Notice2023-01935
Allete, Inc.; Notice of Intent To Prepare an Environmental Assessment
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
January 31, 2023
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 88 Issue 20 (Tuesday, January 31, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 20 (Tuesday, January 31, 2023)]
[Notices]
[Page 6250]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-01935]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2362-044]
Allete, Inc.; Notice of Intent To Prepare an Environmental
Assessment
On December 20, 2021, Allete, Inc. filed a relicense application
for the 2.1-megawatt Grand Rapids Hydroelectric Project No. 2362
(project). The project is located on the Mississippi River near the
City of Grand Rapids in Itasca County, Minnesota. The project does not
occupy Federal land.
In accordance with the Commission's regulations, on October 28,
2022, Commission staff issued a notice that the project was ready for
environmental analysis (REA notice). Based on the information in the
record, staff does not anticipate that licensing the project would
constitute a major Federal action significantly affecting the quality
of the human environment. Therefore, staff intends to prepare an
Environmental Assessment (EA) on the application to relicense the
project.
The EA will be issued and circulated for review by all interested
parties. All comments filed on the EA will be analyzed by staff and
considered in the Commission's final licensing decision.
The application will be processed according to the following
schedule. Revisions to the schedule may be made as appropriate.
---------------------------------------------------------------------------
\1\ The Council on Environmental Quality's (CEQ) regulations
under 40 CFR 1501.10(b)(1) require that EAs be completed within 1
year of the Federal action agency's decision to prepare an EA. This
notice establishes the Commission's intent to prepare an EA for the
Grand Rapids Project. Therefore, in accordance with CEQ's
regulations, the EA must be issued within 1 year of the issuance
date of this notice.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Commission issues EA................... August 2023.\1\
Comments on EA......................... September 2023.
------------------------------------------------------------------------
Any questions regarding this notice may be directed to Laura
Washington at <a href="/cdn-cgi/l/email-protection#a0ccc1d5d2c18ed7c1d3c8c9cec7d4cfcee0c6c5d2c38ec7cfd6"><span class="__cf_email__" data-cfemail="422e233730236c3523312a2b2c25362d2c02242730216c252d34">[email protected]</span></a> or (202) 502-6072.
Dated: January 25, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-01935 Filed 1-30-23; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on January 31, 2023.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.