Full Text
<html>
<head>
<title>Federal Register, Volume 88 Issue 5 (Monday, January 9, 2023)</title>
</head>
<body><pre>
[Federal Register Volume 88, Number 5 (Monday, January 9, 2023)]
[Notices]
[Page 1218]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2023-00098]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 15289-000]
Peak Hour Power, LLC; Notice of Preliminary Permit Application
Accepted for Filing and Soliciting Comments, Motions To Intervene, and
Competing Applications
On October 25, 2022, Peak Hour Power, LLC, filed an application for
a preliminary permit, pursuant to section 4(f) of the Federal Power Act
(FPA), proposing to study the feasibility of the Silver Creek Pumped
Storage Project to be located at Blythe Township in Schuylkill County,
Pennsylvania. The sole purpose of a preliminary permit, if issued, is
to grant the permit holder priority to file a license application
during the permit term. A preliminary permit does not authorize the
permit holder to perform any land-disturbing activities or otherwise
enter upon lands or waters owned by others without the owners' express
permission.
The proposed project would consist of the following: (1) a new
upper reservoir with a surface area of 150 acres and a storage capacity
of 8,000 to 10,000 acre-feet at a pool elevation between 1,650 to 1,700
feet above sea level (asl) and 1,750 to 1,800 feet asl created through
construction of a roller-compacted concrete or rock-fill semi-circular
dam and/or dike; (2) a new lower reservoir with a surface area of 100
acres and a storage capacity of 10,000 acre-feet at a pool elevation
between 1,200 to 1,300 feet asl at the site of the existing Silver
Creek reservoir and neighboring abandoned mine land; (3) a new 3,000-
foot-long, 25-foot-diameter penstock connecting the upper reservoir and
the underground powerhouse; (4) a new 250-foot-long, 70-foot-wide, 120-
foot-high underground powerhouse containing two 125-megawatt (MW)
pumping-generating units with a total installed capacity of 250 MW; (5)
a new 2-mile-long, 230-kilovolt transmission line; and (6) appurtenant
facilities. The proposed project would have an annual generation of
784,750 megawatt-hours.
Applicant Contact: Paul A. DiRenzo, Jr., Peak Hour Power, LLC, 214
Norwegian Woods Drive, Pottsville, PA 17901; email:
<a href="/cdn-cgi/l/email-protection#e19184808a898e9493918e968493a1828e8c82809295cf8f8495"><span class="__cf_email__" data-cfemail="f3839692989b9c8681839c849681b3909c9e90928087dd9d9687">[email protected]</span></a>; phone: (570) 617-7810.
FERC Contact: Woohee Choi; email: <a href="/cdn-cgi/l/email-protection#8cfbe3e3e4e9e9a2efe4e3e5cceae9feefa2ebe3fa"><span class="__cf_email__" data-cfemail="1e697171767b7b307d7671775e787b6c7d30797168">[email protected]</span></a>; phone:
(202) 502-6336.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, notices of intent, and competing
applications using the Commission's eFiling system at <a href="https://ferconline.ferc.gov/eFiling.aspx">https://ferconline.ferc.gov/eFiling.aspx</a>. Commenters can submit brief comments
up to 6,000 characters, without prior registration, using the eComment
system at <a href="https://ferconline.ferc.gov/QuickComment.aspx">https://ferconline.ferc.gov/QuickComment.aspx</a>. You must
include your name and contact information at the end of your comments.
For assistance, please contact FERC Online Support. In lieu of
electronic filing, you may submit a paper copy. Submissions sent via
the U.S. Postal Service must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Room 1A, Washington, DC 20426. Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.
The first page of any filing should include docket number P-15289-000.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of the
Commission's website at <a href="http://www.ferc.gov/docs-filing/elibrary.asp">http://www.ferc.gov/docs-filing/elibrary.asp</a>.
Enter the docket number (P-15289) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Dated: December 29, 2022.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-00098 Filed 1-6-23; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on January 9, 2023.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.