Notice2023-04451
National Fuel Gas Supply Corporation; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
March 6, 2023
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 88 Issue 43 (Monday, March 6, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 43 (Monday, March 6, 2023)]
[Notices]
[Pages 13819-13820]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-04451]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP23-72-000]
National Fuel Gas Supply Corporation; Notice of Request Under
Blanket Authorization and Establishing Intervention and Protest
Deadline
Take notice that on February 17, 2023, National Fuel Gas Supply
Corporation (National Fuel) 6363 Main Street, Williamsville, New York
14221, filed a prior notice request pursuant to Sections 157.205,
157.208, and 157.213 of the Commission's regulations under the Natural
Gas Act and the blanket certificate issued by the Commission in Docket
No. CP83-4-000,\1\ requesting authorization to construct and operate
its Lawtons Well 7459 Project that consists of one new injection/
withdrawal storage well, related pipeline and appurtenances at its
Lawtons Storage Field in Erie County, New York. The new well is
proposed to improve the deliverability of the field, to allow more
efficient withdrawal of inventory. National Fuel states that the
Lawtons Well 7459 Project will have no impact on the Lawtons Storage
Field's certificated physical parameters. The estimated cost of the
project is approximately $2.91 million, all as more fully set forth in
the request which is on file with the Commission and open to public
inspection.
---------------------------------------------------------------------------
\1\ National Fuel Gas Supply Corporation, 21 FERC ] 62,298
(1982).
---------------------------------------------------------------------------
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (<a href="http://www.ferc.gov">www.ferc.gov</a>) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room, due to the proclamation declaring a National Emergency
concerning the Novel Coronavirus Disease (COVID-19), issued by the
President on March 13, 2020. For assistance, contact the Federal Energy
Regulatory Commission at <a href="/cdn-cgi/l/email-protection#90d6d5c2d3dffefcf9fef5c3e5e0e0ffe2e4d0f6f5e2f3bef7ffe6"><span class="__cf_email__" data-cfemail="54121106171b3a383d3a31072124243b262014323126377a333b22">[email protected]</span></a> or call toll-free,
(886) 208-3676 or TTY, (202) 502-8659.
Any questions concerning this application should be directed to
Alice A. Curtiss, Deputy General Counsel for National Fuel Gas Supply
Corporation, 6363 Main Street, Williamsville, New York 14221; by phone
at (716) 857-7075, or by email to <a href="/cdn-cgi/l/email-protection#482b3d3a3c213b3b290826293c2e3d2d24662b2725"><span class="__cf_email__" data-cfemail="482b3d3a3c213b3b290826293c2e3d2d24662b2725">[email protected]</span></a>.
Public Participation
There are three ways to become involved in the Commission's review
of this project: you can file a protest to the project, you can file a
motion to intervene in the proceeding, and you can file comments on the
project. There is no fee or cost for filing protests, motions to
intervene, or comments. The deadline for filing protests, motions to
intervene, and comments is 5:00 p.m. Eastern Time on April 28, 2023.
How to file protests, motions to intervene, and comments is explained
below.
Protests
Pursuant to section 157.205 of the Commission's regulations under
the NGA,\2\ any person \3\ or the Commission's staff may file a protest
to the request. If no protest is filed within the time allowed or if a
protest is filed and then withdrawn within 30 days after the
[[Page 13820]]
allowed time for filing a protest, the proposed activity shall be
deemed to be authorized effective the day after the time allowed for
protest. If a protest is filed and not withdrawn within 30 days after
the time allowed for filing a protest, the instant request for
authorization will be considered by the Commission.
---------------------------------------------------------------------------
\2\ 18 CFR 157.205.
\3\ Persons include individuals, organizations, businesses,
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------
Protests must comply with the requirements specified in section
157.205(e) of the Commission's regulations,\4\ and must be submitted by
the protest deadline, which is April 28, 2023. A protest may also serve
as a motion to intervene so long as the protestor states it also seeks
to be an intervenor.
---------------------------------------------------------------------------
\4\ 18 CFR 157.205(e).
---------------------------------------------------------------------------
Interventions
Any person has the option to file a motion to intervene in this
proceeding. Only intervenors have the right to request rehearing of
Commission orders issued in this proceeding and to subsequently
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
To intervene, you must submit a motion to intervene to the
Commission in accordance with Rule 214 of the Commission's Rules of
Practice and Procedure \5\ and the regulations under the NGA \6\ by the
intervention deadline for the project, which is April 28, 2023. As
described further in Rule 214, your motion to intervene must state, to
the extent known, your position regarding the proceeding, as well as
your interest in the proceeding. For an individual, this could include
your status as a landowner, ratepayer, resident of an impacted
community, or recreationist. You do not need to have property directly
impacted by the project in order to intervene. For more information
about motions to intervene, refer to the FERC website at <a href="https://www.ferc.gov/resources/guides/how-to/intervene.asp">https://www.ferc.gov/resources/guides/how-to/intervene.asp</a>.
---------------------------------------------------------------------------
\5\ 18 CFR 385.214.
\6\ 18 CFR 157.10.
---------------------------------------------------------------------------
All timely, unopposed motions to intervene are automatically
granted by operation of Rule 214(c)(1). Motions to intervene that are
filed after the intervention deadline are untimely and may be denied.
Any late-filed motion to intervene must show good cause for being late
and must explain why the time limitation should be waived and provide
justification by reference to factors set forth in Rule 214(d) of the
Commission's Rules and Regulations. A person obtaining party status
will be placed on the service list maintained by the Secretary of the
Commission and will receive copies (paper or electronic) of all
documents filed by the applicant and by all other parties.
Comments
Any person wishing to comment on the project may do so. The
Commission considers all comments received about the project in
determining the appropriate action to be taken. To ensure that your
comments are timely and properly recorded, please submit your comments
on or before April 28, 2023. The filing of a comment alone will not
serve to make the filer a party to the proceeding. To become a party,
you must intervene in the proceeding.
How To File Protests, Interventions, and Comments
There are two ways to submit protests, motions to intervene, and
comments. In both instances, please reference the project docket number
CP23-72-000 in your submission.
(1) You may file your protest, motion to intervene, and comments by
using the Commission's eFiling feature, which is located on the
Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the link to Documents and
Filings. New eFiling users must first create an account by clicking on
``eRegister.'' You will be asked to select the type of filing you are
making; first select ``General'' and then select ``Protest'',
``Intervention'', or ``Comment on a Filing.'' The Commission's eFiling
staff are available to assist you at (202) 502-8258 or
<a href="/cdn-cgi/l/email-protection" class="__cf_email__" data-cfemail="23654651406c4d4f4a4d46705653534c515763454651400d444c55">[email protected]</a>.
(2) You can file a paper copy of your submission. Your submission
must reference the project docket number CP23-72-000.
To mail via USPS, use the following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426
To send via any other courier, use the following address: Kimberly D.
Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852
Protests and motions to intervene must be served on the applicant
either by mail or email (with a link to the document) at: Alice A.
Curtiss, Deputy General Counsel for National Fuel Gas Supply
Corporation, 6363 Main Street, Williamsville, New York 14221; or by
email to <a href="/cdn-cgi/l/email-protection#b7d4c2c5c3dec4c4d6f7d9d6c3d1c2d2db99d4d8da"><span class="__cf_email__" data-cfemail="44273136302d373725042a2530223121286a272b29">[email protected]</span></a>.
Any subsequent submissions by an intervenor must be served on the
applicant and all other parties to the proceeding. Contact information
for parties can be downloaded from the service list at the eService
link on FERC Online.
Tracking the Proceeding
Throughout the proceeding, additional information about the project
will be available from the Commission's Office of External Affairs, at
(866) 208-FERC, or on the FERC website at <a href="http://www.ferc.gov">www.ferc.gov</a> using the
``eLibrary'' link as described above. The eLibrary link also provides
access to the texts of all formal documents issued by the Commission,
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. For more information and to register, go to
<a href="http://www.ferc.gov/docs-filing/esubscription.asp">www.ferc.gov/docs-filing/esubscription.asp</a>.
Dated: February 27, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-04451 Filed 3-3-23; 8:45 am]
BILLING CODE P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on March 6, 2023.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.