Notice2023-06695
Nevada Power Company; Notice Granting Motion To Hold Proceeding in Abeyance
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
March 31, 2023
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 88 Issue 62 (Friday, March 31, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 62 (Friday, March 31, 2023)]
[Notices]
[Pages 19300-19301]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-06695]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL23-27-000]
Nevada Power Company; Notice Granting Motion To Hold Proceeding
in Abeyance
On March 16, 2023, Nevada Power Company and Sierra Pacific Power
Company (collectively, Nevada Power) filed a joint motion to hold the
show cause proceeding in the above-captioned docket \1\ in abeyance
while the Commission considers a concurrently filed Federal Power Act
(FPA) section 205 filing made by Nevada Power in Docket No. ER23-1406-
000.
---------------------------------------------------------------------------
\1\ Nev. Power Co., 182 FERC ] 61,051 (2023) (Show Cause Order)
(finding that Nevada Power's Large Generator Interconnection
Procedures appear to be unjust, unreasonable, unduly discriminatory
or preferential, or otherwise unlawful and instituting a show cause
proceeding pursuant to FPA section 206).
---------------------------------------------------------------------------
Nevada Power states that, in the FPA section 205 filing, it
proposes revisions to its tariff to specify the method for allocating
network upgrade costs among interconnection customers in a cluster.
Nevada Power represents that good cause exists to hold the show cause
proceeding in Docket No. EL23-27-000 in abeyance because if the
Commission accepts the proposed revisions to Nevada Power's tariff in
Docket No. ER23-1406-000, then the basis for the Show Cause Order would
be addressed.
Upon consideration, notice is hereby given that Nevada Power's
motion is granted and the show cause proceeding in Docket No. EL23-27-
000 will be held in abeyance pending the Commission's consideration of
the filing in Docket No. ER23-1406-000.
[[Page 19301]]
Dated: March 27, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-06695 Filed 3-30-23; 8:45 am]
BILLING CODE 6717-01-P
</pre></body>
</html>Indexed from Federal Register on March 31, 2023.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.