Notice2023-01933

Allete, Inc.; Notice of Intent To Prepare an Environmental Assessment

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
January 31, 2023

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 88 Issue 20 (Tuesday, January 31, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 20 (Tuesday, January 31, 2023)]
[Notices]
[Page 6255]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-01933]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2361-056]


Allete, Inc.; Notice of Intent To Prepare an Environmental 
Assessment

    On December 20, 2021, Allete, Inc. filed a relicense application 
for the 1.1-megawatt Prairie River Project No. 2361 (project). The 
project is located On the Prairie River, near the Township of Arbo in 
Itasca County, Minnesota. The project does not occupy Federal land.
    In accordance with the Commission's regulations, on October 28, 
2022, Commission staff issued a notice that the project was ready for 
environmental analysis (REA notice). Based on the information in the 
record, staff does not anticipate that licensing the project would 
constitute a major Federal action significantly affecting the quality 
of the human environment. Therefore, staff intends to prepare an 
Environmental Assessment (EA) on the application to relicense the 
project.
    The EA will be issued and circulated for review by all interested 
parties. All comments filed on the EA will be analyzed by staff and 
considered in the Commission's final licensing decision.
    The application will be processed according to the following 
schedule. Revisions to the schedule may be made as appropriate.

------------------------------------------------------------------------
               Milestone                           Target date
------------------------------------------------------------------------
Commission issues EA...................  August 2023.\1\
Comments on EA.........................  September 2023.
------------------------------------------------------------------------

    Any questions regarding this notice may be directed to Laura 
Washington at <a href="/cdn-cgi/l/email-protection#0864697d7a69267f697b6061666f7c6766486e6d7a6b266f677e"><span class="__cf_email__" data-cfemail="a4c8c5d1d6c58ad3c5d7cccdcac3d0cbcae4c2c1d6c78ac3cbd2">[email&#160;protected]</span></a> or (202) 502-6072.
---------------------------------------------------------------------------

    \1\ The Council on Environmental Quality's (CEQ) regulations 
under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 
year of the Federal action agency's decision to prepare an EA. This 
notice establishes the Commission's intent to prepare an EA for the 
Prairie River Project. Therefore, in accordance with CEQ's 
regulations, the EA must be issued within 1 year of the issuance 
date of this notice.

    Dated: January 25, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-01933 Filed 1-30-23; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>