6,000 characters, without prior registration, using the
eComment system at <a href="https://ferconline.ferc.gov/QuickComment.aspx">https://ferconline.ferc.gov/QuickComment.aspx</a>. You
must include your name and contact information at the end of your
comments. For assistance, please contact FERC Online Support at
<a href="/cdn-cgi/l/email-protection#f3b5b6a1b0bc9d9f9a9d96a08683839c8187b395968190dd949c85"><span class="__cf_email__" data-cfemail="eea8abbcada1808287808bbd9b9e9e819c9aae888b9c8dc0898198">[email protected]</span></a>, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy.
Submissions sent via the U.S. Postal Service must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via
any other carrier must be addressed to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
Maryland 20852.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of the
Commission's website at <a href="https://elibrary.ferc.gov/eLibrary/search">https://elibrary.ferc.gov/eLibrary/search</a>.
Enter the docket number (P-15298) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Dated: May 9, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-10356 Filed 5-15-23; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on May 16, 2023.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.