Full Text
<html>
<head>
<title>Federal Register, Volume 87 Issue 242 (Monday, December 19, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 242 (Monday, December 19, 2022)]
[Notices]
[Pages 77591-77593]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-27461]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP23-22-000]
Great Lakes Gas Transmission Limited Partnership; Notice of
Application and Establishing Intervention Deadline
Take notice that on December 8, 2022, Great Lakes Gas Transmission
Limited Partnership (Great Lakes), 700 Louisiana Street, Suite 1300,
Houston, Texas 77002-2700, filed in the above referenced docket, an
application under section 7(b) of the Natural Gas Act (NGA), and Part
157 of the Commission's regulations requesting authorization to
temporarily abandon a portion of its certificated horsepower at its
Compressor Station No. 1 located near St. Vincent, Minnesota, and to
temporarily abandon the associated system design capacity from Great
Lakes' point of receipt at Emerson in Kittson County, Minnesota, to its
point of delivery at Fortune Lake in Iron County, Michigan.
More specifically, Great Lakes requests to temporarily abandon, for
up to 36 months, the certificated horsepower of Station No. 1 from
32,330 HP to 15,830 HP and reduce the associated design capacity from
2,049 MDth/d to 1,905 MDth/d in the summer (144 MDth/d) and from 2,132
MDth/d to 1,947 MDth/d in the winter (185 MDth/d) from Great Lakes'
point of receipt at Emerson in Kittson County, Minnesota, to its point
of delivery at Fortune Lake in Iron County, Michigan, all as more fully
set forth in the application which is on file with the Commission and
open to public inspection.
In its application, Great Lakes states that the temporary
abandonments will have no impact on service to Great Lakes' shippers
because the capacity being abandoned is unsubscribed and the HP being
abandoned has not been used by Great Lakes for deliverability since
2018-2019. Great Lakes also states that these temporary abandonments
will allow Great Lakes time for an analysis of long-term needs for this
capacity versus the cost of repair or replacement of certain compressor
units on its system.
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (<a href="http://www.ferc.gov">http://www.ferc.gov</a>) using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room, due to the proclamation declaring a National Emergency
concerning the Novel Coronavirus Disease (COVID-19), issued by the
President on March 13, 2020. For assistance, contact FERC at
<a href="/cdn-cgi/l/email-protection#d3959681909cbdbfbabdb680a6a3a3bca1a793b5b6a1b0fdb4bca5"><span class="__cf_email__" data-cfemail="b8fefdeafbf7d6d4d1d6ddebcdc8c8d7caccf8deddcadb96dfd7ce">[email protected]</span></a> or call toll-free, (886) 208-3676 or TTY,
(202) 502-8659.
Any questions regarding this prior notice request should be
directed to David A. Alonzo, Manager, Project Authorizations, Great
Lakes Gas Transmission Limited Partnership, 700 Louisiana Street, Suite
1300, Houston, Texas 77002-2700, at (832) 320-5477, or by email to
<a href="/cdn-cgi/l/email-protection#462227302f2219272a29283c2906322523282334213f6825292b"><span class="__cf_email__" data-cfemail="bcd8ddcad5d8e3ddd0d3d2c6d3fcc8dfd9d2d9cedbc592dfd3d1">[email protected]</span></a>.
Pursuant to Section 157.9 of the Commission's Rules of Practice and
Procedure,\1\ within 90 days of this Notice the Commission staff will
either: complete its environmental review and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or environmental
assessment (EA) for this proposal. The filing of an EA in the
Commission's public record for this proceeding or the issuance of a
Notice of Schedule for Environmental Review will serve to notify
federal and state agencies of the timing for the completion of all
necessary reviews, and the subsequent need to complete all federal
authorizations within 90 days of
[[Page 77592]]
the date of issuance of the Commission staff's FEIS or EA.
---------------------------------------------------------------------------
\1\ 18 CFR (Code of Federal Regulations) 157.9.
---------------------------------------------------------------------------
Public Participation
There are three ways to become involved in the Commission's review
of this project: you can file a protest to the project, you can file a
motion to intervene in the proceeding, and you can file comments on the
project. There is no fee or cost for filing protests, motions to
intervene, or comments. The deadline for filing protests, motions to
intervene, and comments is 5:00 p.m. Eastern Time on January 3, 2023.
How to file protests, motions to intervene, and comments is explained
below.
Protests
Pursuant to section 157.205 of the Commission's regulations under
the NGA,\2\ any person \3\ or the Commission's staff may file a protest
to the request. If no protest is filed within the time allowed or if a
protest is filed and then withdrawn within 30 days after the allowed
time for filing a protest, the proposed activity shall be deemed to be
authorized effective the day after the time allowed for protest. If a
protest is filed and not withdrawn within 30 days after the time
allowed for filing a protest, the instant request for authorization
will be considered by the Commission.
---------------------------------------------------------------------------
\2\ 18 CFR 157.205.
\3\ Persons include individuals, organizations, businesses,
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------
Protests must comply with the requirements specified in section
157.205(e) of the Commission's regulations,\4\ and must be submitted by
the protest deadline, which is January 3, 2023. A protest may also
serve as a motion to intervene so long as the protestor states it also
seeks to be an intervenor.
---------------------------------------------------------------------------
\4\ 18 CFR 157.205(e).
---------------------------------------------------------------------------
Interventions
Any person has the option to file a motion to intervene in this
proceeding. Only intervenors have the right to request rehearing of
Commission orders issued in this proceeding and to subsequently
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
To intervene, you must submit a motion to intervene to the
Commission in accordance with Rule 214 of the Commission's Rules of
Practice and Procedure \5\ and the regulations under the NGA \6\ by the
intervention deadline for the project, which is January 3, 2023. As
described further in Rule 214, your motion to intervene must state, to
the extent known, your position regarding the proceeding, as well as
your interest in the proceeding. For an individual, this could include
your status as a landowner, ratepayer, resident of an impacted
community, or recreationist. You do not need to have property directly
impacted by the project in order to intervene. For more information
about motions to intervene, refer to the FERC website at <a href="https://www.ferc.gov/resources/guides/how-to/intervene.asp">https://www.ferc.gov/resources/guides/how-to/intervene.asp</a>.
---------------------------------------------------------------------------
\5\ 18 CFR 385.214.
\6\ 18 CFR 157.10.
---------------------------------------------------------------------------
All timely, unopposed motions to intervene are automatically
granted by operation of Rule 214(c)(1). Motions to intervene that are
filed after the intervention deadline are untimely and may be denied.
Any late-filed motion to intervene must show good cause for being late
and must explain why the time limitation should be waived and provide
justification by reference to factors set forth in Rule 214(d) of the
Commission's Rules and Regulations. A person obtaining party status
will be placed on the service list maintained by the Secretary of the
Commission and will receive copies (paper or electronic) of all
documents filed by the applicant and by all other parties.
Comments
Any person wishing to comment on the project may do so. The
Commission considers all comments received about the project in
determining the appropriate action to be taken. To ensure that your
comments are timely and properly recorded, please submit your comments
on or before January 3, 2023. The filing of a comment alone will not
serve to make the filer a party to the proceeding. To become a party,
you must intervene in the proceeding.
How To File Protests, Interventions, and Comments
There are two ways to submit protests, motions to intervene, and
comments. In both instances, please reference the Project docket number
CP23-22-000 in your submission:
(1) You may file your protest, motion to intervene, and comments by
using the Commission's eFiling feature, which is located on the
Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the link to Documents and
Filings. New eFiling users must first create an account by clicking on
``eRegister.'' You will be asked to select the type of filing you are
making; first select ``General'' and then select ``Protest'',
``Intervention'', or ``Comment on a Filing''; or \7\
---------------------------------------------------------------------------
\7\ Additionally, you may file your comments electronically by
using the eComment feature, which is located on the Commission's
website at <a href="http://www.ferc.gov">www.ferc.gov</a> under the link to Documents and Filings.
Using eComment is an easy method for interested persons to submit
brief, text-only comments on a project.
---------------------------------------------------------------------------
(2) You can file a paper copy of your submission by mailing it to
the address below. Your submission must reference the Project docket
number CP23-22-000.
To mail via USPS, use the following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426.
To mail via any other courier, use the following address: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852.
The Commission encourages electronic filing of submissions (option
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or <a href="/cdn-cgi/l/email-protection" class="__cf_email__" data-cfemail="4a0c2f382905242623242f193f3a3a25383e0a2c2f3829642d253c">[email protected]</a>.
Protests and motions to intervene must be served on the applicant
either by mail at: David A. Alonzo, Manager, Project Authorizations,
Great Lakes Gas Transmission Limited Partnership, 700 Louisiana Street,
Suite 1300, Houston, Texas 77002-2700, or email (with a link to the
document) at: <a href="/cdn-cgi/l/email-protection#f79396819e93a8969b98998d98b7839492999285908ed994989a"><span class="__cf_email__" data-cfemail="8aeeebfce3eed5ebe6e5e4f0e5cafee9efe4eff8edf3a4e9e5e7">[email protected]</span></a>. Any subsequent submissions by
an intervenor must be served on the applicant and all other parties to
the proceeding. Contact information for parties can be downloaded from
the service list at the eService link on FERC Online.
Tracking the Proceeding
Throughout the proceeding, additional information about the project
will be available from the Commission's Office of External Affairs, at
(866) 208-FERC, or on the FERC website at <a href="http://www.ferc.gov">www.ferc.gov</a> using the
``eLibrary'' link as described above. The eLibrary link also provides
access to the texts of all formal documents issued by the Commission,
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. For more information and to register, go to
<a href="http://www.ferc.gov/docs-filing/esubscription.asp">www.ferc.gov/docs-filing/esubscription.asp</a>.
[[Page 77593]]
Dated: December 13, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-27461 Filed 12-16-22; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on December 19, 2022.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.