Notice2023-09487
Green Mountain Power Corporation; Notice of Intent To Prepare an Environmental Assessment
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
May 4, 2023
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 88 Issue 86 (Thursday, May 4, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 86 (Thursday, May 4, 2023)]
[Notices]
[Page 28536]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-09487]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2445-028]
Green Mountain Power Corporation; Notice of Intent To Prepare an
Environmental Assessment
On December 23, 2021, Green Mountain Power Corporation filed a
relicense application for the 275-kilowatt Center Rutland Hydroelectric
Project No. 2445 (project). The project is located on Otter Creek in
Rutland County, Vermont.
In accordance with the Commission's regulations, on February 17,
2023, Commission staff issued a notice that the project was ready for
environmental analysis (REA Notice). Based on the information in the
record, including comments filed on the REA Notice, staff does not
anticipate that licensing the project would constitute a major federal
action significantly affecting the quality of the human environment.
Therefore, staff intends to prepare an Environmental Assessment (EA) on
the application to relicense the project.
The EA will be issued and circulated for review by all interested
parties. All comments filed on the EA will be analyzed by staff and
considered in the Commission's final licensing decision.
The application will be processed according to the following
schedule. Revisions to the schedule may be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Commission issues EA...................... October 2023.\1\
Comments on EA............................ November 2023.
------------------------------------------------------------------------
Any questions regarding this notice may be directed to Nicholas
Tackett at (202) 502-6783 or <a href="/cdn-cgi/l/email-protection#145a7d777c7b7875673a4075777f71606054727166773a737b62"><span class="__cf_email__" data-cfemail="bcf2d5dfd4d3d0ddcf92e8dddfd7d9c8c8fcdad9cedf92dbd3ca">[email protected]</span></a>.
---------------------------------------------------------------------------
\1\ The Council on Environmental Quality's (CEQ) regulations
under 40 CFR 1501.10(b)(1) require that EAs be completed within 1
year of the federal action agency's decision to prepare an EA. This
notice establishes the Commission's intent to prepare an EA for the
Center Rutland Hydroelectric Project. Therefore, in accordance with
CEQ's regulations, the EA must be issued within 1 year of the
issuance date of this notice.
Dated: April 28, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-09487 Filed 5-3-23; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on May 4, 2023.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.