Notice2023-06695

Nevada Power Company; Notice Granting Motion To Hold Proceeding in Abeyance

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
March 31, 2023

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 88 Issue 62 (Friday, March 31, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 62 (Friday, March 31, 2023)]
[Notices]
[Pages 19300-19301]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-06695]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EL23-27-000]


Nevada Power Company; Notice Granting Motion To Hold Proceeding 
in Abeyance

    On March 16, 2023, Nevada Power Company and Sierra Pacific Power 
Company (collectively, Nevada Power) filed a joint motion to hold the 
show cause proceeding in the above-captioned docket \1\ in abeyance 
while the Commission considers a concurrently filed Federal Power Act 
(FPA) section 205 filing made by Nevada Power in Docket No. ER23-1406-
000.
---------------------------------------------------------------------------

    \1\ Nev. Power Co., 182 FERC ] 61,051 (2023) (Show Cause Order) 
(finding that Nevada Power's Large Generator Interconnection 
Procedures appear to be unjust, unreasonable, unduly discriminatory 
or preferential, or otherwise unlawful and instituting a show cause 
proceeding pursuant to FPA section 206).
---------------------------------------------------------------------------

    Nevada Power states that, in the FPA section 205 filing, it 
proposes revisions to its tariff to specify the method for allocating 
network upgrade costs among interconnection customers in a cluster. 
Nevada Power represents that good cause exists to hold the show cause 
proceeding in Docket No. EL23-27-000 in abeyance because if the 
Commission accepts the proposed revisions to Nevada Power's tariff in 
Docket No. ER23-1406-000, then the basis for the Show Cause Order would 
be addressed.
    Upon consideration, notice is hereby given that Nevada Power's 
motion is granted and the show cause proceeding in Docket No. EL23-27-
000 will be held in abeyance pending the Commission's consideration of 
the filing in Docket No. ER23-1406-000.


[[Page 19301]]


    Dated: March 27, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-06695 Filed 3-30-23; 8:45 am]