Notice2023-01492
Venture Global CP2 LNG, LLC, Venture Global CP Express, LLC; Notice of Availability of the Draft Environmental Impact Statement for the Proposed CP2 LNG AND CP Express Project
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
January 26, 2023
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 88 Issue 17 (Thursday, January 26, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 17 (Thursday, January 26, 2023)]
[Notices]
[Pages 4995-4996]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-01492]
[[Page 4995]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP22-21-000; Docket No. CP22-22-000]
Venture Global CP2 LNG, LLC, Venture Global CP Express, LLC;
Notice of Availability of the Draft Environmental Impact Statement for
the Proposed CP2 LNG AND CP Express Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) has prepared a draft environmental impact statement (EIS)
for the CP2 LNG and CP Express Projects (Project), proposed by Venture
Global CP2 LNG, LLC (CP2 LNG) and Venture Global CP Express, LLC (CP
Express) in the above-referenced dockets. CP2 LNG and CP Express
request authorizations to construct, install, own, operate, and
maintain certain liquefied natural gas (LNG) facilities in Cameron
Parish, Louisiana and certain pipeline facilities in Cameron and
Calcasieu Parishes, Louisiana and Jasper and Newton Counties, Texas.
The draft EIS assesses the potential environmental effects of the
construction and operation of the Project in accordance with the
requirements of the National Environmental Policy Act (NEPA). The FERC
staff concludes that approval of the proposed Project, with the
mitigation measures recommended in the EIS, would have some adverse
environmental impact. However, most of these impacts would be avoided
or reduced to less-than-significant levels, with the exception of
climate change and visual resources, including cumulative visual
impacts, and visual impacts on environmental justice communities in the
region. Climate change impacts are not characterized in the EIS as
significant or insignificant.
The U.S. Army Corps of Engineers New Orleans and Galveston
Districts, U.S. Department of Energy, U.S. Coast Guard, U.S. Department
of Transportation's Pipeline and Hazardous Materials Safety
Administration, and National Marine Fisheries Service participated as
cooperating agencies in the preparation of the EIS. Cooperating
agencies have jurisdiction by law or special expertise with respect to
resources potentially affected by the proposal and participate in the
NEPA analysis. The U.S. Army Corps of Engineers New Orleans and
Galveston Districts will adopt and use the EIS to consider compliance
with Section 404 of the Clean Water Act of 1972, as amended and Section
10 of the Rivers and Harbors Act of 1899. Although the cooperating
agencies provided input to the conclusions and recommendations
presented in the draft EIS, the agencies will present their own
conclusions and recommendations in their respective Records of Decision
for the Project.
The draft EIS addresses the potential environmental effects of the
construction and operation of the following Project facilities:
<bullet> a liquefaction plant consisting of 18 liquefaction blocks
and ancillary support facilities, each block having a nameplate
capacity of about 1.1 million tonnes per annum of LNG;
<bullet> six pretreatment systems, each including an amine gas-
sweetening unit to remove carbon dioxide (CO<INF>2</INF>) and a
molecular sieve dehydration system to remove water;
<bullet> four 200,000 cubic meter aboveground full containment LNG
storage tanks (two per phase) with cryogenic pipeline connections to
the liquefaction plant and to the berthing docks;
<bullet> carbon capture and sequestration facilities, including
carbon capture equipment within the terminal site as well as a non-
jurisdictional CO<INF>2</INF> send-out pipeline outside of the terminal
site; \1\
---------------------------------------------------------------------------
\1\ CP2 LNG anticipates this pipeline would be installed under
the southern portion of the Terminal Site floodwall and terminate at
a non-jurisdictional offshore platform in State of Louisiana waters.
---------------------------------------------------------------------------
<bullet> a combined cycle natural gas turbine power plant with a
nameplate capacity of 1,470 megawatts;
<bullet> two marine LNG loading docks and turning basins and two
cryogenic lines for LNG transfer from the storage tanks to the docks;
<bullet> administration, control, maintenance, and warehouse
buildings and related parking lots;
<bullet> 85.4 miles of 48-inch-diameter natural gas pipeline (CP
Express Pipeline);
<bullet> 6.0 miles of 24-inch-diameter natural gas lateral pipeline
connecting to the CP Express Pipeline in northwest Calcasieu Parish
(Enable Gulf Run Lateral);
<bullet> one 187,000-horsepower natural gas-fired compressor
station (Moss Lake Compressor Station);
<bullet> six meter stations (five at interconnects with existing
pipelines and one at the terminus of the CP Express Pipeline within the
Terminal Site); and
<bullet> other appurtenant facilities.\2\
---------------------------------------------------------------------------
\2\ The LNG terminal would also include the following non-
jurisdictional facilities: electrical transmission line and
substation, water pipeline, septic system, and stormwater
facilities/outfalls.
---------------------------------------------------------------------------
The Commission mailed a copy of the Notice of Availability of the
draft EIS to federal, state, and local government representatives and
agencies; elected officials; environmental and public interest groups;
Native American tribes; potentially affected landowners and other
interested individuals and groups; and newspapers and libraries in the
Project area. The draft EIS is only available in electronic format. It
may be viewed and downloaded from the FERC's website (<a href="http://www.ferc.gov">www.ferc.gov</a>), on
the natural gas environmental documents page (<a href="https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents">https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents</a>). In
addition, the draft EIS may be accessed by using the eLibrary link on
the FERC's website. Click on the eLibrary link (<a href="https://elibrary.ferc.gov/eLibrary/search">https://elibrary.ferc.gov/eLibrary/search</a>) select ``General Search'' and enter
the docket number in the ``Docket Number'' field, excluding the last
three digits (i.e. CP22-21 or CP22-22). Be sure you have selected an
appropriate date range. For assistance, please contact FERC Online
Support at <a href="/cdn-cgi/l/email-protection#0e486b7c6d41606267606b5d7b7e7e617c7a4e686b7c6d20696178"><span class="__cf_email__" data-cfemail="571132253418393b3e393204222727382523173132253479303821">[email protected]</span></a> or toll free at (866) 208-3676,
or for TTY, contact (202) 502-8659.
The number of pages in the draft EIS exceeds the page limits set
forth in the Council on Environmental Quality's July 16, 2020 final
rule, Update to the Regulations Implementing the Procedural Provisions
of the National Environmental Policy Act (85 FR 43304). Noting the
scope and complexity of the proposed action and action alternatives,
the Director of the Office of Energy Projects, as our senior agency
official, has authorized this page limit exceedance for this draft EIS.
The draft EIS is not a decision document. It presents Commission
staff's independent analysis of the environmental issues for the
Commission to consider when addressing the merits of all issues in this
proceeding. Any person wishing to comment on the draft EIS may do so.
Your comments should focus on draft EIS's disclosure and discussion of
potential environmental effects, measures to avoid or lessen
environmental impacts, and the completeness of the submitted
alternatives, information, and analyses. To ensure consideration of
your comments on the proposal in the final EIS, it is important that
the Commission receive your comments on or before 5:00 p.m. Eastern
Time on March 13, 2023.
For your convenience, there are four methods you can use to submit
your comments to the Commission. The
[[Page 4996]]
Commission will provide equal consideration to all comments received,
whether filed in written form or provided orally. The Commission
encourages electronic filing of comments and has staff available to
assist you at (866) 208-3676 or <a href="/cdn-cgi/l/email-protection#d395b6a1b09cbdbfbabdb680a6a3a3bca1a793b5b6a1b0fdb4bca5"><span class="__cf_email__" data-cfemail="3a7c5f485975545653545f694f4a4a55484e7a5c5f4859145d554c">[email protected]</span></a>. Please
carefully follow these instructions so that your comments are properly
recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the link to
FERC Online. This is an easy method for submitting brief, text-only
comments on a project;
(2) You can file your comments electronically by using the eFiling
feature also on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the link
to FERC Online. With eFiling, you can provide comments in a variety of
formats by attaching them as a file with your submission. New eFiling
users must first create an account by clicking on ``eRegister.'' If you
are filing a comment on a particular project, please select ``Comment
on a Filing'' as the filing type;
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the Project docket number (CP22-21
and CP22-22) on your letter. Submissions sent via the U.S. Postal
Service must be addressed to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville, Maryland 20852; or
(4) In lieu of sending written or electronic comments, the
Commission invites you to attend one of the public comment sessions its
staff will conduct in the Project area to receive comments on the draft
EIS, scheduled as follows:
------------------------------------------------------------------------
Date and Time Location
------------------------------------------------------------------------
Wednesday, March 1, 2023, 5:00 p.m.-8:00 Ward 7 Community Center,
p.m. 1615 Horridge Street,
Vinton, LA 70668, (337) 589-
5181.
Thursday, March 2, 2023, 5:00 p.m.-8:00 Cameron Parish Police Jury
p.m. Room, 148 Smith Circle,
Cameron, LA 70631, (337)
775-5718.
------------------------------------------------------------------------
The primary goal of these comment sessions is to have you identify
the specific environmental issues and concerns with the draft EIS.
Individual oral comments will be taken on a one-on-one basis with a
court reporter. This format is designed to receive the maximum amount
of oral comments, in a convenient way during the timeframe allotted.
Each comment session is scheduled from 5:00 p.m. to 8:00 p.m.
Central Standard Time. You may arrive at any time after 5:00 p.m. There
will not be a formal presentation by Commission staff when the session
opens. If you wish to speak, the Commission staff will hand out numbers
in the order of your arrival. Comments will be taken until 8:00 p.m.
However, if no additional numbers have been handed out and all
individuals who wish to provide comments have had an opportunity to do
so, staff may conclude the session at 7:30 p.m.
Your oral comments will be recorded by the court reporter (with
FERC staff or representative present) and become part of the public
record for this proceeding. Transcripts will be publicly available on
FERC's eLibrary system (see page 3 for instructions on using eLibrary).
If a significant number of people are interested in providing oral
comments in the one-on-one settings, a time limit of 5 minutes may be
implemented for each commentor. Although there will not be a formal
presentation, Commission staff will be available throughout the comment
session to answer your questions about the environmental review
process.
It is important to note that the Commission provides equal
consideration to all comments received, whether filed in written form
or provided orally at a comment session.
Any person seeking to become a party to the proceeding must file a
motion to intervene pursuant to Rule 214 of the Commission's Rules of
Practice and Procedures (18 CFR part 385.214). Motions to intervene are
more fully described at <a href="https://www.ferc.gov/how-intervene">https://www.ferc.gov/how-intervene</a>. Only
intervenors have the right to seek rehearing or judicial review of the
Commission's decision. The Commission grants affected landowners and
others with environmental concerns intervenor status upon showing good
cause by stating that they have a clear and direct interest in this
proceeding which no other party can adequately represent. Simply filing
environmental comments will not give you intervenor status, but you do
not need intervenor status to have your comments considered.
Questions?
Additional information about the Project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website (<a href="http://www.ferc.gov">www.ferc.gov</a>) using the eLibrary link. The eLibrary link
also provides access to the texts of all formal documents issued by the
Commission, such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription that allows you to keep track of all formal issuances and
submittals in specific dockets. This can reduce the amount of time you
spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to
register for eSubscription.
Dated: January 19, 2023.
Kimberly D. Bose,
Secretary.
Appendix 1
Session Format
FERC is conducting the session to solicit your comments on the
Draft Environmental Impact Statement. There will not be a formal
presentation by Commission staff; however, FERC staff is available
to answer questions about the environmental review process. The
session format is as follows:
<bullet> Tickets are handed out on a ``first come, first serve''
basis starting at the time listed in the Notice.
<bullet> Individuals are called in ticket number order to
provide oral comments to be transcribed by a court reporter for the
public record.
<bullet> Time limits on oral comments may be enforced to ensure
that all those wishing to comment have the opportunity to do so
within the designated session time.
<bullet> Written comments may be submitted in addition to, or in
lieu of, oral comments.
<bullet> Additional materials about FERC and the environmental
review process are available at information stations at the session.
Session Conduct
Proper conduct will help the sessions maintain a respectful
atmosphere for attendees to learn about the FERC Environmental
Review Process and to be able to provide comments effectively.
<bullet> Loudspeakers, lighting, oversized visual aids, or other
visual or audible disturbances are not permitted.
<bullet> Disruptive video and photographic equipment may not be
used.
<bullet> Conversations should be kept to a reasonable volume.
Attendees should be respectful of those providing oral comments to
the court reporters.
<bullet> Recorded interviews are not permitted within the
session space.
<bullet> FERC reserves the right end the session if disruptions
interfere with the opportunity for individuals to provide oral
comments or if there is a safety or security risk.
[FR Doc. 2023-01492 Filed 1-25-23; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on January 26, 2023.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.